Annexure A FORM 1 ISee Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:06-01-2024 To, BALAJ! INFRA, PLOT NO 2, AMBIKA NAGAR, NEAR JALGAON ROAD, CHHATRAPATT SAMBHAJTNAGAR-431008 Subject: Certificate of Percentage of Completion of Construction Work of SHIV PARK-2 having MahaRERA Registration No. P51500053337 being developed by BAIAJ! INFRA Sir, I/ We Arch. Mr. PARMESHWAR GOVIND GAWALT have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of SHIV PARK-2 having MahaRERA Registration No. P51500053337 being developed by BAIAJI INFRA. Based on the Site lnspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on.date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A1-A9 herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABtE.A For Project Shiv Park - 2 AL Building S. No. Tasks / Activity Percentage of Actual Work Done As on date of the Certificate (1) (21 (3) L Excavation LOO% 2 X number of Basement(s) and Plinth LOO% 3 X number of Podiums 4 Stilt Floor too% 5 X number of Slabs of Super Structure 700% 6 lnternal walls, lnternal Plaster, Floorings within 70% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical o0% Fittines within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level oo% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 00% completion of terraces with waterproofing of the Bulldine/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings oo% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABTE-A - For Project Shiv Park -2 A2 Building S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (3) (1) l2l 1 Excavation LOO% 2 X number of Basement(s) and Plinth too% 3 X number of Podiums 4 Stilt Floor 100% 5 X number of Slabs of Super Structure LOO% 6 lnternal walls, lnternal Plaster, Floorings within 70% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 00% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 00% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 00% completion of terraces with waterproofing of the Buildine/Wine 10 lnstallation of lifts, water pumps, Fire Fighting Fittings oo% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A For Project Shiv Park - 2 A3 Building S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 700% 2 X number of Basement(s) and Plinth 700% 3 X number of Podiums 4 Stilt Floor LOO% 5 X number of Slabs of Super Structure 100% 6 lnternal walls, lnternal Plaster, Floorings within 70% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 00% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level o0% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 00% completion of terraces with waterproof ing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings o0% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to I I Obtai. Occuoation /Comoletion Certificate I I TABLE.A For Project Shiv Park - 2 A4 Building S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) LOO% 7 Excavation LOO% 2 X number of Basement(s) and Plinth 3 X number of Podiums LO0% 4 Stilt Floor X number of Slabs of Super Structure 700% 5 lnternal walls, lnternal Plaster, Floorings within 70% 6 Flats/Premises, Doors and Windows to each of the Flat/Premises 00% 7 Sanitary Fittings within the Flat/Premises, Electrical Fittinss within the Flat/Premises o0% 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. oo% 9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Buildine/Wing 00% 10 lnstallation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A For Project Shiv Park - 2 A5 Building S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) t Excavation t00% 2 X number of Basement(s) and Plinth L00% / 3 X number of Podiums 4 Stilt Floor t00% 5 X number of Slabs of Super Structure 700% 5 lnternal walls, lnternal Plaster, Floorings within 70% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical oo% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 00% connecting Staircases and Lifts, Overhead and Undersround Water Tanks. 