Issue relating to Plinth Level Certificate Brief History As per Notification of Maharashtra Government dt. 20/09/2016 UDCPR was notified for D class Municipal Corporation. As per notification regulation applicable for D class are applicable to Aurangabad. The details relating to Plinth level checking is given at point 10.3 on page no. 21 (Annexure 1) and is reproduced as below:- Checking of plinth, columns upto plinth level- The owner through his licensed surveyor, engineer, structural engineer or supervisor or his architect, as the case may be, shall give notice in the form of Appendix-F to the Commissioner on completion of work upto plinth level and where there is no plinth, construction above general ground level upto 0.60 m.to enable and ensure that the work conforms to the sanctioned plans. The Commissioner may inspect the work jointly with the licensed technical personnel or architect within 15 (fifteen) days from the receipt of such notice and either grant or refuse permission for further construction as per the sanctioned plans in the form in Appendix -G. If within this period, the permission is not refused it shall be deemed to have been granted, provided the work is carried out strictly according to the sanctioned plans. Further the appendix to the rules at page no. 204 and 205 states as under: (Annexure 1) Form F - “FORM FOR INTIMATION OF COMPLETION OF WORK UPTO PLINTH LEVEL” Form G – “FORM OF APPROVAL / DISAPPROVAL OF DEVELOPMENT WORK UPTO PLINTH LEVEL” Hence as per 2016 rules it was mandatory for the builder/promotor to intimate and ger the plinth level certificate for further construction. New UDPCR 2020 as further amended from time to time. New UDPCR 2020 is applicable to Aurangabad. The details relating to Plinth level checking is given at point 2.8.4 on page no. 37 (Annexure 2) and is reproduced as below:- 2.8.4 Plinth Checking The owner shall give intimation in the prescribed form in Appendix- F to the Authority after the completion of work upto plinth level. This shall be certified by Architect / licensed Engineer / Supervisor with a view to ensure that the work is being carried out in accordance with the sanctioned plans. After such intimation, the construction work shall be carried out further. The officers of the Authority, who are empowered to grant development permission and subordinate officers to him, shall each, inspect about 10% of such plinth certified cases. Further the appendix to the rules at page no. 355 and 356 states as under: (Annexure 2) Form F - “FORM FOR INTIMATION OF COMPLETION OF WORK UP TO PLINTH LEVEL” Form G – “FORM FOR COMPLETION CERTIFICATE” Hence as per new rules the provision relating plinth checking is modified and it is mandatory only to intimate regarding completion of plinth level and proceed for further work. Also, approval of plinth level from the authorities is done away with and no longer required. In view of above, we have attach the Appendix F and request to kindly grant us RERA Registration. Government of Maharashtra, Urban Development Department, Mantralaya, Mumbai - 400 032. Dated: 20/09/2016 NOTIFICATION Maharashtra No. TPS-1812/CR-112/12/DCR D Class /UD-13:- Whereas, the Government has sanctioned various Regional & Development Plans (hereinafter referred to as ‗the said Development Plans‘) along with their Town Building Bye-laws and Development Control Rules with or without modifications (hereinafter Planning referred to as ‘the said Development Control Regulations’) for D Class Municipal Corporations Act, 1966 (hereinafter referred to as ‘the said Planning Authorities’) in the Maharashtra State under the provisions of the Maharashtra Regional & Town Planning Act, 1966 (hereinafter referred to as ‘the said Act), as mentioned in Schedule-A appended hereto; And whereas, the said Development Control Regulations of the said Planning Authorities needed overall changes because of rapid urbanization, introduction of concepts like FSI, TDR, various land uses and need for regulations which support developments like generation