Annexure A Form 1 ARCHITECT'S CERTIFICATE QPR 2 01-07-2025 TO 30-09-2025 To, The Asif Patel Rasheed Patel Plot No 1, Opp Taj Residency , Mehmoodpura Chh. Sambhajinagar Subject: Certificate of Percentage of Completion of Construction Work of (“Uptown Park ") having MahaRERA Registration Number P51500051740 (Only Applicable after project Registration) being developed by Asif Patel Rasheed Patel Sir, I/We Mr. Tadeebuddin Siddiqui have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction Work of ("Uptown Park") having MahaRERA Registration Number P5150051740 (Only Applicable after project Registration, being developed by Asif Patel Rasheed Patel Based on Site Inspection, with respect to Layout/each of the Building/Wing of the aforesaid Real Estate Project. I certify that on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Layout/Building/Wing Number Uptown Park (to be prepared separately for each Layout/Building/Wing of the Project) Sr.No Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) NIL 3. Podiums (if Any) NIL 4. Plinth 100% 5. Stilt Floor NIL 6. ------- Slabs of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors and 80% windows within Flats/Premises 8. Sanitary Fittings within the Flat/Premises NIL 9. Staircases, Lifts Wells and Lobbies at each Floor Level NIL Overhead and Underground Water Tanks 10. External plumbing and External Plaster, Elevation, 0 Completion of terraces with waterproofing of the Building/Wing. 11. Installation of Lifts, water pumps, Fire Fighting Fittings and 0 Equipment as per CFO NOC, Electrical fittings, Mechanical equipment, compliance to conditions of environment/CRZ NOC , Finishing to entrance Lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement to sale. Any other activities. TABLE B Common Areas (Internal and External Development Works) in respect of the Registered Phase/Project Number Sr.No Common areas and Facilities Proposed Percentage of actual work Details (Yes/No) Done (As on date of the Certificate) (1) (2) (3) (4) (5) 1. Internal Roads & footpaths YES 0% As Per Sanctioned Plan 2. Water Supply YES 0 Water From AMC 3. Sewarage (Chamber, Lines, YES 0 Chamber Line Septic Tank, STP). 4. Storm Water Drains NO NIL NIL 5. Landscaping & Tree YES 0 As Per Sanctioned Plantations Plan 6. Street Lighting NO NIL NIL 7. Community Buildings NO NIL NIL 8. Treatment and disposal of NO NIL NIL sewage and sullage water. 9. Solid Waste management & NO NIL NIL Disposal 10. Water Conservation/Rain YES 0 As Per Sanctioned Water Harvesting Plan 11. Energy Management NO NIL NIL 12. Fire protection and fire safety NO NIL NIL requirements 13. Electrical meter room , Sub- YES 0 DP Provided from Station, receiving station MSEB 14. Others (Option to Add More). Yours faithfully, Signature & Name (IN BLOCK LETTERS) with Stamp of Engineer Agreed & Accepted by: Signature of Promoter Name: Asif Patel Rasheed Patel Date : 02-10-2025