Annexure A FORM 1 ISee Regulation 3] ARCHITECT'S CERTIFICATE ('1'o bc submittr)d at the timc of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Dale. 10-04-2024 To, SUNRISE CONSTRUCTIONS, BLOCK NO 3 AND 4, GLOBAL AVENUE, BESIDE MUNICIPAL CORPORATION MARKET, PAITHAN GATE AREA, AURANGABAD Subject: Certificate of Percentage of Completion of Construction Work of SUNRISE ELITE having MahaRERA Registration Number P51500055264 being developed by SUNRISE CONSTRUCTIONS. Sir | / We have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of SUNRISE ELITE having MahaRERA Registration Number P51s00055254 being developed by SUNRISE CONSTRUCTIONS tsased on the Site Inspection, with respect to the Layout / each Building/Wing of the ioresaiO Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the BuildingAruing of the Real Estate Project under MahaRERA is as per Table-A herern below. The percentage of work executed with respect to each of the activity of entire Phase rs detailed in Table-B TABLE-A Layout i Bullding / Wing Number for Sunrise Elite s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the 10001 X number of Baser and Plinth 50% {Iun,b,e[-_o,f P-o,qiq!! slll_Elo_ol _ X numper of Slabs of Super Q!rycture t 0o/o lnternal walls, lnternal Plaster, Floorings within 0o/o Flats/Premises. Doors and Windows to each of the FlaUPremrses 7 Sanitary Fittings within the FlaVPremises, Electrical 00k 8 Fittinqs within the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 00 --l o The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of Iifts, water pumps, Fire Fighting Fittings 00k and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to L Obtain Occupation /Completion Certificate TABLE.B Common Areas (lnternal & External Development Works) for Sunrise Elite S. Common Areas & Facilities Proposed Percentage of Details No. (Yes / NO) actua I Work Done (As on date of Certificate) 1 (3) (4) 1 lnternal Roads & Footpaths . No NA 2. Water Conservation, Rain water Yes 0 Rain Water Harvesting Harvesting As Per Norms 3 Energy management No NA 4 Fire Protection And Fire Safety Yes 0 As Per Norms Requirements: 5 Electrical Meter Room. Sub- Yes 0 As Per MSEB Norms Station, Receiving Station : 6 Aggregate area of recreational No NA Open Space : 7 Open Parkinq . Yes 0 As Per Drawing 8. Water Suoolv : Yes 0 From Bore-Well q Sewerage (Chamber, Lines, Yes 0 Drainage Line Till Septic Tank . STP) : Corporation Line 10. Storm Water Drains l No NA 11. Landsca ping a free Ptjniing No NA 12. Street Liohtino : No 13 Communitv Buildinos : No NA 14 Others Option to Add more No NA Yours faithfully, For IMPACT DESIGN & ASSOCIATES, ARCH, HARES SIDDIQUI Signature & Name (lN BLOCK LETTERS) of Land Surveyor / Architect License Number CA / 2003 / 30793 Agreed & Accepted by: aun$sE coNsrRucrloN I t' P Signature of Promoter PAR'I.FP Name: SUNRISE CONSTRUCTIONS Dale. 10-04-2024