Archipel Architects Architects, Plonners, lnlerior Designers *' *;if :liHff :illli', 3lli,lil1"n"'"' Ar.Kopil Guiorothi Annexure A FORM 1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date: 05-10-2023 To, RAJYOG DEVELOPERS, OFFICE NO-E, THIRD FLOOR, SAAM SQUARE, NIRALA BAZAR,, CHHATRAPATI SAMBHAJI NAGAR (AURANGABAD) Subject: Certificate of Percentage of Completion of Construction Work of SAIRAAJ HEIGHTS having MahaRERA Registration Number [!!Q@!$Q! beins developed by Sir, I / We ARCHIPEL Architect / Licensed Surveyor of Certifying Percentage of !!@\l]lffi having MahaRERA Registration by RAJYOG DEVELOPERS Based on the Site of the aforesaid Real Estate Project, I of Work Done for each of the Build is as per Table-A& B herein below. The of the activity of entire Phase is detailed in T TABLE.A SAIRAAJ HEIGHTS - A.WPE BUILDING S. Tasks / Activity Percentage of Actual Work No. Done I (As on date bf the Certificate (1) 1 xcavation 100 2. asements (if an\ ums (if anv) I 100% Stilt Floor 1000k Slab of Super Structure 7. lnternal Walls, lnternal Plaster windows within Flats / Premises 8. Sanitary Fittings within Flats / Premises 40o/o 9. Staircases, Lift Wells & Lobbies at each Floor Level 40% Overhead and Underqround Water Tanks 10. External Plumbing & External Plaster, Elevation, 400k Completion of Terraces, with waterproofing of the Buildinq / Winq 11. lnstallation of Lifts, Water Pumps, Fire Fighting Fittings and Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-A SAIRAAJ HEIGHTS - B-TYPE BUILDING S, Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1. Excavation 1000 2. Basements (if anv) c. Podiums (if any) 4. Plinth 100% Stilt Floor 100% 6. Slab of Super Structure 100o/o 7. lnternal Walls, lnternal Plaster, Floorings, Doors, 500h windows within Flats / Premises L Sanitary Fittings within Flats / Premises 5oo/o L Staircases, Lift Wells & Lobbies at each Floor Level 50% Overhead and Underqround Water Tanks '10. External Plumbing & External Plaster, Elevation, 50% | Completion of Terraces, with waterprooflng of the Buildinq / Winq 11. lnstallation of Lifts, Water Pumps, Fire Fighting Fittings and Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (lnternal & External Development Works) in respect of SAIRAAJ HEIGHTS - A & B -TYPE BUILDING S. Common Areas & Facilities Proposed Percentage of Details No. (Yes / NO) actual Work Done (As on date of Certificate) (1) (21 (3) (4) (5) 1. lnternal Roads & Footpaths NO N.A. 2. Water Supply YES 5Oo/o From Borewell 3. Sewerage (Chamber, Lines, YES oo% Drainage Line till Seotic Tank. STP) Corporation Line 4. Strom Water Drains NO N.A. ( Landscaping & Tree Planting YES 00% lnternal Project Tree Plantation b. Street Liqhtinq NO N.A. 7. Community Buildinqs NO N.A. 8. Treatment & Disposal of Sewage NO N.A. and Sullaqe Water L Solid Waste Management & NO N.A. Disposal 10. Water Conservation / Rain Water YES 00% Rain Water Harvesting Harvgsting As per Norms 11 Enerqv Manaqement NO N.A. 12. Fire Protection & Fire Safety NO N.A. requirements 13. Electrical Meter Room, Sub- NO N.A. Station, Receivinq Station 14. Aggregate area of recreational NO N.A. Ooen Soace 15. Others (Option to Add more) 'l ARCHITECTS t & Name of Land LicenseNumber( -- ) Agreed & Accepted by: Signature of?romoter Name: RAJYOG DEVELOPERS Date: 05-10-2023