Sr. No. Tasks/Activity Parcentageof Actual Work Done (As on date of the Certificate) 9 Staircases, lifls Wells And Lobbies at eAch Foor level Overhead and 0 00 Underground Water Tanks 10 External plumbing and external plaster, elevation,completion of terraces with 0 00 waterproofing of the Building/wing 11 Instellation of Lifts, water pumps, Fire Fighting fittings and Equipment as oer 0 00 CFO NOC, Electricalfittings, mechanical eguipment, compl1ance to conditions of envitonnment/CRZ NOC, Finishingto entrance lobby/s. plinth protection,paving of areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale Any other activities. Layout/Building/Wing Number: BLOCK BWING B1 Sr. No. Tasks/Activity Percentage of Actual Work Done (Ason date of the Certificate) (1) (2) (3) 1 Excavation 100.00 Basements (f any) 100 00 3 Podiums (if any) 100.00 Plinth, 100.00 Stilt Floor 50 00 Slabs of Super Structure 0.00 7 Internal walls, Internal plaster, Floorings, Floors and windows within 0.00 Flats/Premises Sanitary Fitting within the FlatPremises 0.00 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 0.00 Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 0.00 |waterproofing of the Building/wing. 11 |Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, complianceto Conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing,Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Anyother activities. Layout/Building/Wing Number: BLOCK BWING B2 Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3 Excavation 100.00 Basements (if any) 100.00 3 Podiums (if any) 100.00 Plinth 100.00 5 Stilt Floor 50.00 |Slabsof Super Structure 0.00 7 Internal walls, Internal plaster, Floorings, Floors and windows within 0.00 Flats/Premises 8 Sanitary Fitting within the Flat/Premises 0.00 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 0.00 |Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 0.00 waterproofing ofthe Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of lareas appurtenant to Building/Wing, Compound Walland all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Layout/Building/Wing Number: BLOCK CWING C1 Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) Page 2 of 4 Sr. No. Tasks/Activity Porcontage of Actual Work Done (Ason date of tho Certificate) 9 00 Excavaton Basemets (if any) Podums (fany) 0 00 Plinth Stilt Floor 000 000 Slabsof Super Structure 7 Internal walls, Internal plaster, Floorings, Floors and windows witlhin 000 Flats Premises 0.00 Santary Fting within theFlat/Promises 0.00 Staircases, lifts Wells and Lobbios at oach Floor levol Overhead and Underground Water Tanks External plumbing and external plaster, elovation, complotion of terracos with 0.00 10 waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Filtings and Equipmont as per CFO NOC, Electrncal fittings, mechanical equipment, compliance to cond1tions of environnment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,pavingof are as appurtenant to Build1ng/Wing. Compound Wall and all other requiroments as may be required to conmplete project as per specifications in agreemont of Sale. Any other activities. Layout/Building Wing Number: BLOCK CWING C2 Percentage of Actual Work Sr. No. Tasks/Activity Done (As on date of the Certificate) (1) (2) (3) 0.00 Excavation Basements (if any) 3 Podiums (if any) 4 Plinth. 0.00 0.00 5 Stilt Floor Slabs of Super Structure 0.00 7 Internal walls. Internal plaster, Floorings, Floors and windows within 0.00 Flats/Premises Santary Fitting within the FlatVPremises 0.00 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 0.00 Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 0.00 waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC. Electrical fittings, mechanical equipment, compliance to conditions of environmen/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Page 3 of 4 Works) in respect of Registered Table B- Common Areas (Internal and External Development Phase /Project Number) Percentago of Actual Details Common areas and facilitles Proposed Sr.No (Yos / No) Work Done (As on date of the Certiflcate) (4) (5) (2) (3) (1) Yes 0.00 1 Internal Roads &Footpaths Yes 0.00 2 Water Supply Yes 0.00 3 Sewerage (Chamber, Lines, Septic Tank,STP) Yes 0.00 4 Storm Water Drains Yes 0.00 5 Landscaping &Tree Planting 0.00 Yes 6 Street Lighting No 7 Community Buildings No Sullage Water Treatment And Disposal Of Sewage And No Gold Waste Management And Disposal Yes 0.00 Walcr conservation /Rain water harvesting 0.00 Yes 11 Energy managemcnt 0.00 Yes 12 |Fire protection and fire safety requirements 0.00 station Yes 3 Electrical meter room, sub-station, receiving 0.00 Space Yes j4 |Aggregate area of recreationai Üpen 0.00 Yes 15 Open Parking NG 16 Yours Faithfully/ ARCHITECTL6s Reg. MANOJ KALA CAJa6 Sigrature & Name (INBLOCK LETTERS)of L.S/Architect i License iNo: CAi9M/ 19597i Date of Certificate: Agreed and accepted by: Signature of Promoter Name: Gopal BalaprasadAjme Date: Page 4 of 4