FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of 0ngoing Project and for withdrawal of Money from Designated Account BuildingMing wise) Date: 07/08/2023 To M/S SAMARTH INFRA, 8.402, PLOT-o7, HARE RAMA HARE KRISHNA SOCIETY, MIDC CHIKALTHANA, AURANGABAD. Subject Certificate of Percentage of Completion of Construction Work of project ShivSamarth Residency Building(s)/_ Wing(s) [To be registered under Maha-Rera] being developed by M/S SAMARTH INFRA. Sir, We Samil Architects have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of the of the Project ShivSamarth Residency To be registered under Maha-Rera [To be registered under Maha-Rera] being developed by M/S SAMARTH INFRA. Based on Site lnspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the buildingAffing of the Real Estate Project as registered vide number [To be registered under Maha- Reral is as per table A herein below. The percentage of the work executed with respect to each of the major activity of the Shiv Samarth Residency project and Overall Percentage of work done with respect to each Building is detailed in the Table B. Table A (To be prepared separately for each Building Ming of the Project) ROW HOUSES A73 TO A9O Percentage of Sr. No Tasks /Activity work done 1 Excavation 0% 2 1 Number of Plinth 0% ,i ti lrlrrnrher of Baserrrent Flonr il% 4 0 Number of Stilt Floor 0Yo 5 2 Number of Slabs of Super Structure 0Yo Page | 1 Nishigandh - C, Disha Srushti, Opp. HotelAtithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Call - +91 240 2451616 E - Mail - info@samilarchitects.com, Web Site - www.samilarchitecs.com lnternal walls, lnternal Plaster, Floorings within Flats/Premises, o 00% Doors and Windows to each of the Flat/Premises Sanitary Fittings within the FlaUPremises, Electrical Fittings within 7 00% the FlaUPremises Staircases, Lifts Wells and Lobbies at each Floor level connecting 8 00% Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion I 00% of terraces with waterproofing of the Building/Wing, lnstallation of l+fts, water pumps, @ @, Electricalfittings to Common Areas, envireflmen+JeRz-N€C, f n s h n g to e n tra n ce o b by/s, plin{h i i i I 10 00% prot€€+io+, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to 0btain Occupation /Completion Certificate Occupation /Completion Certificate ROW HOUSES A91 TO A99 Percentage of Sr. No Tasks /Activity work done 1 Excavation 0o/o 2 1 Number of Plinth 0Yo 3 0 Number of Basement Floor 0Yo 4 0 Number of Stilt Floor 0 o/o 5 2 Number of Slabs of Super Structure 0Yo lnternal walls, lnternal Plaster, Floorings within Flats/Premises, 6 00% Doors and Windows to each of the Flat/Premises Sanitary Fittings within the FlaUPremises, Electrical Fittings within 7 00% the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level connecting 8 00% Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion I 00% of terraces with waterproofing of the Building/Wing, lnstallation of lifts, waterpumps, ffi 10 @, EleCmcalfittngs t0 U0mmOn Areas, 00% eny+reJqfien++CRz-N€e, F n s h n g to e ntra n ce obby/s, plinth i i i I Pagel2 Nishigandh - C, Disha Srushti, Opp. Hotel Atithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Call - +91 240 2451616 E - Mail - info@samilarchitects.com, Web Site - www.samilarchitecs.com prote€tie+, paving of areas appurtenant to BuildingAffing, Compound Walland all other requirements as may be required to 0btai n Occu pation /Co mpletion Certificate 0ccu patio n /Completion Certificate ROW HOUSES A55 TO A72 Percentage of Sr. No Tasks /Activity work done 1 Excavation 1Yo 2 1 Number of PIinth 0Yo 3 0 Number of Basement Floor 0Yo 4 0 Number of Stilt Floor 0Yo 5 2 Number of Slabs of Super Structure 0 o/o lnternal walls, lnternal Plaster, Floorings within Flats/Premises, b 00% Doors and Windows to each of the FlatiPremises Sanitary Fittings within the FlaUPremises, Electrical Fittings within 7 00% the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level connecting 8 00% Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion I 00% of