PARMESHWAR GOVIND GAWALI Arch. Annexure A FORM 1 [See Regulation 3] ARCHITBCT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date: L3-07-2024 To, BALA'I INFRA, PLOT NO 2, AMBIKA NAGAR, NEAR JALGAON ROAD, CHHATRAPATI SAMBHAJINAGAR-431008 Su bject: Certificate of Percentage of Completion of Construction Work of SHIV PARK- 2having MahaRERA Registration No. P51500051750being developed by BAWI INFRA Sir, l/ WeArch. MT.PARMESHWAR GOVIND GAWALlhave undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of SHIV PARK-2 having MahaRERA Registration No. P51500053337 being developed by BALA',I INFRA Based on the Site lnspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A1-A9 herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A ForProject Shiv Park - 2 A1 Building S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) ')- Excavation to0% 2 X number of Basement(s) and Plinth 3 X number of Podiums 4 Stilt Floor LOO% 5 X number of Slabs of Super Structure L00% PARMESHWAR GOVIND GAWATI Arch. 5 lnternal walls, lnternal Plaster, Floorings within L00% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 700% Fittings within the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level 700% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, L00% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings 700% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRz NOc, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A ShivPark-2A2 S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) l2l (3) 7 Excavation 700% 2 X number of Basement(s) and Plinth 3 X number of Podiums 4 Stilt Floor o% 5 X number of Slabs of Super Structure 0% 6 lnternal walls, lnternal Plaster, Floorings within o% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical o% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level o% connecting Staircases and Lifts, Overhead and Underground Water Tan ks. 9 The external plumbing and external plaster, elevation, o% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings o% PARMESHWAR GOVIND GAWALI Arch. and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Win8, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A ShivPark-2A3 S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Exca vat ion 0% 2 X number of Basement(s) and Plinth 3 X number of Podiums 4 Stilt Floor 0% 5 X number of Slabs of Super Structure o% 6 lnternal walls, lnternal Plaster, Floorings within o% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical o% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level o% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittlngs o% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate PARMESHWAR GOVIND GAWALI Arch. TABLE.A ForPro ShivPark-2A4 S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation o% 2 X number of Basement(s) and Plinth 3 X number of Podiums 4 Stilt Floor o% 5 X number of Slabs of Super Structure o% 6 lnternal walls, lnternal Plaster, Floorings within o% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical o% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level O%o connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings o% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and'all other requirements as may be required to Obtain occupation /Completion Certificate TABLE-A ShivPark-2A5 S. No, Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation o% 2 X number of Basement(s) and Plinth 3 X number of Podiums 4 Stilt Floor o% 5 X number of Slabs of Super Structure o% o lnternal walls, lnternal Plaster, Floorings within o% PARMESHWAR GOVIND GAWALI Arch. Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 0% Fittings within the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level o% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, o% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings o% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A ShivPark-2A6 S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation o% z X number of Basement(s) and Plinth 3 X number of Podiums 4 Stilt Floor o% 5 X number of Slabs of Super Structure o% 6 lnternal walls, lnternal Plaster, Floorings within o% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical o% Fittings within the Flat/Premises o Staircases, Lifts Wells and Lobbies at each Floor level o% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, o% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings o% and Equipment as per CFO NOC, Electrical fittings to PARMESHWAR GOVIND GAWATI Arch. Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to obtain occuoation /Completion Certificate TABLE.A ShivPark-281 S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 7 Excavation 100% 2 X number of Basement(s) and Plinth too% 3 X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 700% 6 Internal walls, lnternal Plaster, Floorings within 700% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical too% Fittings within the Flat/Premises _ 8 Staircases, Lifts Wells and Lobbies at each Floor level TOOo/o connecting Staircases and Lifts, Overhead and Undergrou nd Water Tanks. 9 The external plumbing and external plaster, elevation, 700% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings o% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate PARMESHWAR GOVIND GAWALI Arch. TABLE.A ShivPark-282 S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation tOOo/o 2 x number of Basement(s) and Plinth too% 3 X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 700% 6 lnternal walls, lnternal Plasler, Floorings within 1-OO% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 100% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 700% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 700% completion of terraces with waterproofing of the Buildine/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings o% and Equipmcnt as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRz NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABTE.A ForProject Shiv Park - 2 83 Building S. No. Tasks / Activity Percentage of Actual work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 700% 2 X number of Basement(s) and Plinth 700% 3 X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 700% PARMESHWAR GOVIND GAWALI Arch. 6 lnternal walls, lnternal Plaster, Floorings within 1.00% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 100% Fittings within the Flat/Premises o Staircases, Lifts Wells and Lobbies at each Floor level 100% connecting Staircases and Lifts, Overhead and Undergrourrd Water Tanks. I The external plumbing and external plaster, elevation, 100% completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings oo% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-B Common Areas (lnternal & External Development Works) in respect of ForNew Project Shiv Park- 2-A & B Buildings S. No. Common Areas & Facilities Proposed Percentage of actual Details (Yes / NOI Work Done (As on date of Certificate) (1) (2) (3) (4) (s) 1. lnternal Roads & Footpaths YES oo% Cement Roads 2. Water Supply YES 50% From Bore-well 3. Sewerage (Chamber, Lines, YES 00% Drainage Line & Septic Tank, STP) Septic Tank 4. Strom Water Drains NO N.A. 5. Landsca ping & Tree Planting YES oo% As Per Norms 5. Street Lighting YES oo% Street Light in theproiect 7. Community Bulldings NO N.A. 8. Treatment & Disposal of Sewage NO N.A. and Sullage Water 9. Solid Waste Management & NO N.A. Disposal PARMESHWAR GOVIND GAWATI Arch, 10. Water Conservation / Rain Water YES oo% Rain Water Harvesting Ha rvesting !1. Energy Management NO N.A. 72. Fire Protection & Fire Safety NO N.A. requirements 13. Electrical Meter Room, Sub- NO N.A. Station, Receiving Station 74. Aggregate area of recreational YES OOo/o Open Space Open Space 15. Others (Option to Add more) NO N.A. Yours faithfully, Arch. PARMESHWAR GOVIND GAW, License Number Agreed & Accepted by: signature of Promot# W ( r Name:BALA.,l INFRA Date:13-07-2024