-t I Annexure A FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 15/05/2025 To, M/S. KRPS Properties 2nd Floor, RK Tower, Shivaji Nagar Road,Beside Water Tank, Chh. Sambhajinagar,43l 005 Subject : Certificate of percentage of Work of completion of construction work of Adinath Aangan Phase-01 situated at Gut No. 95/P, Deolai, Chh. Sambhajinagar.having MahaRERA Registration Number P51500077736 being developed by M/S KRPS Properties Sir, lA/t/e Ar. SAMEER AUSEKAR have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of completion of Construction Work of Adinath Aangan Phase-O1 situated at Gut No. 95/P, Deolai, Ghh. Sambhajinagar. having MahaRERA Registration Number (P51500077736, being developed by M/S KRPS Properties) Based on Site lnspection,with respect to Layout / each of the BuildingMing of the aforesaid Real Estate Project I certify that as on the date of this certificate, the Percentage of Work done for each of the buildingMing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A lteruuanY To MARcH 2o2sl LayouUBuildingMling Number: BLOGK A R.H. 01 TO R.H. 04 Sr. No Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) 12) (3) 1 Excavation 100.0( 2 Basements (if any) 3 Podiums (if any) 4 01 Plinth, 100.0( 5 Stilt Floor 6 03 Slabs of Super Structure 100.0( lrrluilral walls, lrrtefiral plaster, Floorlngs, Floors and wlndows wlllrll'r Flats/pterf[ses 100.0( 8 Sanitary Fitting within the FlaUPremises 80.0( I Qtaircases, lifts Wells and Lobbies at each Floor level Overhead and Underground 80.0( Water Tanks Nishigandh-C,DishaSrushti,Opp.Hotel Atithi,Rananagar;JalnaRd,Chh.Sambhajinagar,Maharashtra-431005q\+91 240 2451616Xinfo@samilarchitects.com Table B - Common Areas (lnternal and External Development Works) in respect of Registered Phase / Project Number) (JANUARY TO MARGH 2025) Sr.No Gommon areas and facilities Proposed Percentage of Actual Details (Yes / No) Work Done (As on date of the Certificate) (1) (2) (3) (4) (5) 1 lnternal Roads & Footpaths Yes 0.00 As per drawings by Consultants 2 Water Supply Yes 0.00 By Borewell 3 Sewerage (Chamber, Lines, Septic Tank , STP) Yes 0.00 As per drawings by Consultants 4 Storm Water Drains No 5 Landscaping & Tree Planting Yes 0.00 As per drawings by Consultants 6 Street Lighting Yes 0.00 As per drawings bv Consultants 7 Community Buildinqs No 8 Treatment And Disposal Of Sewage And Sullage Water No I Solid Waste Management And Disposal No 10 Water conservation /Rain water harvesting Yes 0.00 As per drawings by Consultants 11 Energy managemcnt No 12 Fire protection and fire safety requirements No 13 Electrical meter room, sub-station, receiving station Yes 0.00 As per drawings by Consultants 14 Aggregate area of recreational Open Space Yes 0.00 As per drawings by Consultants 15 Ooen Parkino No 16 Others. Compound wall & Entrance Gate Yes 0.00 As per drawings by Consultants Overall Project Completion is for internal & externa! development work. Yours Faithfully t UD' * rL SEKAR Signature & N)me (lN BLOCK 49 .S/ Architect ( License No: CA-95/19301) Date of Certificate: Agreed and accepted by: Signature of Promoter Namc: M/6. KRPE Propcrtics Date: