Er Amo! Sonawane (civirrnee) Chhatrapati SambhajiNagar, Mobile No. 7083737809 Annexure - B FORM - 2 [See Regulation 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for Withdrawal of Money from Designated Bank Account) Date:18-07-2024 To, Mr. |yot Niranjan fadhav, Plot No 18 and 34 jain Mandir Road, N.3 CIDCO, AURANGABAD-03 Subject: Certificate of Cost Incurred for Development of LA MAISON 18/34 having MahaRERA Regishation Number P51500050155 being Developed by Mr. |yot Niranjan Jadhav. Sir, 1. I / We Er. Amol Sonawane have undertaken assignment of Certifying Estimated Cost for LA MAISON 1fl34 having MahaRERA Registration Number P51500050155 being Developed by Mr. fyot Niranjan fadhav. We have estimated the cost of Civil, MEP and Allied Works requirdd for completion of the aparhnents & proportionate completion of internal & external works of the Proiect as per the specificatioru mentioned in the Agreement of Sale. Our estimated cost calculations are based on the Drawings/Plans made available to us for the Project under Reference by the Developers / Consultants. The Schedule of Items & Quantity required for the entire work as calculated by ER, Amol Sonawane Quantity Surveyor* appointed by the Developer/ Engineer, the assumption of the cost of matedal, labour & other inputs made by the Developer, and the Site Inspection caried out by us to ascertain / confirm the above analysis given to us. J. We estimate Total Estimated Cost of completion of the aforesaid Project mentioned under reference at Rs.27,77,37,331/- (Total of Table A & B) at the time of Registration. The estimated Total Cost of Project is with reference to the Civil MEP & Allied Works completion of the apartments & proportionate completion of internal & external works, as per the specifications mentioned in the Agreement of Sale & for the purpose of obtaining Occupation Certificate / Completion Certificate for the Building(s) / Wng(s) / l,ayottt / Plotted Development from the CHHATRAPATI SAMBHAJI NAGAR Er Amol Sonawahe (civirrnee) Chhatrapati SambhajiNagar, Mobile No. 7 0837 37 8O9 MUNICIPAL CORPORATION (EARSTWHILE AURANGABAD MUNICIPAL CORPORATION) being the Planning Authority under whose jurisdiction the aforesaid Project is being implemented. The Estimated Cost incurred till date is calcuiates to Rs. Rs. 5,24,76,851,/- (Total of Table A & B). The Amount of .Eq.ti.qtetsd_.epe.t..Ut-c.sr.te.d..ic..cal-qlla!9d..9n.!.h-e-.b.asis..p..f .;r.1.psl .+.1a.t-e.{ia!s.l.qe.{yi.se-s-.q.c-ed .&..rrni!.ca9.t.af.th.e.ce.1!e11.1€. 5. The Balance Cost of completion of the Civil, MEP & Allied Works for completion of Apartments & proportionate completion of internal & external works, as per specifications mentioned in Agreement of Sale, of the aforesaid Project is estimated at Rs. 15,86,60,480/- (Total of Table A & B). 6. I Certify that the cost of Civil, MEP & Allied Work for apartments & proportionate internal & external works, as per the speci{ications mentioned in Agreement of Sale, of the aforesaid Project as completed on the date of this certificate is as given in Table A & B below: TABI,F, - A For La Maison t8/34 S. Particulars Amount (in Rs.) No, 1. Total Estimated Cost of Building / Wing / Layout Rs.20,49,87,700/ - / Plotted Development as on date of Registration is 2. Cost incurred as on date of Certilicate till 30th June RlS,-12,46,925 / - 2024 3. Work Done in Percentage (as Percentage of 25% Estimated Cost) 4. Balance Cost to be incurred .. ((based on Estimated Rs .1.5 ,37 ,40 ,775 / - Cost) 5. Cost incurred on Additional / Extra Items not NIL included in the Estimated Cost (Table-C) TABLE - B Internal & External Development Works for Building La Maison 18/34 S. Particulars Amount (in Rs.) No. 1. Total Estimated Cost of Internal & External Rs.614963-I/- Development Works including amenities & facilities in the Layout as on date of Registration is Er Amol Sonawah€ lcrvitrnggl Chhatrapati SambhajiNagar, Mobile No. 7083737809 2. irr"rtr"d as on date of Certificate 30th June Rs.-1229926 2024 -Cort W.* D."" ir-t P"".entage (as Percentage of 20% 3. Estimated Cost) Elance dst to be incnrred * (@ased on Estimated Rs.4919705 / - Cost) 5. C""t i.-r.*d o" Addifr."al / Extra Items not NIL included in the Estimated Cott (T{&-C)- P- Yours faithfully, Signature & Name with Stamp of Engineer Er. Amol Sonawane Local Authority License Number (if applicable) Agreed & Accepted bY: , , . ^t,./ ,1,./- h'I' l, Sigrfrture of Promoter Name: Mr. |yot Niranian fadhav Date:18-U7 -2O24 Note: 1. The scope of work is to complete Registered Real Estate Proiect as per drawings approved from time to time as per specifications mentioned in the Agreement to Saie' (.) Quantity Survey can be clone by the office of Engineer or can be done by an independent Quantity Surveyor, who's Certificate of Quantity Calculated' can be reliei up on by Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) & in case quantity Er Amol Sonawahe lcivirrnggl Chhatra pati SambhajiNaga r, Mobile No. 7 0837 37 809 are being calculated by office of Engineer, the name of person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). 3. (**) Balance Cost to be incurred (4) may vary from difference betrveen Total Estimated Cost (1) & actual Cost incurred (2) due to deviation in quantity required / escalation of cost etc. As this is an Estimated Cost any deviation quantity required for the Development of Real Estate Project will result in an amendment of the cost incurred / to be incurred. 4. All components of work with specifications are indicative & not exhaustive 5. Please specify if there are any deviations / quali{ications. Example: Any deviation in input material used from specifications in Agreement of Sale. TABLE - C List of Extra / Additional / Deleted Items considered in the Cost (Which were not parts of the original Estimate of Total Cost) S. No. List of Extra / Additional / Deleted Items Amount (in Rs.) 1. 2.