Annexure A FORT 1 MnNssnl Besrsx AACXITECTS & II'TENIOF DESIGNEB [See Regulation 3] ARCHITECT'S CERTIFICATE Cfo be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Dale:25-10-2023 To, I{ARAYANII BUILDCREATION PVT. LTD. BAHETI COMPLEX, KELI BAZAR, AURANGABAD 43IOOI Subject: Certificate of Percentage of Completion of Construc{ion Work of HRlt SKY CITY ELITE having MahaRERA Registration Number NEW REGISTRATION being developed by NARAYANII BUILDCREATIOI{ PVT. LTD. Sir, I / We T,s. MANGGAL ARCHITECT & INTERIOR DESIGNORS have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Conslruc{ion Work of HRlt SKY CITY ELITE having MahaREM Registration Number iIEW REGISTRATION being developed by NARAYAI{II BUILDCREATION PVT. LTO. Based on the Site Inspec{ion, with respecl to the Layout / each BuildingMing of the aforesaid Real Estate P@ect, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wng of the Real Estate Projec{ under MahaRERA is as per Table-A herein below. The percentage of work executed with resped to each of the activity of entire Phase is detailed in Table-B. TABLE.A FOR THE ROW HOUSES 1{O RH.I TO RH-3{ s. Tasks / Activity Percentage of Actual UYor* o. Done (As on date of the Certificatel (1) 12t (3) 1. Excavation '100o/o 2. Basements (if any) 3. Podiums (if any) 4. Plinth 'looo/o 5. Stilt Floor lOOo/o 6. Slab of Super Struclure 20o/o 7. lntemal Walls, lntemal Plasler, Floorings, Doors, windows within Flats / Premises 1 8. Sanitarv Fittinos within Flats / Premises 9. Staircases, Lift Wells & Lobbies at each Floor Level Overhead and Underqround Water Tanks '10. Extemal Plumbing & Extemal Plaster, Elevation, Completion of Tenaces, with waterproofing of the Buildinq / Winq 't1. lnstallation of Lifls, Water Pumps, F.ire#ighting-F#ings a@, Electrical Fittings, Ueceanicafeqopments, Comptianee-to-conditiens-ef Esvir€tftment- / GRZ-i{O€, Finishing to Entrance Lobby/s, Plinth Protec{ion, Paving of Areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to complete Pro.iect as per specifications to Agreement of Sale, Any other Ac{ivity TABLE.B FOR THE ROW HOUSES ilO I TO,l4 AND 57 TO 61 S. Common Areas & Facilities Proposed Percentage of Details No. (Yes / NO) actual Work Done (As on date of Certificate) (1) t2l (3) (4) {51 1. lntemal Roads & Footpaths YES 20o/o INTERNAL PROJECT ROADS 2. Water Suoolv YES FROM BOREWELL 3. Sewerage (Chamber, Lines, YES 0 DBAINAGE LINE Seotic Tank. STP) 4. Strom Water Drains NO N.A. 5. Landscaping & Tree Planting YES 0 INTERNAL PROJECT TREE PLANTATION 6. Street Lighting YES INTERNAL PROJECT STREET LIGHTS 7. Community Buildings NO N.A. 8. Treatment & Disposal of Sewage NO N.A, and Sullaoe Water L Solid Waste Management & YES 0 AS PER NORMS Disposal 10. Water Conservation / Rain Water YES 0 RAIN WATER Harvesting HARVESTING AS PER NORMS 11. Enerqy Manaqement NO N.A. 12. Fire Proteciion & Fire Safety NO requirements 13. Elec{rical Meter Room, SuF YES 0 AS PER MSEB Station. Receivinq Station NORMS 14. Others (Option to Add more) NO N.A. 2 IiPromod vitnooo ltotole cd d.D6.d2t{,9f;6r -'ilEit?i',onls.r6"- Yours faithfully, FOR TAiIGGAL ARCHITECT & IiITERIOR DESIGI{ORS ARCH. PRAMOD NARALE Signature & Name of Land Surveyor / Architec{ License Number lCN20'l1l5i,82A1 Agreed & Accepted by: MRAYANII BUITD CREATION PVT. LTO. *za-,:.> ( ,4V' DINECTOR Signature of Promoler Name: NARAYANU BUILDCREATIOil PVT. LTD. Date: 25-10-2023 3