Er. Abhoy Potil Civil Engg Anrexuse - B FORM - 2 [See Regulation 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for Withdrawal of Money from Designated Bank Account) Date:02-01-2025 To, BALAJI INFRA, PLOT NO 2, AMBIKA NAGAR, NEAR JALGAON ROAD, CHHATRAPATI SAMBHAJINAGAR431OOS Subject: Certificate of Cost lncurred for Development of SHIV PARK-2 having MahaRERA Registration No. P51500051760bein9 developed by BALAJI INFRA Sir, 1. l/We Er. ABHAY PATlLhave undertaken assignment of Certifying Estimated Cost for SHIV PARK-2 having MahaRERA Registration No. P51 500051760bein9 developed by BALAJI INFRA. 2. We have estimated the cost of Civil, MEP and Allied Works required for completion of the apartments & proportionate completion of internal & external works of the Project as per the specifications mentioned in the Agreement of Sale. Our estimated cost calculations are based on the Drawings/Plans made available to us for the Project under Reference by the Developers / Consultants. The Schedule of ltems & Quantity required for the entire work as calculated by Quantity Surveyor* appointed by the Developer/Engineer, the assumption of the cost of material, labour & other inputs made by the Developer, and the Site lnspection carried out by us to ascertain / confirm the above analysis given to us. 3. We estimate Total Estimated Cost of completion of the aforesaid Project mentioned under reference at Rs.5,97,74,130/- (Total of Table A & B) at the time of Registration. The estimated Total Cost of Project is with reference to the Civil, MEP & Allied Works completion of the apartments & proportionate completion of internal & external works, as per the specifications mentioned in the Agreement of Sale & for i the purpose of obtaining Occupation Certificate Completion Certificate for the / / Building(s) / Wing(s) Layout Plotted Development from the CHHATRAPATI SAMBHAJTNAGAR MUN|C|PAL CORPORATTON (EARTWHTLE AURANGABAD Er. Abhoy Potil Civil Engg MUNICIPAL CORPORATION) being the Planning Authority under whose jurisdiction the aforesaid Project is being implemented. 4. The Estimated Cost incurred till date is calculates to Rs.3,51 ,01 ,404/-(Total of Table A & B). The Amount of Eslim.ated..Qest.lncu!'.r.ed..i9..9al.sul.a.ted..en..the..has!s..sf.input m.dends-19erviQ.e..E..u.ged.&.unt!..-c-o.9l.cf .Lheae.it-e.m.9. 5. The Balance Cost of completion of the Civil, MEP & Allied Works for completion of Apartments & proportionate completion of internal & external works, as per specifications mentioned in Agreement of Sale, of the aforesaid Project is estimated atRs.2,46,72,7261 (Total of Table A & B). 6. I Certify that the cost of Civil, MEP & Allied Work for apartments & proportionate internal & external works, as per the specifications mentioned in Agreement of Sale, of the aforesaid Project as completed on the date of this certiflcate is as given in TableA&Bbelow: TABLE - A ForNew ShivPark-2-A&BBu S. Particulars Amount (in Rs.) No. 1. Total Estimated Cost of Building / Wing / Layout / Rs. 5,21,43,390/- Plotted Development as on date of Registration is Cost incurred as on date of Certiflcate Rs.3,12,86,034/- 31 D6cember2024 3. Work Done in Percentage (as Percentage of 60Yo Estimated Cost) 4. Balance Cost to be incurred "- ((based on Rs. 2,08,57,3561 Estimated Cost) 5. Cost incurred on Additional / Extra ltems not included in the Estimated Cost (Table-C) TABLE - B lnternal & External Development Works forNew Project Shiv Park - 2 - A& B Building S. Particulars Amount (in Rs.) No. 1. Total Estimated Cost of lnternal & External Rs. 76,30,7401 Development Works including amenities & facilities in the Layout as on date of Registration iS 2. Cost incurred as on date of Certificate Rs. 38, 15,3701 31 Decembe12024 .> Work Done in Percentage (as Percentage of 50o/o 4*\ Estimated Cost) +l csr4f-lYl.ll L- Er. Abhoy Potil Civil Engg .. ((based on Rs.38,'15,370/- 4. Balance Cost to be incurred 5. Cost incurrea on Additional / Extra ltems not included in the Estimated Cost (Table-C Yours faithfullY, ix------____rrl L_ ET. ABHAY PATIL Local Authority License Number: Agreed & AccePted bY: Signature of Promoter < f Name;BALAJI INFRA Date:02-01-2025 Note: l.TheSoopeofworkistocompleteRegisteredRealEstateProjectasperdrawings approvecl from time to time as per specifications mentioned in the Agreement to Sale. 2. (.) Quantity Survey can be done by the office of Engineer or can be done by an inoep"noentQuantitySurveyor'who,scertificateofQuantitycalculated,canbe relied up on by Engineer. ln case of independent quantity surveyor being (.) & appointed byDeveloper, the name has to be mentioned at the place marked in case quantity are being calculated by office of Engineer' the name of person in theofficeofEngineer,whoisresponsibleforthequantitycalculatedshouldbe mentioned at the Place marked (.). 3. (.-) Balance Cost to be incurred (4) may vary from difference between Total EstimatedCost(1)&actualCostincurred(2)duetodeviationinquantity required / escalation of cost etc. As this is an Estimated cost any deviation quantityrequiredfortheDevelopmentofRealEstateProjectwillresultinan amendment of the cost incurred / to be incurred' 4. All components of work with specifications are indicative & not exhaustive Er. Abhoy Potil Civil Engg 5. Please specify if there are any deviations / qualifications. Example. Any deviation in input material used from specifications in Agreement of Sale. TABLE - C List of Extra / Additional / Deleted ltems considered in the Cost (Which were not parts of the original Estimate of Total Cost) S. No. List of Extra / Additional / Deleted Amount (in Rs.) Items 1. 2.