of parking areas, creation of more built-up area for Hospitals, Educational Institutions, Star Category Hotels, Institutional Buildings, development of more housing stock through MHADA, eco-friendly buildings, regulation of height of buildings commensurate with fire fighting facilities etc. and therefore such new provisions are required to be included in the said Development Control Regulations; And whereas in view of the above, the Government in Urban Development Department, vide its resolution no TPS-1812/CR-112/12/DCR D Class /UD-13 dated the 20/11/2013 has appointed a Committee ((hereinafter referred to as ‘the said Committee’) under Director of Town Planning, Maharashtra State as a Coordinator for drafting the uniform new Development Control Regulations for D class Municipal Corporations in the State; And whereas, the said Committee after deliberating meeting among themselves prepared the Draft development and Control Regulations named as ‘Draft Development Control and Promotion Regulations for D Class Municipal Corporations in Maharashtra’ and submitted the same to the Government vide letter No.2686, dated the 23/04/2015; And whereas, the Government felt it necessary to replace the existing said Development Control Regulations by the new set of Draft Standardised Development Control and Promotion Regulations for D class Municipal Corporations in Maharashtra prepared by the said Committee (hereinafter referred to as ‘the said proposed modification); And whereas Aurangabad Municipal Corporation now being C Class Municipal Corporation has requested Government to made applicable the said proposed Draft Standardised Development Control and Promotion Regulations prepared for the D Class Municipal Corporations for their Corporation; And whereas, the Government, found it expedient in the public interest to take recourse of the provision contained in Section 37(1AA) of the said Act; And whereas , pursuant to the above and in exercise of the powers conferred by Clause (a) of sub-section (1AA) of Section 37 of the said act and all other powers enabling in that behalf, the Government of Maharashtra has published a notice bearing No. TPS-1812/CR-112/12/DCR D Class /UD-13/Dated 19/11/2015 which appeared in the Maharashtra Government Gazette D Class Municipal Corporation DCR dated 3rd to 9th Dec 2015 on the page no 9 to 215 for inviting objections and suggestions upon the said proposed modifications from the general public and concerned Joint Director of Town Planning of the division was authorized as an Officer (hereinafter referred to as the said Officer) to give hearing and submit his report to the Government; And whereas after considering the reports submitted by the concerned said Officers and consulting the Director of Town Planning M. S. Pune ,the Government of Maharashtra is of the opinion that in supersession and in place of existing Development Control Regulations of the D Class Municipal Corporations, the proposed new set of “Draft Development Control and Promotion Regulations for D Class Municipal Corporations in Maharashtra’‖ should be sanctions and made applicable with certain modifications for the said Planning Authorities; Now therefore, in exercise of the powers conferred by Clause (c) of sub-Section (1AA) of Section 37 of the said act and all other powers enabling in that behalf, the Government of Maharashtra finally sanctions the proposed modifications in respect of "Development Control and Promotion Regulations for D Class Municipal Corporations in Maharashtra" and made applicable for the said Planning Authorities as mentioned in Schedule-A attached herewith; 02. This notification shall be kept open for inspection to the general public in the following offices for the above period on all working days. (i) Office of the Director of Town Planning, Central Building, Pune; (ii) Office of the Joint Director of Town Planning, Pune, Nashik, Nagpur, Aurangabad, Amravati Division; (iii) Commissioner Municipal Corporation This notification shall also be made available on the