Er. Balasaheb Devkate Diploma Civil Engg. Annexure - B FORM - 2 [See Regulatton 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for Withdrawa_l of Money from Designated Bank Account) Dale:02-01-2025 To, RIDDHI VIYAAN VENTURES, PLOT NO 40, SECTOR N-3, CIDCO, AURANGABAD Subject: Certificate of Cost lncurred for Development of ANUKUL having MahaRERA Registration Number P51500052898 being devetoped by RtDDHt VtyAAN VENTURES. (For Oct to Dec 2024 QTR) Sir, I / we Mr BALASAHEB DEVKATE have undertaken assignment of certifying Estimated cost p51500052898 being devetoped by lo1 fNUKUL having MahaREM Registration Number RIDDHI VIYAAN VENTURES. 1. we have estimated the cost of civil, MEp and Allied works required for completion of the apartments & proportionate completion of internal & external works of the Project as per the specifications mentioned in the Agreement of Sale. Our estimated cost calculatjons are based on the Drawings/Plans made available to us for the Project under Reference by the Developers / consultants. The schedule of ltems & euantity required for the entire work as calculated by Quantity Surveyor* appointed by the Developer/Engineer, the assumption of the cost of material, labour & other inputs made by the Developer, and the Site lnspection carried out by us to ascertain / confirm the above analysis given to us. 2. We estimate Total Estimated Cost of completion of the aforesaid Project mentioned under reference at Rs. 9,47,28,300/- (Total of Table A & B) at the time of Registration. The estimated Total Cost of Project is with reference to the Civil, MEp & Allied Works completion of the apartments & proportionate completion of internal & external works, as per the specifications mentioned in the Agreement of Sale & for the purpose of obtaining Occupation Certificate / Comptetion Certificate for the Building(s) / Wing(s) / Layout i Plotted Development from the CHHATRApATT SAMBHAJI NAGAR MUN|CIPAL CORPORATION CHHATMPATT SAMBHAJT NAGAR being the ptanning Authority under whose jurisdiction the aforesaid Project is being implemented. Er. Balasaheb Devkate Diploma Civil Engg. J, The Estimated Cost incuned till date is calculates to Rs. 2,84,1 8,4904(Total of Table A & B). The Amount of .Eslimetgd..QpsLl.D.c..u.r.9C.j.s-.qa!.c. Je!-e..C..9n.!he-.baSi9..aJ.inpu!.m.?.tCrie!9 1 j.c.-e..s-.q.se..C..&..v.n j.t.q_o..9!..-oJ.th999-!!e.m.c _s.e.Lv. 4. The Balance Cost of completion of the Civil, MEP & Allied Works for completion of Apartments & proportionate completion of internal & external works, as per specifications mentioned in Agreement of Sale, of the aforesaid Project is estimated at Rs. 6,63,09,8101 (Total of Table A & B). 5. I Certify that the cost of Civil, MEP & Allied Work for apartments & proportionate internal & external works, as per the specifications mentioned in Agreement of Sale, of the aforesaid Project as completed on the date of this certificate is as given in Table A & B below: TABLE-A-ANUKUL S. Particulars Amount (in Rs.) No. 1 Total Estimated Cost of Building / Wing / Layout / Rs. 9,09,78,300r Plotted Development as on date of Registration is 2. Cost incurred as on date of Certificate Rs. 2,72,93,490t 31 December 2024 J. Work Done in Percentage (as Percentage of 3Oo/o Estimated Cost) 4. Balanie Cost to be incurred -- ((based on Rs. 6,36,84,8101 Estimated Cost) 5. Cost incurred on Additional / Extra ltems not included in the Estimated Cost (Table-C) TABLE - B lnternal & External Works in of ANUKUL s Particulars Amount (in Rs.) No. 1. Total Estimated Cost of lnternal & External Rs 37,50,000f Development Works including amenities & facilities in the Lavout as on date of Registration is 2. Cost incurred as on date of Certificate Rs. 1 1,25,000/- 3'1 December 2024 J. Work Done in Percentage (as Percentage of 30Yo Estimated Cost) *" Rs. 26,25,000/- 4. Balance Cost to be incurred ((based on Estimated Cost) 5. Cost incurred on Additional / Extra ltems not included in the Estimated Cost (Table-C) Er. Balasaheb Devkate Diploma Civil Engg. Yours faithfully, iftY ER BALASAHEB DEVKATE Signature & Name with Stamp of Engineer Local Authority License Number ( ) Agreed & Accepte ffii Signature of Promoter Name: RIDDHI VIYAAN VENTURES tu\# Date: 02-O1-2025 Note: 1. The scope of work is to complete Registered Real Estate Project as per drawings approved from trme to time as per specifications mentioned in the Agreement to Sale. (.) Quantity Survey can be done by the office of Engineer or can be done by an independent Quantity Surveyor, who's Certificate of Quantity Calculated, can be relied up on by Engineer. ln case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (") & in case quantity are being calculated by office of Engineer, the name of person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). c. (**) Balance Cost to be incurred (4) may vary from difference between Total Estimated Cost (1) & actual Cost incurred (2) due to deviation in quantity required / escalation of cost etc. As this is an Estimated Cost any deviation quantity required for the Development of Real Estate Project will result in an amendment.of the cost incurred / to be incurred. 4. All components of work with specifications are indicative & not exhaustive Er. Balasaheb Devkate Diploma Civil Engg. 5. Please specify if there are any deviations / qualifications. Example: Any deviation in input material used from specifications in Agreement of Sale. TABLE - C List of Extra / Additional / Deleted ltems considered in the Cost (Which were not parts of the original Estimate of Total Cost) S. No. List of Extra / Additional / Deleted ltems Amount (in Rs.) 1 2.