SARTHAK ASSOCIATES OFFICE NO C-7, THIRD FLOOR, PROZONE TRADE CENTRE, PROZONE MALL, AURANGABAD _ 431006 Annexure A FORM 1 ISee Regulation 3] ARCHITECT'S CERTIFICATE, {To be submitted at the time of Registration of Ongoing Project & for Withdrawa.l of Money from Designated Account) Date: 10-04-2024 To, NAVBHARAT BUILDERS, PLOT NO 54, NS 1 CIDCO, SHIVAJI NAGAR, AURANGABAD. 02 Subject: Certificate of Percentage of Completion of Construction Work of LABH APARTMENTS having MahaREM Registration Number P51500052867 being developed by NAVBHARAT BUILDERS Sir. l/ We M/s. SARTHAK ASSOCIATES have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of LABH APARTMENTS having MahaRERA Registration Number P51500052867 being developed by NAVBHARAT BUILDERS. Based on the Site Inspectaon, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the BuildingtuVing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE.A FOR BUILDING OF LABH APARTMENTS S. -l Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 100o/o 2. Basements (if any) 3 Podiums (if anv) 4 Plinth 100o/o 5 Stilt Floor 100o/o 6 Slab of Super Structure 100% 7. 8 o lnternal Walls, lnternal Plaster, Floorings, Doors, windows within Flats / Premises Sanitarv Fittinqs within Flats / Premises Staircases, Lift Wells & Lobbies at each Floor Level 100o/o 100o/o l SARTHAK ASSOCIATES OFFICE NO C.7, THIRD FLOOR, PROZONE TRADE CENTRE, PROZONE MALL, AURANGABAD _43'1006 Overhead and Underqround Water Tanks 10 External Plumbing & External Plaster, Elevation, 90% Completion of Terraces, with waterproofing of the Buildinq / Winq 11 lnstallation of Lifts, Water Pumps, Fire Fighting Fittings 90% and Equipment's as per CFO NOC, Electrical Fittings, Mechanical Equipment's, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Buildingll,{ing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE.B common Areas (lnternal & External Development works) in respect of the Registered Project FOR BUILDING OF LABH APARTMENTS S. Common Areas & Facilities Proposed Percentage Deta ils No. (Yes / NO) of actua I Work Done (As on date of Certificate) (1) (2) (3) (4) (5) 1 lnternal Roads & Footpaths NO N,A, 2 Water Supply YES 50o/o From BorerWell J, Sewerage (Chamber, Lihes, YES 10o/o Drainage Line Till Septic Tank, STP) Corporation Line 4 Strom Water Drains NO N,A, 5 Landscapinq & Tree Planting NO N.A. 6 Street Liqhtinq NO N,A. 7. Communitv Buildinqs NO N,A, I Treatment & Disposal of Sewage NO N,A, and Sullaqe Water o Solid Waste Management & NO N,A, Disposal 10 Water Conservation / Rain Water YES 00% Rain Water Harvesting Harvestinq As Per Norms 11 Enerqy Manaqement NO N.A. 12 Fire Protection & Fire SafetY NO N,A. requirements tJ. Electrical Meter Room, Sub- YES 0004 Separate Meter Area Station, Receiving Station 14. Others (Option to Add more) NO N.A. SARTHAK ASSOCIATES . 431006 oFFICE No C-7, THIRD FLooR, PRozoNE TRADE CENTRE, PRozoNE MALL, AURANGABAD Yours faithfully, For SARTHAK ASSOCIA i \.=-y ...l Surveyor / Architect Signature & Name (lN BLoCk LETTERS) oi Land Surve Lrcense Number (-) Agreed & Accepted by tt2' -\ S rg nature of Fromoter Name: NAVBHARAT BUILDERS Date 10-04-2024