Annexure A FORM 1 {See Regulation 3l ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:08-01-2024 To, PARAM DEVELOPERS, 14, SHYAM CHAMBERS, BANSILAL NAGAR, RAILWAY STATION ROAD, AURANGABAD Subject: Certificate of Percentage of Completion of Construction Work of PARAM SUVARNVASTUhaving MahaREM Registration Number P51500052126bein9 developed by PARAM DEVELOPERS. (For Oct to Dec 2023 QTR) Sir, I / We ARCH PRAMOD NARALEhave undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of PARAM SUVARNVASTU having MahaRERA Registration Number P51500052126 being developed by PARAM DEVELOPERS. Based on the Site lnspection, with respect to the Layout / each BuitdingM/ing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the BuildingMing of the Real Estate Project under MahaREM is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Tabl+.B. TABLE.A B Winq Number FoR PARAM SUVARNVASTU . TYPE A ROW HOUSE S. Tasks / Activity Percentage of Actual Work No. Oone (As on date of the Certificate) (1) (21 (3) 1 Excavation 10Oo/o 2 X number of Basement(s) and Plinth 100o/o J X number of Podiums 4 Stilt Floor X number of Slabs of Super Structure 100Yo 6 lnternal walls, lnternal Plaster, Floorings within 80% Flats/Premises, Doors and Windows to each of the FlaVPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 60% Fittings within the FlaVPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 60% connecting Staircases and Lifts, Overhead and Underoround Water Tanks. o The external plumbing and external plaster, elevation, 600/o completion of terraces with waterproofing of the BuildingAr'Ving 10 Instal lation of lift s, water pumps, Eire+EilrtingrfittifiErs 60% and Equioment as f'er GF+NOC , Electrical fittings to Common Areas, electro, ma€lealica@t, comnlianee to eonditions efenvirenmcnt /eRZ NOC Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A Number FOR PARAM SUVARNVASTU - TYPE B ROW HOUSE S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100o/o 2 X number of Basement(s) and Plinth 100% 3 X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 100% 6 lnternal walls, lnternal Plaster, Floorings within 80% Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 60o/o Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 40% connecting Staircases and Lifts, Overhead and Underoround Water Tanks. o The external plumbing and external plaster, elevation, 40o/o completion of terraces with waterproofing of the BuildingAlVing 10 lnstallation of lifts, water pumps, FirgFEhtlnlrFitting€ 10% arrd Equipment as per CFO-N@C: Electrical fittings to Com mon Areas, electro, mecfqffiprne,rt Gempliancstocond,tiens of environmcnt /eRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A Number FOR PARAM SUVARNV ASTU - WPE C ROW HOUSE s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100% X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 100% 6 lnternal walls, lnternal Plaster, Floorings within 80% Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 50o/o Fittings within the FlaUPremises I Staircases, Lifts Wells and Lobbies at each Floor level 400k connecting Staircases and Lifts, Overhead and Underqround Water Tanks. I The exlernal plumbing and external plaster, elevation, 40o/o completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, ffiErhtirg Fttttngrs 40% @Electrical fittings to Common Areas, meeAanileaffi electro, Gcm Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A Buildi Number FOR PARAM SUVARNVASTU - WING D S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 0% 2 X number of Basement(s) and Plinth 0o/o X number of Podiums 4 Stilt Floor E X number of Slabs of Super Structure 0o/o b lnternal walls, lnternal Plaster, Floorings within 0o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlEUpremEEs. Elea 0% Flttings within the Flaupremises 8 Staircases, LiftsWeffi Oo/o connecting Staircases and Lifts, Overhead and Underoround Water Tanks. I The externat plumbing a@ 0% completion of terraces with waterproofing of the BuildingAlVing 10 lnstallation of lifts, water pumps, 0o/o @ Etectiicat iittingsio Common Areas, electro, rne@ipmenl, Cornplian6e to eonditior rs of envlrfnTEificlzTloq Finishing to entrance lobby/s, plinth protection, paving oI areas appurtenant to BuildingA/Ving, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A / Building / Winq Number FOR PARAM SUVAF NVASTT I WrNn tr S, - Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) t2l (3) 1 ExCaVatron 0o/o z X number of BasemEnt(s) and plinth 0o/o 3 X number of Podiums- 4 Stilt Floor E X number of Slabs oiSupEiStructure- ; lnternal walls, tntern@ 0% Oo/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary rittings witrr@ 0% Fittings within the Flaupremises I Staircases, lifts W@ 0o/o connecting Staircases and Lifts, Overhead and Underoround Water Tanks. o 0o/o completion of terraces with waterproofing of the BuildingAlVing 10 lnstallation oi tlttq water purnps, 0% ana Fquipment as p Electiical ittingJ; Common Areas, electro, rneeffi€$Jipm€€t- Compliance to conditions of anvironmenr TCRZilOe, Finishing to entrance lobby/s, plinth prolection, paving of areas appurtenant to BuildingA/Ving, Compound Will and all other requirements as may be required to Obtain Occupation Certificate TABLE.B Common Areas (lnternal & External Development Works) FOR PARAM SUVARNVASTU - TYPE A, B & C ROW HOUSE, WING D, WING E S. Common Areas & Facilities Proposed Percentage of Details No. (Yes / NO) actual Work Done (As on date of Certificate) (1) (21 (3) (4) (s) 1. lnterp#* FootDaths: YES lYo lnternal Cement Roads 2. Water Conservation, Rain water YES Oo/o Rain Water Harvesting As Harvestinq: Per Norms Enerqy manaqement : NO NA 4. Fire Protection And Fire Safety NO NA Requirements: Electrical Meter Room, Sub- YES 0o/o As Per MSEB Norms Station, Receivinq Station : 6. Aggregate area of recreational YES 0o/o Open Space Open Space : 7. Open Parkinq : NO NA a Water Supplv : YES 1Oo/o From Well o Sewerage (Chamber, Lines, YES 0 Drainage Line Till Seotic Tank . STP) : Corporation Line 10. Storm Water Drains : NO NA 11. Landscapinq & Tree Plantinq : YES lYo Tree Plantation 12. Street Lighting : YES 0o/o Street Lights For lnternal Proiect 13. Communitv Buildinqs : NO NA 14. Others (Option to Add more) NO NA Yours faithfully, e*-b Ak6-PRAM-.DNARALE Signature & Name (lN BLOCK LETTERS) of Land Surveyor / Architect License Number (_______________ Agreed & Accepted by: ffiH*x"g'* rm*r 9:Y{A (s.or)| z\--1"5,, Signature of Promoter Name:PARAM DEVELOPERS Date:08-01-2024