A:urexure A FORM 1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:13-1G2024 To, PARAM DEVELOPERS, 14, SHYAM CHAMBERS, BANSILAL NAGAR, RAILWAY STATION ROAD, AURANGABAD Subject: Certificate of Percentage of Completion of Construction Work of PARAM SUVARNVASTUhaving MahaRERA Registration Number P51500052126bein9 developed by PARAM DEVELOPERS. (For Jul to Sep 2024 QTR) Sir, I / We ARCH PRAMOD NARALEhave undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of PARAM SUVARNVASTU having MahaRERA Registration Number PSi500052126 being developed by PARAM DEVELOPERS. Based on the Site lnspection, with respect to the Layout / each BuildingMing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the BuildingMing of the Real Estate Project under MahaREM is as per Table'A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table.B. TABLE-A Buildi Number FOR PARAM SUVARNVASTU . TYPE A ROW HOUSE s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% 3 X number of Podiums 4 Stilt Floor ( X number of Slabs of Super Structure 100o/o 6 lnternal walls, lnternal Plaster, Floorings within 100o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 100% Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 90% connecting Staircases and Lifts, Overhead and Underqround Water Tanks. o The external plumbing and eliternal plaster, elevation, 80% completion of terraces with waterproofing of the BuildingM/ing 10 lnstallation of lifts, water pumps, liircfightif,C+rttinC€ 80% ; Electrical fittings to Common Areas, electro, meehanlea@ Complianee to conditions of envirortrttent /eRZ ftoe ; Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A Buildi N umber FOR PARAM SUVARNVASTU - TYPE B ROW HOUSE s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 10Oo/o 2 X number of Basement(s) and Plinth 10Oo/o X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 1OO%o b lnternal walls, lnternal Plaster, Floorings within 100% Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 100o/o Fittings within the FlaUPremises I Staircases, Lifts Wells and Lobbies at each Floor level 90% connecting Staircases and Lifts, Overhead and Underqround Water Tanks. o The external plumbing and external plaster, elevation, 80o/o completion of terraces with waterproofing of the BuildingANing 10 lnstallation of lifts, water pumps, F*e€ightingEitliqgs 80% a@, FilectrirdHittings-to Common Areas, electro, nre€hanicsf6qilpmEnt, Compliance to conditions offivironmentTOR-l$Oe, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingANing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A Bui Number FOR um PARAM SUVARNVASTU - TYPE C ROW HOUSE s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2 (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% X number of Podiums 4 Stilt Floor A X number of Slabs of Super Structure 100% 6 lnternal walls, lnternal Plaster, Floorings within 100o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 90% Fittings within the FlaUPremises I Staircases, Lifts Wells and Lobbies at each Floor level 90% connecting Staircases and Lifts, Overhead and Underqround Water Tanks. The external plumbing and external plaster, elevation, 90% completion of terraces with waterproofing of the Building/vVing 10 lnstallation of lifts, water pumps,{i+e+igh+ingFittings-' 80% al,rl tr$#pmentas-percFoNoC, Electrical fittings to Common Areas, electro, mechanical equipment, Com pli ance 1s 69nditi ons of environrlEnt+GRre, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingANing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certifi cate TABLE.A / Buildi Number F OR PARAM SUVARNVASTU -WING D S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2t (3) 1 Excavation 0Yo 2 X number of Basement(s) and Plinth 0% 3 X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 0o/o o lnternal walls, lnternal Plaster, Floorings within 0o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 0% Fittinos within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level lYo connecting Staircases and Lifts, Overhead and Underqround Water Tanks. 9 The external plumbing and external plaster, elevation, 0o/o completion of terraces with waterproofing of the Building/Wing 10 Instal latio n of ift s, water pu m ps, fi5e-FigrhtingrEittings I Oo/o ?nd Fquipment as per e FO t{OG, Eleckical fittings to Common Areas, electro, Sech:ni€el€quipment- Co.npliance te eenditiens of environment /eRZ NOe, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildinglVVing, Compound Wall and all other requirements as may be required to Obtain Occuoation /ComDletion Certificate TABLE-A Buildi Number FOR PARAM SUVARNVASTU - WING E S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 0% 2 X number of Basement(s) and Plinth 0% 3 X number of Podiums 4 Stilt Floor X number of Slabs of Super Structure ook b lnternal walls, lnternal Plaster, Floorings within 0!o Flats/Premises, Doors and Windows to each of the FIaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 0% Fittings within the FlaVPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 00k connecting Staircases and Lifts, Overhead and Underqround Water Tanks. o The external plumbing and external plaster, elevation, 0o/o completion of terraces with waterproofing of the Building^/ving 10 I nsta| ation of Iift s, water pu m ps, F+eFig,ht'r'ngrFittin€s I Oo/o a@ Electrical fittings to Common Areas, electro, mechaAi€+€quipm€n{ c Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-B Common Areas (lnternal & External Development Works) FOR PARAM SUVARNVASTU - N/PE A, B & C ROW HOUSE, WING D WING E S. Common Areas & Facilities Proposed Percentage of Details No. (Yes / NO) actual Work Done (As on date of Certificate) 1) (2) (3) (4) (s) 1. I ntern:f8oade-& Footpaths : YES lYo lnternal Cement Roads 2. Water Conservation, Rain water YES Oo/o Rain Water Harvesting As Harvestinq: Per Norms Enerqv manaqement : NO NA 4. Fire Protection And Fire Safety NO NA Requirements: Electrical Meter Room, Sub- YES o% As Per MSEB Norms Station, Receivinq Station : b. Aggregate area of recreational YES 0o/o Open Space Open Space : 7. Open Parkinq : NO NA 8. Water Supplv : YES 100/o From Well o Sewerage (Chamber, Lines, YES 0 Drainage Line Till Septic Tank , STP) : Corporation Line 10. Storm Water Drains : NO NA 11. Landscapinq & Tree Planting : YES 0% Tree Plantation 12. Street Lighting : YES 0o/o Street Lights For lnternal Proiect 13. Communitv Buildinqs : NO NA 14. Others (Option to Add more) NO NA Yours faithfully, Signature & Name (lN BLOCK LETTERS) of Land Surveyor / Architect License Number ( ) Agreed & Accepted by: ffiS*x,*qE.,* nAt rylry=+ 9"9 Signature of Promoter Name:PARAM DEVELOPERS Date:13-10-2024