Government website www.maharashtra.gov.in (कायदे /नियम). By order and in the name of Governor of Maharashtra, Sanjay Digitally signed by Sanjay Balkrishna Saoji DN: c=IN, o=Government Of Maharashtra, ou=UNDER SECRETARY, postalCode=400032, st=Maharashtra, Balkrishna 2.5.4.20=13f024b79c19b420653021e5231 1db55b7964b2bc5c3642efdb26f8633f8af 7f, serialNumber=be169cc754827a9bfadc91 Saoji 6ac5c85a4c876ae29f24ca9e6f7c2064ada 52d6747, cn=Sanjay Balkrishna Saoji Date: 2016.09.20 18:30:14 +05'30' (Sanjay Saoji) Under Secretary to Government D Class Municipal Corporation DCR SCHEDULE A (Accompanied with Government Notification no TPS-1812/CR-112/12/ DCR D Class /UD-13, Dated 20/09/2016) Name of the Division Name of the Municipal Corporation Nagpur Chandrapur Amaravati Amaravati Akola Aurangabad Nanded-Waghala Aurangabad Parabhani Latur Pune Kolhapur Solapur Sangali Miraj Kupawad Nashik Jalgaon Ahamadnagar Dhule Malegaon By order and in the name of Governor of Maharashtra, Sanjay Digitally signed by Sanjay Balkrishna Saoji DN: c=IN, o=Government Of Maharashtra, ou=UNDER SECRETARY, Balkrishna postalCode=400032, st=Maharashtra, 2.5.4.20=13f024b79c19b420653021e52311 db55b7964b2bc5c3642efdb26f8633f8af7f, serialNumber=be169cc754827a9bfadc916a Saoji c5c85a4c876ae29f24ca9e6f7c2064ada52d6 747, cn=Sanjay Balkrishna Saoji Date: 2016.09.20 18:30:55 +05'30' (Sanjay Saoji) Under Secretary to Government D Class Municipal Corporation DCR Development Control and Promotion Regulations for D Class Municipal Corporations in Maharashtra URBAN DEVELOPMNET DEPARTMENT, GOVERNMENT OF MAHARASHTRA (Sanctioned under Section 37(1AA) (c) of the Maharashtra Regional & Town Planning Act, 1966 vide Notification vide TPS-1812/CR-112/12/DCR D Class /UD-13 Dated 20/09/2016) D Class Municipal Corporation DCR 10.0 Procedure during Construction 20 10.1 Owners / Architect / Engineers liability 20 10.2 Documents at sites 20 10.3 Checking of plinth 21 10.4 Deviation during construction 21 10.5 Completion Certificate 21 10.6 Occupancy Certificate 21 10.7 Part Occupancy Certificate 21 11.0 Inspection 22 12.0 Unsafe Buildings 22 13.0 Revocation of Permission 22 14.0 Development undertaken on behalf of Government. 22 15.0 Items of operational construction by some authorities to be excluded 22 16.0 Discretionary Powers 24 16.1 Interpretation by Municipal Commissioner 24 16.2 Relaxation in Specific cases 24 17.0 Temporary Construction 24 18.0 Unauthorized development - liability for offences and penalties 25 19.0 Amendment to Appendices 25 20.0 NBC as reference 25 21.0 Clarification 25 PART II - GENERAL LAND DEVELOPMENT REQUIREMENTS 22 Requirement of site 26 22.1 Sites not eligible for construction of buildings 26 22.2 Distance of Site from Electric Lines 26 22.3 Construction within Blue and Red Flood Line 27 22.4 Development within 30 m. from Railway Boundary 27 22.5 Environmental Clearance 27 22.6 Development along Highways / Classified Roads 27 22.7 Development within 500 m. from the Jail Premises 28 22.8 Distances from land fill sites 28 22.9 Restrictions in the vicinity of Airport 28 22.10 Restrictions in the Vicinity of Ancient Monuments 28 22.11 Restrictions by Other Departments 28 22.12 Authorities to supply complete information to corporation 28 D Class Municipal Corporation DCR APPENDIX APPENDIX A-1 FORM FOR CONSTRUCTION OF BUILDING OR LAYOUT OF BUILDING/ 181 GROUP HOUSING APPENDIX A-2 FORM FOR SUB-DIVISION OF LAND AS PLOTTED LAYOUT 190 APPENDIX B FORM OF SUPERVISION 195 APPENDIX C LICENSING AND QUALIFICATIONS TO THE TECHNICAL PERSON 196 APPENDIX D-1 FORM FOR SANCTION OF BUILDING PERMISSION AND 199 COMMENCEMENT CERTIFICATE APPENDIX D-2 FORM FOR TENTATIVE APPROVAL FOR DEMARCATION OF LAND/ 200 SUB-DIVISION LAYOUT APPENDIX D-3 FORM FOR FINAL APPROVAL TO THE LAND SUB-DIVISION / LAYOUT 201 APPENDIX E-1 FORM FOR REFUSAL OF BUILDING PERMIT / COMMENCEMENT 202 CERTIFICATE APPENDIX E-2 FORM FOR REFUSAL OF LAND SUB-DIVISION / LAYOUT 203 APPENDIX F FORM FOR INTIMATION OF COMPLETION OF WORK UPTO PLINTH LEVEL 204 APPENDIX G FORM OF APPROVAL / DISAPPROVAL OF DEVELOPMENT WORK UPTO 205 PLINTH LEVEL APPENDIX H FORM FOR COMPLETION CERTIFICATE 206 APPENDIX I FORM FOR OCCUPANCY CERTIFICATE 207 APPENDIX J FORM FOR REFUSAL OF OCCUPANCY CERTIFICATE 208 APPENDIX K FORM OF INDEMNITY FOR PART OCCUPANCY CERTIFICATE 209 D Class Municipal Corporation DCR b) A copy of the approved drawings and specifications referred to in Regulation no.7.0 on the site in respect of which the development permission was issued. ii)Display board mentioning name of the owner, name of architects, name of structural engineer, details as per approved plan, except for small individual plot holders 10.3 Checking of plinth, columns upto plinth level- The owner through his licensed surveyor, engineer, structural engineer or supervisor or his architect, as the case may be, shall give notice in the form of Appendix-F to the Commissioner on completion of work upto plinth level and where there is no plinth, construction above general ground level upto 0.60 m.to enable and ensure that the work conforms to the sanctioned plans. The Commissioner may inspect the work jointly with the licensed technical personnel or architect within 15 (fifteen) days from the receipt of such notice and either grant or refuse permission for further construction as per the sanctioned plans in the form in Appendix -G. If within this period, the permission is not refused it shall be deemed to have been granted, provided the work is carried out strictly according to the sanctioned plans. 10.4 Deviation during constructions:-If during construction of a building any deviation of a substantial nature from the sanctioned plans is intended by way of internal or external additions, sanction of the Commissioner shall be necessary. A revised plan showing such deviation shall be submitted and the procedure laid down for the original plans shall apply to all such amended plans. Any work done in contravention of the sanctioned plans, without prior approval of the Commissioner shall be deemed as unauthorized. However, any changes made within the internal layout of a residential or commercial unit, which do not violate FSI or other regulations, shall not be treated as unauthorised. Such changes shall be incorporated in plan along with completion certificate. 10.5 Completion certificate:-The owner through his licensed surveyor / engineer / structural engineer/ supervisor or his architect, as the case may be, who has supervised the construction, shall furnish a building completion certificate to the Commissioner in the form in Appendix-H This certificate shall be accompanied by three sets of plans of the completed development 10.6 Occupancy certificate:-The Commissioner after inspection of the work and after satisfying himself that there is no deviation from the sanctioned plans, issue an occupancy certificate in the form in Appendix-I or refuse to sanction the occupancy certificate in Appendix - J within 21 days from the date of receipt of the said completion certificate, failing which the work shall be deemed to have been approved for occupation, provided the construction conforms to the sanctioned plans. One set of plans, certified by the Commissioner, shall be returned to the owner alongwith the occupancy certificate. Where the occupancy certificate is refused or rejected, the reasons for refusal or rejection shall be given in intimation of the rejection or the refusal In case of building identified in Regulation No.6.2.2.g, the occupancy certificate shall be issued by the Municipal Commissioner, only after the clearance from the Chief Fire Officer, regarding the completion of the work from fire protection point of view. 10.7 Part occupancy certificate:- When requested by the holder of the development permission, the Commissioner may issue a part occupancy certificate for a building or part thereof, before completion of the entire work, as per development permission, provided sufficient precautionary measures are taken by the holder to ensure public safety and health. The occupancy certificate shall be subject to the owners indemnifying the Commissioner in the form in Appendix- K D Class Municipal Corporation DCR 21 APPENDIX „F‟ FORM FOR INTIMATION OF COMPLETION OF WORK UPTO PLINTH LEVEL To, The Municipal Commissioner, ___________ Municipal Corporation Sir, The construction up to plinth / column up to plinth level has been completed in Building No ______________Plot No ______________, Revenue Survey No.