terraces with waterproofing of the BuildingMing, lnstallation of lifts, water pumps, @ @, Electricalfittings to Common Areas, 10 ffi, Finishing to entrance lobby/s, plinth 00% p+eteetie+, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtai n 0ccu pation /Completion Certificate Occu pation /Completion Certificate ROW HOUSES B()1 TO BO7 Sr. Percentage of Tasks /Activity No work done 1 Excavation 0% ') L 1 Number of Plinth 0% 3 0 lJrrmher nf flrcrment l-lnnr 0 1(, 4 0 Number of Stilt Floor 0% 5 2 Number of Slabs of Super Structure 0Yo Page | 3 Nishigandh - C, Disha Srushti, Opp. HotelAtithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Call - +91 240 2451616 E - Mail - info@samilarchitects.com, Web Site - www.samilarchitecs.com lnternal walls, lnternal Plaster, Floorings within Flats/Premises, Doors 6 00% and Windows to each of the FlaUPremises Sanitary Fittings within the FlaUPremises, Electrical Fittings within the 7 00% FlaUPremises Staircases, Lifts Wells and Lobbies at each Floor level connecting 8 00% Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion of o 00% terraces with waterproofing of the BuildingMing, lnstallation of lifts, water pumps, asper+g+gg, Electricalfittings to Common Areas, ele€tre 10 ffi}NOC, Finishing to entrance lobby/s, pln+++eee+re+, paving of 00% areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate Occupation /Completion Certificate ROW HOUSES A37 TO A54 Percentage of Sr. No Tasks /Activity work done 1 Excavation 0Yo 2 1 Number of Plinth 0Yo 3 0 Number of Basement Floor 0Yo 4 0 Number of Stilt Floor 0% 5 2 Number of SIabs of Super Structure 0Yo lnternal walls, lnternal Plaster, Floorings within Flats/Premises, 6 00% Doors and Windows to each of the Flat/Premises Sanitary Fittings within the FlaUPremises, Electrical Fittings within 7 00% the FlaUPremises Staircases, Lifts Wells and Lobbies at each Floor level connecting 8 00% Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion I 00% of terraces with waterproofing of the BuildingMing, lnstallation of lifts, waterpumps, @ @, Electrical fittings to Common Areas, 10 00% envireffien++CRz-N€C, f n s h n g to e ntra n ce obby/s, plin{h i i i I protection, paving of areas appurtenant to BuildingiWing, Compound Wall and all other requirements as may be required to Page | 4 Nishigandh - C, Disha Srushti, Opp. Hotel Atithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Gall - +91 240 2451616 E - Mail - i$o@sa{nilqrchitects.com, Web Site - www.samilarchitecs.com Obtain Occupation /Completion Certificate 0ccupation /Com pletion Certificate ROW HOUSES AlOO TO A117 Percentage of work Sr. No Tasks /Activity done 1 Excavation 0Yo 2 1 Number of Plinth 0 o/o 3 0 Number of Basement Floor 0Yo 4 0 Number of Stilt Floor 0Yo 5 2 Number of Slabs of Super Structure 0Yo lnternal walls, lnternal Plaster, Floorings within o Flats/Premises, Doors and Windows to each of the 00% FlaUPremises Sanitary Fittings within the FlaUPremises, Electrical Fittings 7 00% within the FlaUPremises Staircases, Lifts Wells and Lobbies at each Floor level 8 connecting Staircases and Lifts, Overhead and Underground 00% Water Tanks The external plumbing and external plaster, elevation, I completion of terraces with waterproofing of the 00% BuildingMing, lnstallation of lifts, water pumps, @ @, Electrical fittings to Common Areas, , Finishing to entrance 10 00% lobby/s, pt+n+++e{ee+e+, paving of areas appurtenant to Building/Wing, Compound Wall and allother requirements as may be required to Obtain Occupation /Completion Certificate 0ccupation /Completion Certificate ROW HOUSES A19 TO A36 Percentage of work Sr. No Tasks /Activity done I Excavation 0% ? { Number of Plinth 0% 3 0 Number of Basement Floor 0Yo Page | 5 Nishigandh - C, Disha Srushti, Opp. HotelAtithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Gall - +91 240 2451616 E - Mail - info@samllarchite-qts.cou, Web Site - www.samilarchitecs.com 4 0 Number of Stilt Floor 0% 5 2 Number of Slabs of Super Structure 0Yo lnternal walls, lnternal Plaster, Floorings