Amol Annexure - B Kshirsagar Architectural Planner, FORM - 2 Consulting Engineer & [See Regulation 3] Valuer ENG IN EER'5 CERTIFICATE (To be submitted at the time of Registration of ongoing project and for withdrawal of Money from Designated Ba nk Account) Date: 78/07 /2024 To, The Jagrutsara Realtors LLp, Block No.11, Narayan Plaza, Towen Center, CIDCO Cannaught Place. Chhatrapati Sa mbhajinagar subject:certificate of cost lncurred for Development of ,,signature 27,' having MahaRERA Registration Number P51500054759 being Developed by Jagrutsara Realtors LLp. Sir, t. I / We Er. Amol Kshirsagar have undertaken assignment of certifying Estimated cost for "signature 27" having MahaRERA Registration Number p51500054759 being Developed by Jagrutsara Realtors LLp. 2. We have estimated the cost of Civil, MEP and Allied Works required for completion of the apartments & proportionate completion of internal & external works of the project as per the specifications mentioned in the Agreement of sale. our estimated cost calculations are based on the Drawings/Plans made available to us for the project under Reference by the Developers / Consultants.'The Schedule of ltems & euantity required for the entire work as calculated by Er. Amol irsagar Quantity surveyor* appointed by the Developer/Engineer, the assumption of the cost of , labour & other inputs made by the Developer, and the site lnspection carried out by us to in / confirm the above analysis given to us. 3. we estimate Total Estimated cost of completion of the aforesaid project mentioned under ref, at Rs. 6,34,44,880/- (Total of Table A & B) at the time of Registration. The estimated rotal Cost Project is with reference to the civil, MEp & Allied works completion of the apartments & completion of internal & external works, as per the specifications mentioned in the Agreeme of sale & for the purpose of obtaininB occupation certificate completion certificate / for the Buildi Development from the chhtrapati Sambhajinagar Municipal corporation chhatrapati Sambhaji ing the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Esti incurred till date is calculates to Rs. 1,84,69,061/- (Total of Table A & B). The Amount of E.stima .-o.r'..1h,e..b.?.r i9.9f. lnpu!. ma!.e. rialr,1. r.e.ry. r-qes-.used & at N oY+ilP 6t.9{In eJo !9.,r,.s FI Nathprangan,Garkheda, Ghhatrapati Sambhajinagar Mob. : 09960669921 5. The Barance cost of compretion of the civir, MEp & Aried works for compretion of ,loro*.n::".comptetion of internat & externat *"rnr, mentioned n iAgreement of sare, of the aforesaid project ilT,T-":ji ", ;.;:;;il;; is estimated at Rs. 4,49,75,819/_ (Totar Table A & B). of 6 r certify that the cost of civir, MEp & A,ied Work for apartments & proportionate internar & externar works, as per the specifications mentioned in Agreement of sare, of the aforesaid project completed on the date of this certificate is as as given in Table A & B below: TABLE - A Project Signature 27, Block A and Block B Row Houses/Row Bungalows Total Estimated cost ot auildin, winS Plotted Development as on date of Registraiion Cost incurred as on d.t" of C".tifi.ate ^ayouvis Work Done in percentage (as percentage of Estimated Balance cost to Uu in.rr"a [ (U.*J onTrtilffi Cost incurred on edditionaV Extra ttems not included in the Estimated Cost (Table_c) lrnternal & External Development Works in respect of Registered phase S. No. Amount (in Rs,) 1. Total Estimated Cost of tntern-at & fxtern-at Rs.56,44,030=00 Development Works including amenities & facilities I in a: on d 2. :h:Svout LU5L rLurreO aS On Oate ol Certifi.etp ?i/i(:,/)^1^ Rs.11,28,806=00 3. L0% 4. Batance cost to u" in.*Ea {(o*"d onEtiffi Rs.45,15,224=00 5. Cost incurred on Additionil/Etra ttems noiincluiEi in the Estimated Cost (Table-C) Yours faithfully, siBnature & Name Er. amot Kstrirsagfr)/\ffi J [Not less thon Bochelor,s Degree Holder orLquivotent os- per e Actl Local Authority License Number (if applicable) Agreed & Acc"ot"d N, .'NcP #,(u Signature of Prdrhoter Name: Jagrutsara Realtors LLp Date: 78/07 /2024 ek, 3ou.-uo} l The scope of work is to comprete Registered Rear Estate project as per drawings approved from time to time as per specifications mentioned in the Agreement to Sale. 2' l*l Quantity survey can be done by the office of Engineer or can be done by an independent Quantity Surveyor, who's Certificate of euantity Calculated, can be relied up on by Engineer. ln case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) & in case quantity are being calculated by office of Engineer, the name of person in the office of Engineer, who is responsibre for the quantity carcurated shourd be mentioned at the place marked (*). 3 (**) Balance cost to be incurred (4) may vary from difference between Total Estimated cost (1) & actual cost incurred (2) due to deviation in quantity required / escalation of cost etc. As this is an Estimated cost any deviation quantity required for the Development project of Real Estate will result in an amendment ofthe cost incurred / to be incurred. 4. All components of work with specifications are indicative & not exhaustive 5' Please specify if there are any deviations / quarifications. Exampre: Any deviation in input material used from specifications in Agreement of Sale. TABTE - C List of Extra / Additional / Deleted ttems considered in the Cost (Which were not parts of the original Estimate of TotalCost) tist of Extra / Additional / Deleted ttems '.+ I q a(,,1 KU Ys