____________, City Survey No.________________, Village______________SectorNo.________Ward No.____________, situated at Road/Street ________________,Society____________ in accordance with your permission No _________ dated ___________________ under my supervision and in accordance with the sanctioned plan. Please check the completed work and permit me to proceed with the rest of the work. Yours faithfully Signature of Architect /Licensed Engineer/ Structural Engineer/Supervisor Name : ______________________ (In Block Letters)_______________ Address : ____________________ ____________________ ____________________ E-mail ID : ___________________ Mobile No.: ___________________ Date: ________________ D Class Municipal Corporation DCR 204 APPENDIX „G‟ FORM OF APPROVAL / DISAPPROVAL OF DEVELOPMENT WORK UPTO PLINTH LEVEL To, _________________ _________________ _________________ Sir, Please refer to your intimation No _____________________ dated _____________________ regarding the completion of construction work upto plinth / column upto plinth level in Building No _______________ Plot No ____, Revenue Survey No.____________, City Survey No.________________, Village______________SectorNo.________WardNo.____________,situated at Road/Street ________________,Society______________ You may proceed / are not allowed to proceed with the further work as per sanctioned plans / as the construction upto plinth level does / does not confirm to the sanctioned plans. Yours faithfully, Municipal Commissioner, _________Municipal Corporation Office No ___________________________ Office Stamp ________________________ Date : ______________________________ D Class Municipal Corporation DCR 205 UDCPR-2020 UNIFIED DEVELOPMENT CONTROL AND PROMOTION REGULATIONS FOR MAHARASHTRA STATE. I UDCPR-2020 II UDCPR-2020 Applicable to all Planning Authorities and Regional Plan areas except Municipal Corporation of Greater Mumbai, Other Planning Authorities / Special Planning Authorities / Development Authorities within the limit of Municipal Corporation of Greater Mumbai, MIDC, NAINA, Jawaharlal Nehru Port Trust, Hill Station Municipal Councils, Eco-sensitive / Eco-fragile region notified by MoEF & CC and Lonavala Municipal Council, in Maharashtra. GOVERNMENT OF MAHARASHTRA URBAN DEVELOPMENT DEPARTMENT III UDCPR-2020 INDEX Regulation Particulars Page No. No. CHAPTER – 1 ADMINISTRATION 1.0 Short Title, Extent and Commencement 1 1.1 Extent and Jurisdiction 1 1.2 Commencement of Regulations 1 1.3 Definitions 1 1.4 Applicability of Regulations 17 1.5 Saving 18 1.6 Applicability of Other Regulations 19 1.7 Power to Prescribe the Proformas 19 1.8 Power to Decide Charges 19 1.9 Meanings as in Acts, Rules & Interpretations 19 1.10 Removal of Difficulties 20 CHAPTER – 2 DEVELOPMENT PERMISSION AND COMMENCEMENT CERTIFICATE 2.1 Permission from the Planning Authority is Mandatory 21 2.1.1 Necessity of Obtaining Permission 21 2.1.2 Permission Not Necessary 21 2.1.3 Development Undertaken on Behalf of Government 22 2.1.4 Operational Constructions 22 2.1.5 Constructions Not Covered Under the Operational Constructions 23 2.1.6 Temporary Constructions 23 2.1.7 Repairs to Building 24 Procedure for Obtaining Development Permission / Building Permission / 2.2 24 Commencement Certificate 2.2.1 Notice/ Application 24 2.2.2 Information Accompanying Notice / Application 24 2.2.3 Ownership Title and Area 24 2.2.4 Key Plan or Location Plan 25 2.2.5 (a) Sub-division Layout Plan 25 2.2.5 (b) Amalgamation Plan 26 2.2.6 Site Plan 26 2.2.7 Building Plan 26 2.2.8 Building Plans for Special Buildings 27 2.2.9 Service Plan 28 V UDCPR-2020 2.2.10 Supervision 28 2.2.11 Clearance From Other Departments 28 2.2.12 Building / Layout Permission Scrutiny Fee 29 2.2.13 Development Charges 29 2.2.14 Premium Charges and Fire Infrastructure Charges. 