qa Amol Kshirsagar Architectural Planner, Consulting Engineer & Valuer Annexure A FORM 1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of ongoing project & for withdrawal of Mooey from Designated Account) Date: 15-04-2024 To, SHANTAMA BUILD TEC, OFFICE NO 9, B WING NARAYAN PLAZA, CANNOUGHT PLACE, CIDCO, AURANGABAD Subject: Certificate of Percentage of Completion of Construction Work of AARAMBH qOMMERCIAL SPACES having MahaRERA Registration Number p51500051954 being developed by SHANTAMA BUILD TEC. Sir, I / We Af€ll AMOL KSHIRSAGAR have undertaken assignment as Architect / Licensed Surveyor of certifying Percentage of completion of construction work of AARAMBH coMMERCTAL spAcEs having MahaRERA Registration Number P51500051954 being developed uy sHlitraMe etJItD TEc. Based on the Site hspection, with respect to the Layout / each Building/Wng of the aforesaid Real Estate I ceftify that as on date of this certificate, the percentage of work Done for each of the of the Real Estate ProJect under MahaREM is as per Table-A& B herein below. The of work executed with respect to each of the activity of entire phase is detailed in Table-B. Flat No.4, Plot No. 102, Nathprangan,Garkheda, Ghhatrapati Sambhajinagar Mob. : 09960669921 I ,il @ Amol Kshirsagar Architectural Planner, Consulting Engineer & Valuer TABLE-A AAMMBH COMMERCIAL SPACES BUILDING S, No, Tasks / Activity Percentage of Actual Work Done (As on date of the (1) _ Certificate) {4 (3) 1. 2. Excavation Basements (ifany) -- 100% 3. Podiums (if any) ------ 4. Plinth 700o/o 5. Stilt Floor 1000/o 6. Slab of Super Structure -_ 80% 7. Internal Walls, Internal plaster, Floorings, Doors, windows 500o/o within Flats / Premises 8. Sanitary Fittings witrin rnffi 20o/o 9. Staircases, Lift Wells & Lobbies at each Floor t_evel Overtre-aa 50% and Underqround Water Tanks 10. External Plumbing & External plaster, Elevation, Comptetion of 20o/o Terraces, with waterproofing of the Buildinq / Winq 11. Installation of Litu, Water pumps, Fire fighting Fittings aM 50o/o Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compljance to condjtions of Environment / CM NOC, Finishing to Entrance Lobby/s, plinth protection, paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications to Agreement of Sale, Any other Activitv TABLE-B Common Areas (internal & External Devejopment Works) in respect of AARAMBH COMMERCIAL SPACES BUILDING Common Areas & Facilities Proposed Percentag (Yes / e of actual No) Work Done (As on date of Certificate Internal Tar Or Cement Flat No.4, Plot No. 102, Nathprangan,Garkheda, iiad Chhatrapati Sambhajinagar Mob. : 09960669921 Amol Kshirsa af Sewerage (Chamber, Lines, Septic Treatment & Disposal of Sewage and Water Conservation / Rain Water Fire Protection & Fire Safety Electrical Meter Room, Sub-Statlon, Aggregate area of recreational Open ihli ffi Yours faithfully, ANGtI'AMOL KSHIRSAGAR Signature & Name (IN BLOCK LETTERS) of Land Surveyor / Architect License Number () & Accepted by: ,Q,,o o,., AMA BUILD TEC 2024 Flat No.4, Plot No. 102, Nathprangan,Garkheda, Chhatrapati Sambhajinagar Mob. : 09960669921 ,r T I f,