MANOJ KALA & ASSOCIATES KAL B 301, 302 Space Olympia, Sutgirni Chowk, Garkheda, Chh. SambhajiNagar 431005 Contact: +91 9637005781 | architecture@mkaa.co in FORM 1 (See Regulation 3| ARCHITECT'S CERTIFICATE (Tobe submitted at the time of Registration of Ongoing Project &for Withdrawal of Money from Designated Account) Date: - 03-01-2025 To. Satfron Associates, Chhatrapati Sambhajinagar (Aurangabad). Subject: Certificate of Percentage of Completion of Construction Work of Saffron Landmark having MahaRERA Registration Number P51500048247 being developed by Saffron Associates. Sir, Ihave undertaken assignment as Architect of Certifying Percentage of Completion of Construction Work of Saffron Landmark having MahaRERA Registration Number P51500048247 beingdeveloped by Saffron Associates. Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaidReal Estate Project, Icertify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. Date: 03/01/2025 Yours Faithfully, MANOJKALA Architect Architect Reg. No. CAI96/19597 Manoj Kala RegNo: CA/96/19597 MANOJ KALA & ASSOCIATES KAL B301, 302 Space Olympia, Sutgirni Chowk, Garkheda, Chh. Sambhaji Nagar 431005 Contact: +91 9637005781| architecture@mkaa,co.in TABLE-A Layout | Building / Wing Number (to be prepared separately for each Layout/Building/Wing of Project) Tasks / Activity Percentage of Actual No. Work Done (Ason date of the Certificate) (1) (2) (3) 100% 1. Excavation 100% 2. Basements (if any) No Podiums (if any) 100% 4 Plinth Ground Floor 100% 5. 75% 6. Slab of Super Structure Doors, 30% 7. Internal Walls, Internal Plaster, Floorings, windows within Flats / Premises 8 Sanitary Fittings within Flats/Premises 9. Staircases, Lift Wells & Lobbies at each FIoor Level Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, Completion of Terraces, with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipment's as per CFO NOC, Electrical Fittings, Mechanical Equipment's, Compliance to conditions of Environment /CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/VWing, Compound Wall and al other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity Date: 03/01/2025 Yours Faithfully, |MANOJ KALA KALA Architect Reg. No. CAI96/19597 Architect Manoj Kala RegNo:CA/96/19597 2| Pag e MANOJ KALA &ASSOCIATES KAL s S01, 302 Space Olynmpia, Sutgirrni Chowk, Garkheda, Chh. Sambhaji Nagar 431005 Contact: +91 9637005781 | architecturoomkaa co n TABLE-B Common Areas (lnternal &External Development Works) in rospect of the Registered Phase/ Project Number Porcontago of Dotalls S. Common Areas & Facilities Proposod nctual Work Dono No. (Yos/NO) (As on dato of Cortiflcato) (3) (4) (5) () (2) 40% Road Base 1 Internal Roads & Footpaths YES (Foundation) Partially Completed. Not yet started YES 2. Water Supply Not yet started 3 Sewerage (Chamber, Lines, YES Septic Tank, STP) Not yet started 4 Strom Water Drains NO 50% As per landscaping 5 Landscaping & Tree Planting YES drawing Not yet started YES 6 Street Lighting NA 7 Community Buildings NO of NO NA 8 Treatment & Disposal Sewage and Sludge Water NA Solid Waste Management & NO Disposal Not yet started 10. Water Conservation / Rain YES Water Harvesting Not yet started 11. Energy Management YES Fire Protection & Fire Safety YES 10% Partially Completed. 12. requirements Electrical Meter Room, Sub- YES Not yet started 13. Station, Receiving Station 14 Others (Option to Add more) NA Date: 03/01/2025 Agreed &Accepted by: Yours Faithfully, MANOJ KALA C i t yP r i d e Architect Aurangabad Architect Reg. No. CAI96/19597 Signatúre of Promoter Manoj Kala Name: Saftron Assoclates NCARAS A RegNo:CA/96/19597 Date: 03/01/2025 3| Page