30 2.2.15 Structural Stability Certificate 31 2.2.16 Signing the Plan 31 2.2.17 Size of Drawing Sheets 31 2.2.18 Colouring Notations for Plans 32 Qualification and Competence of the Architect / Licensed Engineer / 2.2.19 32 Structural Engineer / Town Planner / Supervisor 2.3 Discretionary Powers – Interpretation 33 2.4 Discretionary Powers - Relaxations in Specific Cases 33 2.5 Drafting Error 34 2.6 Grant or Refusal of Permission 34 2.6.1 General 34 2.6.2 Deemed Permission 34 2.6.3 Approval of building permission on Risk Based Classification 35 2.6.4 Display of Sanctioned Permissions on Authority's Web-Site. 35 2.7 Commencement of Work 35 2.7.1 Commencement 35 2.7.2 Development of Land Subdivision/ Group Housing Schemes 36 2.8 Procedure During Construction 36 Owner / Developer / Architect / Town Planner / Engineer / Structural 2.8.1 Engineer / Supervisor or any licensed technical person's Responsibilities 36 in Their Respective Domain. 2.8.2 Results of Test 36 2.8.3 Display Board 36 2.8.4 Plinth Checking 37 2.8.5 Deviation during Construction 37 2.9 Completion Certificate 37 2.10 Occupancy Certificate 37 2.11 Part Occupancy Certificate 38 2.12 Inspection 38 2.13 Unsafe Buildings 38 2.14 Offences and Penalties 38 2.15 Revocation of Permission 39 CHAPTER – 3 GENERAL LAND DEVELOPMENT REQUIREMENTS 3.1 Requirements of Site 41 VI UDCPR-2020 Appendix E-2 Form for Refusal of Land Sub-Division/ Layout 354 Appendix F Form for Intimation of Completion of Work up to Plinth Level 355 Appendix G Form for Completion Certificate 356 Appendix H Form for Full / Part Occupancy Certificate 357 Appendix I Form for Refusal of Occupancy Certificate 358 Appendix J Form of Indemnity for Part Occupancy Certificate 359 Appendix K Approvals of Building Permission Based on Risk Based Categorization 360 Appendix K-1 Form for Permission of Construction of Building on a plot upto 150 sq.m. 363 Appendix L Heritage List Card (Town & Region) 364 Appendix M Typical Plans & Cross-section of the Road. 369 PLANS Plan - A Nallahs Identified for Cycle Track in Nashik Municipal Corporation Area. 381 XV UDCPR-2020 i) Name and address of owner, developer, all concerned licensed persons. ii) Survey number / city survey number of land under reference. iii) Order number and date of grant of development / building permission / redevelopment permission issued by the Authority. iv) Built up area permitted. v) RERA registration no. Such Display Board shall not be required for individual plot holder's individual building. 2.8.4 Plinth Checking The owner shall give intimation in the prescribed form in Appendix- F to the Authority after the completion of work upto plinth level. This shall be certified by Architect / licensed Engineer / Supervisor with a view to ensure that the work is being carried out in accordance with the sanctioned plans. After such intimation, the construction work shall be carried out further. The officers of the Authority, who are empowered to grant development permission and subordinate officers to him, shall each, inspect about 10% of such plinth certified cases. 2.8.5 Deviation During Construction If during construction of a building, any deviation of a substantial nature from the sanctioned plans is intended by way of internal or external additions, sanction of the Authority shall be necessary. A revised plan showing the deviation shall be submitted and the procedure laid down for the original plans shall apply to all such amended plans. Any work done in contravention of the sanctioned plans, without prior approval of the Authority, shall be deemed as un-authorised. However, any changes made within the internal layout of a residential or commercial unit, which do not violate FSI or other regulations, shall not be treated as unauthorised. Such changes shall be incorporated in plan along with completion certificate. Provided that revised permission may also be granted after completion of work before obtaining full occupancy certificate. 