(ON ARCHITECTS LETTERHEAD) Annexure A FORM 1 [See Regulation 3] ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date: 31/03/2026 To, M/s. Aakash Ganga Developers, 102, Veer Shanti, Kranti Chowk, Chh. Sambhajinagar (Aurangabad) – 431005. Subject: Certificate of Percentage of Completion of Construction Work of Project named as Aakash Ganga – Phase II having MahaRERA Registration No P51500054973 being developed by Aakash Ganga Developers. (QTR Jan to March 2026) Sir, I, Satyam B. Jadhav, have undertaken assignment as an Architect of Certifying Percentage of Completion of Construction Work of Project named as Aakash Ganga – Phase II having MahaRERA Registration No P51500054973 being developed by Aakash Ganga Developers situated at Plot No. / Gut No. 20(P), Nakshatrawadi, Chh. Sambhajinagar (Aurangabad), Maharashtra – 431101. Based on the Site Inspection, with respect to the Layout / each of Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A Building Name: Aakash Ganga – Phase II Percentage of Actual Work S. Done Tasks / Activity No. (As on date of the (2) (1) Certificate) (3) 1. Excavation 100% 2. Basements (if any) NA 3. Podiums (if any) NA 4. Plinth 100% 5. Stilt Floor NA 6. Slabs of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors, windows 100% within Flats / Premises 8. Sanitary Fittings within Flats / Premises 100% 9. Staircases, Lift Wells & Lobbies at each Floor Level 100% Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, Completion of Terraces, with waterproofing of the 100% Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to NA Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale. Any other activivites. TABLE-B Common Areas (Internal & External Development Works) in respect of the Aakash Ganga –Phase II, MahaRERA No: P51500054973 Percentage of actual Work S. Proposed Common Areas & Facilities Done Details No. (Yes / No) (2) (As on date of Certificate) (5) (1) (3) (4) 1. Internal Roads & Footpaths Yes 100% Completed 2. Water Supply Through Yes 99% Borewell 3. Sewerage (Chamber, Lines, Septic 99% Through Yes Tank, STP) Septic Tank 4. Strom Water Drains No NA 5. Landscaping & Tree Planting Only Tree Yes 99% Plantation 6. Street Lighting Only on DP Yes 99% Road 7. Community Buildings No NA 8. Treatment & Disposal of Sewage No NA and Sullage Water 9. Solid Waste Management & No NA Disposal 10. Water Conservation / Rain Water No NA Harvesting 11. Energy Management No NA 12. Fire Protection & Fire Safety No NA requirements 13. Electrical Meter Room, Sub- No NA Station, Receiving Station 14. Aggregate area of recreational No NA Open Space 15. Open Parking Yes NA Yours Faithfully, SATYAM B. JADHAV (Architect) License/Registration Number (CA/2020/119082) Address: 18, Jalna Road, Aurangabad. Agreed & Accepted by: Signature of Promoter For & On behalf of M/s.Aakash Ganga Developers Name: Mr.Kiran Patil (Partner/Authorized Signatory) Date: 31/03/2026