Er. Balasaheb Devkate Diploma Civil Engg. Annexure - B FORM - 2 [See Regulation 3] ENG]NEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for Withdrawa-l of Money from Designated Bank Account) Date: 12-04-2024 To, RIDDHI VIYAAN VENTURES, PLOT NO 40, SECTOR N.3, CIOCO, AURANGABAD Subject: Certificate of Cost lncurred for Development of ANUKUL having MahaREM Registration Number P5'1500052898 being developed by RIDDHI VIYAAN VENTURES. (For Jan to Mar 2024 QTR) Sir, I / We Mr BALASAHEB DEVKATE have undertaken assignment of Certifying Estimated Cost for ANUKUL having MahaRERA Registration Number P51500052898 being developed by RIDDHI VIYAAN VENTURES. 1. We have estimated the cost of Civil, MEP and Allied Works required for completion of the apartments & proportionate completion of internal & external works of the Project as per the specifications mentioned in the Agreement of Sale. Our estimated cost calculations are based on the Drawings/Plans made available to us for the Project under Reference by the Developers / Consultants. The Schedule of ltems & Quantity required for the entire work as calculated by Quantity Surveyor* appointed by the Developer/Engineer, the assumption of the cost of material, labour & other inputs made by the Developer, and the Site lnspection carried out by us to ascertain / confirm the above analysis given to us. 2. We estimate Total Estimated Cost of completion of the aforesaid Project mentioned under reference at Rs. 9,47,28,300/- Ootal of Table A & B) at the time of Registration. The estimated Total Cost of Project is with reference to the Civil, MEP & Allied Works completion of the apartments & proportionate completion of internal & external works, as per the specifications mentioned in the Agreement of Sale & for the purpose of obtaining Occupation Certificate / Completion Certificate for the Building(s) / Wing(s) / Layout / Plotted Development from the CHHATRAPATI SAMBHAJI NAGAR MUNICIPAL CORPORATION CHHATRAPATI SAMBHAJI NAGAR being the Planning Authority under whose jurisdic{ion the aforesaid Project is being implemented. Er. Balasaheb Devkate Diploma Civil Engg. 3. The Estimated Cost incurred till date is calculates to Rs. 1,42,09,2451-(Total of Table A & B). The Amount of .EslimaleC..QpS!.].ng.u.r:red.j.q.._cdc.ttla!e.d.an_!h.e-.b.asis..-oJ.inpq!.m.a.terials./ S_e.ry1.c._es_ug_ed&..u.nj!..-c.A.S!..-oJ.!h9S9.it.e.m.C I' 4. The Balance Cost of completion of the Civil, MEP & Allied Works for completion of Apartments & proportionate completion of internal & external works, as per specifications mentioned in Agreement of Sale, of the aforesaid Project is estimated at Rs. 8,05,1 9,055/- (Total of Table A & B). 5. I Certify that the cost of Civil, MEP & Allied Work for apartments & proportionate internal & external works, as per the specifications mentioned in Agreement of Sale, of the aforesaid Project as completed on the date of this certificate is as given in Table A & B below: TABLE - A ANUKUL S. Particulars Amount (in Rs.) No. 1 Total Estimated Cost of Building / Wing / Layout / Rs. 9,09,78,3001 Plotted Development as on date of Reqistration is 2. Cost incurred as on date of Certificate Rs. 1,36,46,7451 31 March2O24 J. Work Done in Percentage (as Percentage of 15% Estimatbd Cost) 4. Balance Cost to be incurred ** ((based on Rs. 7,73,31,5551 Estimated Cost) E Cost incurred on Additional / Extra ltems not included in the Estimated Cost (Table-C) TABLE - B lnternal & External Development Works in respect of ANUKUL s. Particu lars Amount (in Rs.) No. 1. Total Estimated Cost of lnternal & External Rs. 37,50,0001 Development Works including amenities & facilities in the Layout as on date of Reqistration is 2. Cost incurred as on date of Certificate Rs. 5,62,500/- 31 March2024 3 Work Done in Percentage (as Percentage of 15o/o Estimated Cost) 4. Balance Cost to be incurred ** ((based on Rs. 31,87,5001 Estimated Cost) Cost incurred on Additional / Extra ltems not included in the Estimated Cost ffable-C) Er. Balasaheb Devkate Diploma Civil Engg. 2E Yours faithfully, ER BALASAHEB DEVKATE Signature & Name with Stamp of Engineer Local Authority License Number t-----J Agreed & Accepte ds% Signature of Prorfi-oter Name: RIDDHI VIYAAN VENTURES u# Dafe.12-04-2024 Note: L ThescopeofworkistocompleteRegisteredRealEstateProjectasperdrawings to approved lrom time to time as per specifications mentioned in the Agreement Sale. (-) Quantity Survey can be done by the office of Engineer or can be done by an independentQuantitySurveyor,who,ScertificateofQuantityCalculated,canbe relied up on by Engineer. ln case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (-) & in case qlantity are being calculated by office of Engineer, the name of person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (.). 3. (*-) Balance cost to be incurred (4) may vary from difference between Total istimatea Cost (1) & actual Cost incurred (2) due to deviation in quantity required / escalation of cost etc. As this is an Estimated cost any deviation quantity required for the Development of Real Estate Project will result in an amendment of the cost incurred / to be incurred. 4. All components of work with specifications are indicative & not exhaustive Er. Balasaheb Devkate Diploma Civil Engg. 5 Please specify if there are any deviations / quarifications. Exampre: Any deviation in input material used from specifications in Agreement of Sale. TABLE - C List of Extra / Additional / Deleted ltems considered in the Cost (Which were not parts of the original Estimate of Total Cost) List of Extra / AaUitionit I Oetetea tterns