9 The external plumbing and external plaster, elevation, oo% completion of terraces with waterproofing of the Buildine/Wine 1.0 lnstallation of lifts, water pumps, Fire Fighting Fittings o0% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate , TABLE.A For Projdct Shiv Park - 2 A6 Building S. No. Tasks / ectivity Percentage of Actual Work Done (As on date of the Certificate) (1) (21 (3) 1 Excavation to0% 2 X number of Basement(s) and Plinth L00% 3 X number of Podiums 4 Stilt Floor '' 100% 5 X number of Slabs of Super Structure 100% 6 lnternal walls, lnternal Plaster, Floorings within 70% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical oo% Fittings within the Flat/Premtses 8 Staircases, Lifts Wells and Lobbies at each Floor level oo% connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 00% completion of terraces with waterproofing of the Buildine/Wine 10 lnstallation of lifts, water pumps, Fire Fighting Fittings 00% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABtE.A For Project Shiv Park -2Bt Building S. No. Tasks / Rctivity Percentage of Actual Work Done (As on date of the Certificate) (1) l2l (3), L Excavation 100% 2 X number of Basement(s) and Plinth lo0% 3 X number of Podiums 00% 4 Stilt Floor o0% 5 X number of Slabs of Super Structure 00% 6 lnternal walls, lnternal Plaster, Floorings within oo% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 00% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 00% connecting Staircases and Lifts, Overhead and Underqround Water Tanks. 9 The external plumbing and external plaster, elevation, o0% completion of terraces with waterproofing of the Building/Wing f lnstallation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment' Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to o bta i n occu pati o n /coqplelg n!94{[9]9 For Project Shiv Park -282 Building Tasks / Activity Percentage of Actual Work S. No. Done (As on datg slqg J94if-199!9I (2) (3) (1) Ewearrrt in n !00% 1 700% 2 X number of Basement(s) and Plinth v nrrmhor of Podirrms 00% 3 c+il+ El^^r 0Oo/o 4 LOO% 5 X number of Slabs of Super Structure o0% 6 *.llt, lnternal Plaster, Floorings within int"rn.l-t"rn.l Flats/Premises, Doors and Windows to each of the I Elaf /Dra rn ic.p( o0% 7 Sanitary Fittings within the Flat/Premises, Electrical Ei+rihdc rrrithin the Flat/Premises oo% 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and I tndorornrrnd \A/:tpr Tanks. o0% 9 The external plumbing and external plaster, elevation' completion of terraces with waterproofing of the Building/Wing 00% 10 lnstallation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment' Compliance to conditions of environment /CRZ NOC' Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABtE.A For Project Shiv Park - 2 83 Building S. No. Tasks / Rctivity Percentage of Actual Work Done (As on date of the Certificate) (1) l2l (3) L Excavation L00% 2 X number of Basement(s) and Plinth LOO% 3 X number of Podiums o0% 4 Stilt Floor 00% 5 X number of Slabs of Super Structure 00% 6 lnternal walls, lnternal Plaster, Floorings within 00% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 00% Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 00% connecting Staircases and Lifts, Overhead and Underqround Water Tanks. 9 The external plumbing and external plaster, elevation, 00% completion of terraces with waterproofing of the I Buildine/Wine 10 lnstallation of lifts, water pumps, Fire Fighting Fittings o0% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-B Common Areas (lnternal & External Development Works) in respect of For New Project Shiv Park -2- A & B Buildings S. No. Common Areas & Facilities Proposed Percentage of actual Details (Yes / No) Work Done (As on date of Certificate) (1) l2l (3) (4) (s) 1. lnternal Roads & Footpaths YES 00% Cement Roads 1 2. Water Supply YES 50% From Borewell 3. Sewerage (Chamber, Lines, YES 00% Drainage Line & Septic Tank, STP) Septic Tank 4. Strom Water Drains NO N.A. 5. Landscaping & Tree Planting YES 00% As Per Norms 5 Street Lighting YES o0% Street Light in the project 7 Community Buildings NO N.A. 8 Treatment & Disposal of Sewage NO N.A. and Sullage Water 9. Solid Waste Management & NO N.A. Disposal 10 Water Conservation / Rain Water YES 00% Rain Water Harvesting Harvesting 11. Energy Management NO N,A. 12. Fire Protection & Fire Safety NO N.A. requirements 13 Electrical Meter Room, Sub- NO N.A. Station, Receiving Station L4 Aggregate area of recreational YES 00% ' Open Space Open Space 15. Others (Option to Add more) NO N.A. Yours faithfully, Arch. PARMESHWAR GOVIND GAWAtt 6,b. License Number Agreed & Accepted by: Name: BAIAJI INFRA Date:05-01-2024