PLEASE USE THIS Annexure A FORM 1 MANGGAL DESIGN ARCHITECTS & INTERIOR DESIGNER [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project &for Withdrawal of Money from Designated Account) Date: 08-07-2023 To, VINAYAK ENTERPRISES, PLOT NO C/8 B/P, BEHIND MARUMOTERS, SATARA PARISAR, BEED BYPASS, AURANGABAD Subject: Certificate of Percentage of Completion of Construction Work of VINAYAK BUSINESS CENTRE having MahaRERA Registration Number P51500047881 being developed by VINAYAK ENTERPRISES Sir, I We MMs. Mangal Design Architects and Interior Designer have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of VINAYAK BUSINESS CENTRE having MahaRERA Registration Number P51500047881 being developed by VINAYAK ENTERPRISES Based on the Site Inspection, with respect to the Layout / each BuildingWing of the aforesaid Real Estate Project, Icertify that as on date of this Certificate, the Percentage of Work Done for each of the BuildingVWing of the Real Estate Project under MahaRERA is as per Table-A &Bherein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A VINAYAK BUSINESS CENTRE S. Tasks I Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 Basements (if any) 3 Podiums (if any) 4 Plinth 100% 5 Stilt Floor 100% 6 Slab of Super Structure 30% 7 Internal Walls, Internal Plaster, Floorings, Doors, 30% windows within Flats / Premises 8 Sanitary Fittings within Flats / Premises 1 MANGGAL ARCHINLcTs&NTEAIOR DESIONEA Ar.Promod Vithoba Ngrale 9. Staircases, Lift Wells & Lobbies at each Floor Level Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, Completion of Terraces, with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting-Fitings and Equipments as-per GFO-NOe, Electrical-Fitings, Mechanical Equipments, Gompliance to conditions of Environment CRZ NOG, Finishing to Entrance Lobby/s, Plinth Protection, Pavingof Areas appurtenant to BuildingWing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (Internal &External Development Works) for ProjectVINAYAK BUSINESS CENTRE Percentage of Details S. Common Areas &Facilities Proposed (Yes /NO) actual Nork Done No. (As on date of Certificate) (3) (4) (5) (1) (2) NO N.A. 1 Internal Roads &Footpaths 2. Water Supply YES 00% As per availability 3 Sewerage (Chamber, Lines, YES 0% Drainage Line till Septic Tank, STP) MIDC Line 4. Strom VWater Drains NO N.A. 5. Landscaping & Tree Planting NO N.A. 6. Street Lighting NO N.A. NO N.A. 7. Community Buildings N.A. 8. Treatment &Disposal of Sewage NO and Sullage Water 9 Solid Waste Management & NO N.A. Disposal 10. Water Conservation / Rain Water YES 00% Rain Water Harvesting Harvesting As per Norms NO N.A. 11. Energy Management N.A. 12. Fire Protection & Fire Safety NO requirements 13. Electrical Meter Room, Sub NO N.A. Station, Receiving Station 2 MANGGAL Ar.Pramod Vithoba Narale narale.pramodaComallcom 14. Aggregate area of recreational NO N.A. Open Space 15. Others (Option to Add more) Yours faithfully, For M/s. Mangal Design Architects and Interior Designer Signature &Name of Land Surveyor / Architect License Number MANGGAL ARCHITECTS A NTERIOA DESIGNEA Ar.Pramod Vithoba Narale narale.ramoc2omal.com Signatunre of Promoter Name: VINAYAK ENTERPRISES Date: 08-07-2023 3