s u Amol Kshirsagar Architectural Planner, Annexure - B Consulting Engineer & Valuer FORM - 2 [See Regulation 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Proj ect and for Withdrawal of Money from Designated Bank Account) Date:05-01-2024 To, SHANTAMA BUILD TEC, OFFICE NO 9, B WING NARAYAN PLAZA, CANNOUGHT PLACE, CIDCO, AURANGABAD Subject: Certificate of Cost Incurred for Development of AARAMBH COMMERCIAL SPACES having MahaREM Registration Number P51500051954 being developed by SHANTAMA BUILD TEC. Sir, 1. I / We AMOL KSHIRSAGAR have undertaken assignment of Certifyin/ij Estimated Cost for AARAMBH COMMERCIAL SPACES having MahaRERA Registration Number P515O0O51954 being developed by SHANTAMA BUILD TEC. 2" We have estimated the cost of Civil, MEP and Allied Works required for completion of the apartments & proportionate completion of internal & external works of the Project as per the specifications mentioned in the Agreement of Sale. Our estimated cost calculations are based on the Drawings/Plans made available to us for the Project under Reference by the Developers / Consultants. The Schedule of Items & Quantity required for the entire work as calculated by Quantity Surveyor* appointed by the Developer/Engineer, the assumption of the cost of material, labour & other inputs made by the Developer, and the Site Inspection carried out by us to ascertain / conflrm the above analysis given to us. estimate Total Estimated Cost of completion of the aforesaid Project mentioned under at Rs. 6,00,65,350/- (Total of Table A & B) at the time of Registration. The estimated I Cost of Project is with reference to the Civil, MEP & Allied Works completion of the & proportionate completion of internal & external work, as per the specifications in the Agreement of Sale & for the purpose of obtaining Occupation Certificate / Certificate for the Building(s) / Wing(s) / Layout / Plotted Development from the CIry AND DEVELOPMENT CORPORANON OF MAHARASHTRA (CIDCO), AURANGABAD being the Authority under whose jurisdiction the aforesaid Prqect is being implemented. 4. The Estimated incurred till date is calculated to Rs. 1,18, ofTableA&B). The Amount of . eest . Inqu r!'.ed. .is. .qa lc. .ulated . en. l used.,&. un it.c-oJt. of . ite.ms. Flat No.4, Plot No. 102, Nathprangan,Garkheda, Chhatrapati Sambhajinagar Mob. : 09960669921 The Balance Cost of completion of the Civil, MEP & Allied Works for completion of Apartments & propoftionate completion of internal & external works, as per specifications mentioned in Agreement of Sale, of the aforesaid Project is estimated at Rs. 4,82,77,373l- (Total of Table A & B). 6. I Certify that the cost of Civil, MEP & Allied Work for apartments & proportionate internal & external works, as per the specifications mentioned in Agreement of Sale, of the aforesaid project as completd on the date of this certificate is as given in Table A & B below: TABLE - A MRAMBH COMMERCIAL SPACES BUILDING S. No. Particulars Amount (in Rs.) 1. Total Estimated Cost of Building / Wing / Layout / Rs.5,84,74,4251- Plotted Development as on date of Reqistration is 2. Cost incurred as on date of Certificate - 31 Dec 2023 Rs. 1,16,82,885/- 3. Work Done in Percentage (as Percentage of Estimated 20o/o Cost) 4. Balance Cost to be incurred ** 1(based on Estimated Rs. 4,67,31,5401- Cost) 5. Cost incurred on Additional / Extra Items not included in the Estimated Cost (Table-C) TABLE - 8 Internal & External Development Works in respect of Registered phase AARAMBH COMMERCIAL SPACES BUILDING Total Estimated Cost of Internal & External Development Rs. 16,50,925/- Works including amenities & facilities in the Layout as on Cost incurred as on date of Certificate - 31 Dec 2023 Work Done in Percentage (as Percentage of Estimated Balance Cost to be incurred t* ((based on Estimated Rs. 14,85,833/- Cost incurred on Additional / Extra Items not included in the Estimated Cost Yours faithfully, \'r"\ AMOL KSHIRSAGAR Signature & Name (IN BLOCK LEITERS) with Local Authority License Number (if applicable) Agreed & Accepted by: Signature of Promoter Name: SHANTAMA BUILD TEC Date: 05-01-2024 Note: The scope of work is to complete Registered Real Estate Poect as per drawings approved from time to time as per specifications mentioned in the Agreement to Sale. (*) Quantity Survey can be done by the office of Engineer or can be done by an independent Quantity Surveyor, who's Certificate of Quantity Calculated, can be relied up on by Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place ma*ed (+) & in case quantity are being calculated by office of Engineer, the name of person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). (**) Balance Cost to be incurred (4) may vary from difference between Total Estimated Cost (1) & actual Cost incurred (2) due to deviation in quantity required / escalation of cos! etc. As this is an Estimated Cost any deviation quantity required for the Development of Real Estate Prolect will result in an amendment of the cost incurred / to be incurred. 4. All components of work with specificitions are indicative & not exhaustive 5. Please specify if there are any deviations / qualifications. Example: Any deviation in input material used from specifications in Agreement of Sale. TABLE - C List of Extra / Additional / Deleted ltems considered in the Cost (Which were not parts of the original Estimate of Total Cost) S. No. List of Extra / Additional / Deleted Items Amount (in Rs,) 1. 2. i=r- ^-1.