Annexure A FORM 1 [See Regulation 3] ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date: 12-07-2025 To, PARAM DEVELOPERS, 14, SHYAM CHAMBERS, BANSILAL NAGAR, RAILWAY STATION ROAD, AURANGABAD Subject: Certificate of Percentage of Completion of Construction Work of PARAM SUVARNVASTU having MahaRERA Registration Number P51500052126 being developed by PARAM DEVELOPERS. (For Apr to Jun 2025 QTR) Sir, I / We ARCH PRAMOD NARALE have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of PARAM SUVARNVASTU having MahaRERA Registration Number P51500052126 being developed by PARAM DEVELOPERS. Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A Layout / Building / Wing Number FOR PARAM SUVARNVASTU - TYPE A ROW HOUSE S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% 3 X number of Podiums ----- 4 Stilt Floor ----- 5 X number of Slabs of Super Structure 100% 6 Internal walls, Internal Plaster, Floorings within 100% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings 100% within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 95% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 95% completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings and 100% Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A Layout / Building / Wing Number FOR PARAM SUVARNVASTU - TYPE B ROW HOUSE S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% 3 X number of Podiums ----- 4 Stilt Floor ----- 5 X number of Slabs of Super Structure 100% 6 Internal walls, Internal Plaster, Floorings within 100% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings 100% within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 95% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 95% completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings and 95% Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A Layout / Building / Wing Number FOR PARAM SUVARNVASTU - TYPE C ROW HOUSE S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% 3 X number of Podiums ----- 4 Stilt Floor ----- 5 X number of Slabs of Super Structure 100% 6 Internal walls, Internal Plaster, Floorings within 100% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings 90% within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 90% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 90% completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings and 90% Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A Layout / Building / Wing Number FOR PARAM SUVARNVASTU – WING D S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% 3 X number of Podiums ----- 4 Stilt Floor 100% 5 X number of Slabs of Super Structure 100% 6 Internal walls, Internal Plaster, Floorings within 0% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings 0% within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A Layout / Building / Wing Number FOR PARAM SUVARNVASTU – WING E S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% 3 X number of Podiums ----- 4 Stilt Floor 100% 5 X number of Slabs of Super Structure 100% 6 Internal walls, Internal Plaster, Floorings within 0% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings 0% within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-B Common Areas (Internal & External Development Works) FOR PARAM SUVARNVASTU – TYPE A, B & C ROW HOUSE, WING D, WING E S. No. Common Areas & Facilities Proposed Percentage of Details (Yes / NO) actual Work Done (As on date of Certificate) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths : YES 10% Internal Cement Roads 2. Water Conservation, Rain water YES 30% Rain Water Harvesting As Per Harvesting : Norms 3. Energy management : NO ----- NA 4. Fire Protection And Fire Safety NO ----- NA Requirements : 5. Electrical Meter Room, Sub-Station, YES 5% As Per MSEB Norms Receiving Station : 6. Aggregate area of recreational Open YES 10% Open Space Space : 7. Open Parking : NO ----- NA 8. Water Supply : YES 25% From Well 9. Sewerage (Chamber, Lines, Septic YES 0 Drainage Line Till Corporation Tank , STP) : Line 10. Storm Water Drains : NO ----- NA 11. Landscaping & Tree Planting : YES 10% Tree Plantation 12. Street Lighting : YES 10% Street Lights For Internal Project 13. Community Buildings : NO ----- NA 14. Others (Option to Add more) NO ----- NA Yours faithfully, ARCH PRAMOD NARALE Signature & Name (IN BLOCK LETTERS) of Land Surveyor / Architect License Number (________________) Agreed & Accepted by: Signature of Promoter Name: PARAM DEVELOPERS Date: 12-07-2025