within 6 Flats/Premises, Doors and Windows to each of the 00% Flat/Premises Sanitary Fittings within the FlaUPremises, Electrical Fittings 7 00% within the FlaUPremises Staircases, Lifts Wells and Lobbies at each Floor level 8 connecting Staircases and Lifts, Overhead and Underground 00% Water Tanks The external plumbing and external plaster, elevation, I completion of terraces with waterproofing of the 00% Building/Wing, lnstallation of lifts, water pumps, @ @, Electrical fittings to Common Areas, , Finishing to entrance 10 00% lobby/s, pt+n+++ege+re+, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Ce rtificate 0ccu pation /Com p letio n Ce rtifi cate ROW HOUSES A118 TO A135 Percentage of work Sr. No Tasks /Activity done 1 Excavation 0Yo 2 1 Number of PIinth 0Yo 3 0 Number of Basement Floor 0 o/o 4 0 Number of Stilt Floor 0Yo 5 2 Number of Slabs of Super Structure 0 o/o lnternal walls, lnternal Plaster, Floorings within 6 Flats/Premises, Doors and Windows to each of the 00% FlaUPremises Sanitary Fittings within the FlaUPremises, Electrical Fittings 7 00% within the FlaUPremises Staircases, Lifts Wells and Lobbies at each Floor level o tl connnntin6; Stairnannn and I iftn Ovarhnad and llndnr6lrorrnd 00 o/n Water Tanks Page | 6 Nishigandh - C, Disha Srushti, Opp. Hotel Atithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Call - +91 240 2451616 E - Mail - info@saf ilarcIritesls.cgn, Web Site - www.samilarchitecs.com The external plumbing and external plaster, elevation, I completion of terraces with waterproofing of the 00% BuildingMing, lnstallation of lifts, water pumps, @ @, Electricalfittings to Common Areas, , Finishing to entrance 10 00% lobby/s, plin++reg*re+, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate Occupation /Completion Certificate ROW HOUSES AO1 TO A18 Percentage of work Sr. No Tasks /Activity done 1 Excavation 0Yo 2 1 Number of PIinth 0Yo 3 0 Number of Basement Floor 0Yo 4 0 Number of Stilt Floor 0% 5 2 Number of SIabs of Super Structure 0 o/o lnternal walls, lnternal Plaster, Floorings within 6 Flats/Premises, Doors and Windows to each of the 00% FlaUPremises Sanitary Fittings within the FlaUPremises, Electrical Fittings 7 00% within the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level 8 connecting Staircases and Lifts, Overhead and Underground 00% Water Tanks The external plumbing and external plaster, elevation, I completion of terraces with waterproofing of the 00% BuildingMing, lnstallation of lifts, waterpumps, @ @, Electrical fittings to Common Areas, , Finishing to entrance 10 00% Iobby/s, pln+l++eee+ie+, paving of areas appurtenant to Rrrlldlngi\A/lng, C.nmpnrrnd \A/nll nnd sll nther rcrlrrlrpmpntg eg may be required to 0btain Occupation /Completion Certificate Occupation /Completion Certificate Page | 7 Nishigandh - C, Disha Srushti, Opp. HotelAtithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Call - +91 240 2451616 E - Mail - info@$${ilArcIilepl-q.agm, Web Site - www.samilarchitecs.com ROW HOUSES A136 TO A150 Percentage of work Sr. No Tasks /Activity done 1 Excavation 0Yo 2 1 Number of Plinth 0Yo 3 0 Number of Basement Floor 0 o/o 4 0 Number of Stilt Floor 0Yo 5 2 Number of Slabs of Super Structure 0Yo lnternal walls, lnternal Plaster, Floorings within 6 Flats/Premises, Doors and Windows to each of the 00% FlaUPremises Sanitary Fittings within the FlaUPremises, Electrical Fittings 7 00% within the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level 8 connecting Staircases and Lifts, Overhead and Underground 00% Water Tanks The external plumbing and external plaster, elevation, 9 completion of terraces with waterproofing of the 00% BuildingMing, lnstallation of lifts, water pumps, ffi @, Electrical fittings to Common Areas, , Finishing to entrance 10 00% lobby/s, ptin+n++eeem+, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate Occu pation /Completio n Certificate A1 BUILDING Percentage of work Sr. No Tasks /Activity done I Excavation 0o/o 1 0 Number of PIinth 0 o/o 3 0 Number of Basement Floor 0% 4 0 