2.9 COMPLETION CERTIFICATE The owner through his Architect / licensed engineer / town planner / supervisor, as the case may be, who has supervised the construction, shall furnish a building completion certificate to the Authority in the form in Appendix-G. This certificate shall be accompanied by three sets of plans of the completed development, the certificate about the operation of the lift from consultant and certificate of structural stability, wherever necessary. In case of special buildings, the Completion Certificate shall also be accompanied with the NOC from Chief Fire Officer of respective Authority or Director of Fire services, as the case may be. 2.10 OCCUPANCY CERTIFICATE The Authority after inspection of the work and after satisfying himself that there is no deviation from the sanctioned plans as mentioned in Regulation No. 2.8.5, issue an occupancy certificate in the form in Appendix-H or refuse to sanction the occupancy certificate in Appendix-I within 21 days from the date of receipt of the said completion certificate, failing which the work shall be deemed to have been approved for occupation, provided the construction conforms to the sanctioned plans. One set of plans, certified by the Authority, shall be returned to the owner along with the occupancy certificate. Where the occupancy certificate is refused or rejected, the reasons for refusal or rejection shall be given in intimation of the rejection or the refusal The 37 UDCPR-2020 APPENDIX 'F' FORM FOR INTIMATION OF COMPLETION OF WORK UP TO PLINTH LEVEL* To, The Authority, Planning Authority /Collector Sir, The construction up to plinth / column up to plinth level has been completed in Building No ______________ Plot No……… Revenue S.No.……./ Gat No........./ Khasara No........ / City Survey No…………../ Final Plot No........., Mouje ……situated at Road/Street __________,Society____________ in accordance with your permission No _________ dated ___________________ under my architectural / technical supervision and construction is carried out strictly in accordance with the sanctioned plan upto plinth level. This is for information to you and we are proceeding further with the remaining construction work. Yours faithfully Signature of Architect/Licensed Engineer/ /Supervisor Name : ______________________ (In Block Letters)`_______________ Address :____________________ ____________________ E-mail ID: ___________________ Mobile No.: ___________________ Date: ________________ 355 UDCPR-2020 APPENDIX 'G' FORM FOR COMPLETION CERTIFICATE To, The Authority, Planning Authority /Collector Sir, I hereby certify that the erection / re-erection or part/ full development work in / on building / part building No ____________ Plot No……… Revenue S.No.……./ Gat No........./ Khasara No........ / City Survey No…………../ Final Plot No........., Mouje ……has been supervised by technical person and has been completed on ___________ without any departures of substantial nature according to the plans sanctioned, vide office communication No. _____________ dated ______________. The work has been completed as per sanctioned plan. No provisions of the Act or the building Regulations, no requisitions made, conditions prescribed or orders issued thereunder have been transgressed, except * a few changes made within the internal layout of residential or commercial units, which do not violate FSI or other regulations, in the course of the work. I am enclosing three copies of the completion plans. The building is fit for occupancy for which it has been erected/ re-erected or altered, constructed and enlarged.** I have to request you to arrange for the inspection & grant permission for the occupation of the building. Yours faithfully (Signature of Owner) Encl : As above. Name of Owner (in Block Letters) Date : Signature and name of Architect /Licensed Engineer/Supervisor * Wherever applicable. ** Delete whichever is not applicable. 356