Annexure A FORM 1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:09-04-2024 To, PARAM DEVELOPERS, 14, SHYAM CHAMBERS, BANSILAL NAGAR, RAILWAY STATION ROAD, AURANGABAD Subject: Certificate of Percentage of Completion of Construction Work of PARAM SUVARNVASTUhaving MahaRERA Registration Number P515000521 26being developed by PARAM DEVELOPERS. (For Jan to Mar 2024 QTR) Sir, I / We ARCH PRAMOD NARALEhave undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of PARAM SUVARNVASTU having MahaRERA Registration Number P51500052'l.26 being developed by PARAM DEVELOPERS. Based on the Site lnspection, with respect to the Layout / each BulldingMing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Buildingruing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-8. TABLE-A B Wi Number FOR PARAM SUVARNVASTU - ryPE A ROW HOUSE S, Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2t (3) I Excavation 100% 2 X number of Basement(s) and Plinth 100% X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 100% 6 lnternal walls, lnternal Plaster, Floorings within 90% Flats/Premises, Doors and Windows to each of the FIaVPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 80% Fittings within the FlaVPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 7 0o/o connecting Staircases and Lifts, Overhead and Underqround Water Tanks. o The external plumbing and external plaster, elevation, 70% completion of terraces with waterproofing of the BuildingMing 10 nstallation of ift s, water pumps, FituFigirtingrftttings- I I 7 0o/o an{ Equipmen+a+peeGF@l{OC, Electrical fittings to Common Areas, electro, rnecbanical€quipment, c Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingA/t'ing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A / Buildi Number FOR PARAM SUVARNVASTU . TYPE B ROW HOUSE S Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% J X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 1O0o/o b lnternal walls, lnternal Plaster, Floorings within 1O0o/o Flats/Premises, Doors and Windows to each of the FlaVPremises 7 Sanitary Fittings within the FlaVPremises, Electrical 80% Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 60% connecting Staircases and Lifts, Overhead and Underqround Water Tanks. o The external plumbing and external plaster, elevation, 60% completion of terraces with waterproofing of the BuildingA/Ving 10 lnstallation of lifts, water pumps, Fi{bSlghtingfittirgs and Fqlipment as f\er CFON€C, Electrical fittings to Common Areas, electro, rnee+aniea+equlpnrent, c, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certifi cate TABLE-A Buildlno / Wino Number FOR PARAM SUVARNVASTU - TYPE C ROW HOUSE S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) I Excavation 100% 2 X number of Basement(s) and Plinth 100o/o X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 100Yo 6 lnternal walls, lnternal Plaster, Floorings within 90o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaVPremises, Electrical 70% Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 60% connecting Staircases and Lifts, Overhead and Underqround Water Tanks. o The external plumbing and external plaster, elevation, 60% completion of terraces with waterproofing of the BuildingANing 10 I nstal latio n of lift s, water pu mps, Fi€+ightingrFittingfs 50% @, Electrical fittings to Common Areas, electro, meehanieal-equipmen! c^rnpliance te eenditions of envirortment eR- tlOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certifi cate TABLE-A Bu Number FOR P ARAM SUVARNVASTU - WING D S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 0o/o 2 X number of Basement(s) and Plinth 0% 3 X number of Podiums 4 Stilt Floor X number of Slabs of Super Structure Oo/o 6 lnternal walls, lnternal Plaster, Floorings within 0o/o Flats/Premises, Doors and Windows to each of the FlaVPremises 7 Sanitary Fittings within the FlaUPremises, Electrical Oo/o Fittinos within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level Oo/o connecting Staircases and Lifts, Overhead and Underqround Water Tanks. o The external plumbing and external plaster, elevation, 0o/o completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Oo/o anO gquinmant as pe C, Electrical fittings to e ommon Areas, electro, mQCheni.al equipmctlt, G€mplianee to eonditions of environment /eRZ NOq Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingANing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A Buildino / Winq Number FOR PARAM SUVARNVASTU - WING E s. Tasks / Activity Percentage of Actual Work No. Oone (As on date of the Certificate) (1) (21 (3) 1 Excavation 0% 2 X number of Basement(s) and Plinth 0% X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 0% o lnternal walls, lnternal Plaster, Floorings within 0o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 0% Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and Underqround Water Tanks. o The external plumbing and external plasler, elevation, Oo/o completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, FiEFight+Fg+ittingE 0% , ebe*le++ittings-to Common Areas, electro, me€hali€aleguipnTent, Comnliance te 6enditions of envil0RmEnUC.l- liOe , Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occu Certificate TABLE-B Common Areas (lnternal & External Development Works) FOR PARAM SUVARNVASTU -TYPE A, B & C ROW HOUSE, WING D, WNG E S. Common Areas & Facilities Proposed Percentage of Details No. (Yes / NO) actual Work Done (As on date of Certificate) (1) (21 (3) (4) (s) 1. lol#dr*Footpaths: YES 0o/o lnternal Cement Roads 2. Water Conservation, Rain water YES 0% Rain Water Harvesting As Harvestinq: Per Norms 3. Enerqy manaqement : NO NA 4. Fire Protection And Fire Safety NO NA Requirements: A Electrical Meter Room, Sub- YES 0% As Per MSEB Norms Station. Receivinq Station : b. Aggregate area of recreational YES lYo Open Space Open Space : 7. Ooen Parkinq : NO NA 8. Water Supplv : YES 1Oo/o From Well 9. Sewerage (Chamber, Lines, YES 0 Drainage Line Till Seotic Tank . STP) : Corporation Line 10. Storm Water Drains : NO NA 11. Landscaplnq & Tree Plantinq : YES 0o/o Tree Plantation 12. Street Lighting : YES Oo/o Street Lights For lnternal Proiect 13. Communitv Buildings : NO NA 14. Others (Ootion to Add more) NO NA Yours faithfully, Sigfature & Name (lN BLOCK LETTERS) of Land Surveyor / Architect License Number ( ) Agreed & Accepted by: ffif'{.,*rggP1 Y/LJ.\ ' " At P,o.".rr,,r,,uoo Notole OrFcx) C^r2! i l/ tl'32' r*a\A +f,9, of Promoter