FORM 1 [See Regulition 3l ARC HITECT'S CERTIFIGATE (To be submitted at the time of Registration of ongoing Project and for withdrawal of Money from Designated Account) DATE: 31-03-2025 To, GayatriAshok Mule Flat No.9, Samta Darshan, Samta Nagar, Jalan Nagar, Aurangabad -431001. subject: certificate of Percentage of Completion of construction work of Happy Homes having MahaRERA Registration Number P51500051755 being developed by Gayatri Ashok Mule. Sir, l/ we sajjad A'K Lodhi have undertaken assignment as Architect /Licensed surveyor of certifying Percentage of completion of construction work of having MahaRERA Regisiration Number P51500051755 being developed by Happy Homes. Based on site inspection with respect to Layout / each of the aforesaid Real Estate project I certify that as on the date of this certificate, the Percentage of work done for each of the building /wingof the Real Estate Project under MahaRERA is as per Table A herein below. percentage of the;wor.k executedwithrespecttoeachoftheactivityof theentirephaseisdetailedinTableB .=' -- -!':- '' i ti : TABLE-A r , ..'""''"' Layout / Building wing Number Row HousE No or ro 06 (To be prepared separately for each ut building/Wing of The project Sr Tasks / Activity Percentage of Actual Work No (21 Done (1) il (As on date of this !. Certificate) (3) 1. Excavation 100% 2. Basement's (if any) 3. roorums (tI any? 4. rilnIn 100% 5. Stilt Floor 6. Slabs of Super StructurB 100% 7. lnternal walls, lnternal plaster, Floorings, l) doors rnd 9s% windows within Flats/premises 8 5anrrary Fltttngs within the Flat/premises 35% SAJJAD ilX. LODHI 2nd floor, Above Chintamani Sweets. cA|05fi7}94 Near Police Cornmissioner Office. Mill Corner signal, Chh. Sambhaiinaoar rrArrrannchaa\ E- ma i r : a rcrr iteffi H,ilfl Jd,"tf"tj,f :X 9 Staircases. lifts, Wells and Lobbies at each Floor leve TOOo/o Overhead and Unde Water Tanks 10 trv+a -^ ^ L^rs,,.ror-prurilutnt I ano external plaster, elevation, I completion s0% of terraces with waterproofing of the I I auitding/wine. lnctallr+i^^ LL ,,,JLq"oLruil ur r:& ^r LrrLs, water pumps, Fire Fitting Fittings and loN Equipment as per cFo Noc, Electrical fittings, mechanical equipment, compliance to conditions of environrhent/cRZ NOC. Finishing to entrance Iobby/s. plinth protection, paving of areas appurtenant to Building /Wing. Compound Wall and all other requirements as may be requiied to complete project as per specification, in -Sale. Any other activities. ,gr""rent of Layout / Building Wing Number ROW HOUSE NO 07 TO 12 (To be prepared Layout bui separately for each ofThe proi Tasks /eaivity Percentage of Actuat Work (21 Done (As on date of this Certificate) Basement's (if any) Pogllums (if any) Slabs of Super Structure lnternal walls, lnternal plastffi windows within Flats/premises Sanitary Fittings within tf,e n.t/premis"s Staircases. tittr' W Overhead and Underground Water Tanks Externalplumbingan@ completion of terraces with waterproofing of the lnstallation of Lifts. water ou@ Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compriance to conditions of environment/cRZ NOC. Finishing to entrance lobby/s. plinth protection, paving of areas appurtenant to Building/Wing. Compound Wall and all other,requirements ,, ,ry be requiied to complete project as per specification, in .gr."rent of Sale. Any other activities. SAJIAD A.K, LODHI .cAlasl37094 Layout / Building Wing Number ROW HOUSE NO 13 TO 18 (To be prepared separately for each t building/Wing of The Project) Sr Tasks / Activity Percentage of Actual Work No (2) Done (1) (As on date of this Certificate) (3) L. Excavation 100% 2. Basement's (if any) 3. Podiums (if any) 4. Plinth 100% 5. Stilt Floor o% 6. Slabs of Super Structure 100% 7. lnternal walls, lnternal Plaster, Floorings, l) doors and 7s% windows within Flats/Premises 8 Sanitary Fittings within the Flat/Premises 70% 9 Staircases. lifts' Wells and Lobbies at each Floor level 80% Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, o% completion of terraces with waterproofing of the Building/wing. tt lnstallation of Lifts. water pumps, Fire Fitting Fittings and o% Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC. Finishing to entrance lobby/s. plinth protection, paving of areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Layout / Building Wing Number ROW HOUSE NO 19 TO 24 (To be prepared separately for each Layout building/Wing of The Project) Sr Tasks / Activity Percentage of Actual Work No (2) Done (1) (As on date of this Certificate) (3) 1. Excavation LOO% 2. Basement's (if any) 3. Podiums (if any) 4. Plinth 1,00% 5. Stilt FIoor 6. Slabs of Super Structure 80% 7. lnternal walls, lnternal Plaster, Floorings, l) doors and 65% windows within Flats/Premises 8 Sanitary Fittings within the Flat/Premises a% 9 Staircases. lifts' Wells and Lobbies at each Floor level 50% Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, o% SAITAD N.ILOONT cA1o5/37094 completion of terraces with waterproofing of the Buildinglwing. lL tnrtrltation of Lifts, water pumps, Flre Fitting Fittings and o% Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC. Finishing to entrance lobby/s" plinth protection, paving of areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Layout / auilding wing Number HAPPY APARTMENT (To be prepared separately for each Layout build ofThe Pro Tasks / Activity Percentage of Actual Work Sr Done No l2l (As on date of this (1) Certificate) (3) t. Excavation o% 2. Basement's (if any) 3. Podiums (if any) 4. Plinth o% 5. Stilt Floor o% 6. Slabs of Super Structure o% 7. lnternal walls, lnternal Plaster, Floorings, l) doors and o% windows within Flats/Premises 8 Sanitary Fittings within the Flat/Premises o% 9 Staircas"s. lifts' Wells and Lobbies at each Floor level o% Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, o% completion of terraces with waterproofing of the Buildine/wine. t! tnstattation of Lifts. water pumps, Fire Fitting Fittings and o% Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC. Finishing to entrance lobby/s' plinth protection, paving of areas appurtenant to Building/Wing' Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. SAJJAD A.K. LODHI cA/os/37094 7 Common TABLE.B (lnternal and External Development Works) respect of the Registered Number Sr Common areas and facilities Proposed Percentage Details No (Yes/No) of Actual (3) Work (s) (1) l2l Done (As on date of the Certificate) (4) 1,. lnternal Roads & FootPaths NO 2. Water Supply YES 0 3. Sewerage (Chamber, lines, Septic Tank, STP). YES 0 4. Storm Water Drains NO 5. Landscaping & Tree Planting YES 0 6. Street Lighting NO 7. Community Buildings NO 8 Treatment and disposal of sewage and sullage water. NO 9 Solid Waste management & DisPosal NO 10 Water conservation / Rain water harvesting YES 0 LT Energy management. NO 12 fire protection and lire Safety requirements YES 13 Electrical meter room, sub-station, receiving station. NO L4 Lifts YES 0 Yours Faithfully, Signature & Name (lN BLOCK LETTERS) of L.S/ Architect (License No. .............) SAJJAD A.K. LODTf,I cA/os/37094 Agreed and Accepted by: GayatriAshok Mule , Name: Date: