MANGGAL DESIGN ARCHITECTS & INTERIOR DESIGNER Annexure A FORM1 |See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project &for Withdrawal of Money from Designated Account) Date:1410/2025 To, M/s. A B Developers, Raaj Group, Office No.2,First Floor, Mulay Tapadiya Complex,Jalna Road, Near Mondha Naka, Aurangabad - 431001 Subject: Certificate of Percentage of Completion of Construction Work of Anandam Residency having MahaRERA Registration Number P51500033671 (Only applicable after Project Registration) being Developed by AB Developers. Sir, /We have undertaken assignment as Architect /Licensed Surveyor of Certifying Percentage of Completion of Construction Work of Anandam Residency having MahaRERA Registration Number. P51500033671 (Only applicable after Project Registration) being Developed by A B Developers. Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, Icertifiy that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wingof the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A Apartment Building Layout / Building / Wing Number (to be prepared separately for each LayoutUBuildingWing of Project) S. Tasks I Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2. Basements (if any) 3 Podiums (if any) 4 Plinth 100% 5 Parking Floor 100% 6 Slab of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors, 100% windows within Flats / Premises 8 Sanitary Fittings within Flats /Premises 100% 9. Staircases, Lift Wells & Lobbies at each Floor Level 100% Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, 100% Completion of Terraces, with waterproofing of the Building / Wing 100% 11. Installation of Lifts, Water Pumps, Electrical Fittings, Mechanieat Equipments, Finishingto Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to BuildingWing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity T BLE-A Row House Block1(R9 TO R19) Layout/ Building / Wing Number (to be prepared separately for each Layout/BuildingWing of Project) S. Tasks / Activity Percentage of Actual Work Done No. (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 Basements (if any) 3 Podiums (if any) 100% 4 Plinth 5 Parking Floor 100% 6 Slab of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors, 100% windows within Flats / Premises 8. Sanitary Fittings within Flats / Premises 100% 9. Staircases, Lift Wells & Lobbies at each Floor Level 100% Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, 100% Completion of Terraces, with waterproofing of the Building / Wing 11, Installation of Lifts, Water Pumps, Electrical Fitings, N.A. Mechanical Equipments, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to BuildingWing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-A Row House Block 2 (R1 TO R8) Layout / Building / Wing Number (to be prepared separately for each Layout/Building/Wing of Project) S Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 Basements (if any) 3 Podiums (if any) 4 Plinth 100% 5. Parking Floor 100% 6. Slab of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors, 100% windows within Flats / Premises 8 Sanitary Fittings within Flats / Premises 100% Staircases, Lift Wells & Lobbies at each Floor Level 100% Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, 100% Completion of Terraces, with waterproofing of the Building /Wing 11. Installation of Lifts, Water Pumps, Electrical Fittings, N.A. Mechanical Equipments, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing. Compound Wall and al other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number S. Common Areas & Facilities Proposed Percentage of actual Work Details No. (Yes /NO) Done (As on date of Certificate) (1) (2) (3) (4) (5) 1 2 Internal Roads &Footpaths YES 100% 3 Water Supply YES 100% Sewerage (Chamber, Lines, YES 100% A Septic Tank, STP) Strom VWater Drains NA Landscaping &Tree Planting YES 100% 6. Street Lighting NA 100% 7 8 Community Buildings NA Treatment & Disposal of Sewage NA and Sullage Water 9. Solid Waste Management NA Disposal 10. Water Conservation / Rain Water YES Harvesting 11. Energy Management NA 12. Fire Protection & Fire SafetyNA requirements 13. Electrical Meter Room, Sub- YES Station, Receiving Station 14. Others (Option to Add more) Hence, as an architect of the scheme we hereby certify that 60% of the construction work of the project namely ANANDAM RESIDENCY, 0s over. Yours faithfully MANGGRL Ar.Pramnod Vithoba Narale Signature & Name of Land Surveyor / Architect narale.pramod26@gmail.com (BARCH) CA/2011/53824 License Number( Agreed &Accepted by: MS AB DEVELOPERS Signature bf PYomoter PARTNER Name: AB Developers, Rameshwar K. Bharuka & Kaushal S. Ajmera Date:1410/2025