Number of Stilt Floor 0 olo 5 7 Number of Slabs of Super Structure 0Yo Page | 8 Nishigandh - C, Disha Srushti, Opp. Hotel Atithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Call - +91 240 2451616 E - Mail - info@samilarchitects.com, Web Site - www.samilarchitecs.com lnternal walls, lnternal Plaster, Floorings within 6 Flats/Premises, Doors and Windows to each of the 00% FlaUPremises Sanitary Fittings within the FlaUPremises, Electrical Fittings 7 00% within the FlaUPremises Staircases, Lifts Wells and Lobbies at each Floor level 8 connecting Staircases and Lifts, Overhead and Underground 00% Water Tanks The external plumbing and external plaster, elevation, o completion of terraces with waterproofing of the 00% Building/Wing, lnstallation of lifts, water pumps, ffi W, Electrical fittings to Common Areas, , finishing to entrance 10 00% lobby/s, pln+lA+eee+re+, paving of areas appurtenant to BuildingiWing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0ccu pation /Co m p letio n Certificate A2 BUILDING Percentage of work Sr. No Tasks /Activity done 1 Excavation 0Yo 2 0 Number of Plinth 0Yo 3 0 Number of Basement Floor 0Yo 4 0 Number of Stilt Floor 0 olo 5 7 Number of Slabs of Super Structure 0 o/o lnternal walls, lnternal Plaster, Floorings within 6 Flats/Premises, Doors and Windows to each of the 00% Flat/Premises Sanitary Fittings within the FlaUPremises, Electrical Fittings 7 00% within the FlaVPremises Staircases, Lifts Wells and Lobbies at each Floor level o connecting Staircases and Lifts, Overhead and Underground 00% Water Tanks The external plumbing and external plaster, elevation, o 00% completion of terraces with waterproofing of the Page | 9 Nishigandh - C, Disha Srushti, Opp. Hotel Atithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Gall - +91 240 2451616 E - Mail - i.nf--oiBsAflr-ilarchitects.com, Web Site - www.samilarchitecs.com BuildingMing, lnstallation of lifts, water pumps, @ @, Electrical fittings to Common Areas, , Finishing to entrance 10 00% lobby/s, p+*np+eeemn, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to 0btain Occupation /Completion Certificate Occu pation /Comp letion Certifi cate TABLE.B lnternal & External Development Yllorks in Respect of the entire Registered Phase Percentage Sr. Common areas and Proposed of Work Details No. Facilities, Amenities (Yes/No) done 1. lnternal Roads Yes 0o/o As per drawings by & Footpaths Consultants Water Supply As per drawings by 2. Yes 0o/o Consultants Sewerage (chamber, lines, 0o/o As per drawings by 3. Yes Consultants Septic Tank, STP) Storm Water Drains 0o/o As per drawings by 4. No Consultants Landscaping & Tree Planting 0o/o As per drawings by 5 Yes Consultants Aggregate Area Of 0o/o As per drawings by 6. Yes Recreational open Space Consultants Street Lighting 0o/o As per drawings by 7. Yes Consultants 8. Community Buildings No 0o/o Not Applicable Treatment and disposal 0o/o As per drawings by 9. Yes Consultants of sewage and sullage water Solid Waste management & As per drawings by 10. No Consultants Disposal ,t Water conservation, Rain AS per orawrngs Dy 11. Yes 0o/o Page | 10 Nishigandh - C, Disha Srushti, Opp. HotelAtithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Call - +91 240 2451616 E - Mail - info@samilarchitects.com, Web Site - www.samilarchitecs.com water harvesting Consultants Energy management As per drawings by 12. No. Consultants Fire protection and fire safety As per drawings by 13. No. Consultants requirements Electrical meter room. sub- 0o/o As per drawings by 14. Yes station, receiving station Consultants Others Compound Wall & As per drawings by 15 Yes Consultants Entrance Gate 0o/o Overall Project completion is 0.00% & 0.00% for internal & external development works. iti?'^i;fHSlfl Reg. No. CA-95/19301 Agreed & Accepted by, Name :- M/S SAMARTH INFRA Date:- Page | 11 Nishigandh - C, Disha Srushti, Opp. Hotel Atithi, Rana Nagar, Jalna Road, Aurangabad.- 431005 Call - +91 240 2451616 E - Mail - info@samila.rchitects.com, Web Site - www.samilarchitecs.com