MANGGAL DESIGN ARCHITECTS & INTERIOR DESIGNER AnneKure A FORM1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:09/07/2025 To, M/s. A B Developers, Raaj Group, Office No.2,First Floor, Mulay Tapadiya Complex, Jalna Road, Near Mondha Naka, Aurangabad - 431001 Subject: Certificate of Percentage of Completion of Construction Work of Anandam Residency having MahaRERA Registration Number P51500033671 (Only applicable after Project Registration) being Developed by A B Developers. Sir, / We have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of Anandam Residency having MahaRERA Registration Number. P51500033671 (Only applicable after Project Registration) being Developed by A B Developers. Based on the Site Inspection, with respect to the Layout / each Building Wing of the aforesaid Real Estate Project, Icertify that as on date of this Certificate, the Percentage of WorkDone for each of the BuildingWing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A Apartment Building Layout | Building / Wing Number (to be prepared separately for each Layout/Building/Wing of Project) S. No. Tasks IActivity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) 3 Podiums (if any) 4 Plinth 100% 100% Parking Floor 6 Slab of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors, windows 100% within Flats /Premises 8. Sanitary Fittings within Flats / Premises 100% 9 Staircases, Lift Wells & Lobbies at each Floor Level 100% Overhead and Underground Water Taniks 10. External Plumbing & External Plaster, Elevation, 100% Completion of Terraces, with waterproofing of the Building /Wing 11. Installation of Lifts, Water Pumps, Electrical Fittings, 100% Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-A Row House Block 1 (R9 TO R19) Layout| Building / Wing Number (to be prepared separately for each LayoutBuilding/Wing of Project) S. No. Tasks / Activity Percentage of Actual Work Done (Às on date of the Certificate) (1) (2) (3) 1 Excavation 100% Basements (if any) 3 Podiums (if any) 4 Plinth 100% 5 Parking Floor 100% 6 Slab of Super Structure 100% 7 Internal Walls, Internal Plaster, Floorings, Doors, windows 100% within Flats / Premises 8 100% Sanitary Fittings within Flats /I Premises 9 Staircases, Lift Wells & Lobbies at each Floor Level 100% Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, 100% Completion of Terraces, with waterproofing of the Building /Wing 11. Installation of Lifts, Water Pumps, Electrical Fittings, N.A. Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to BuildingWing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-A Row House Block 2 (R1 TO R8) Layout I Building I Wing Number (to be prepared separately for each LayoutBuilding/Wing of Project) Percentage of Actual Work S. No. Tasks / Activity Done (As on date of the Certificate) (1) (2) (3) 100% Excavation Basements (if any) 3 Podiums (if any) 100% 4. Plinth 100% Parking Floor 100% Slab of Super Structure 7 Internal Walls, Internal Plaster, Fioorings, Doors, windows 100% within Flats / Premises Sanitary Fittings within Flats / Premises 100% 8 Staircases. Lift Wells & Lobbies at each Floor Level 100% 9 Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, 100% Completion of Terraces, with waterproofing of the Building IWing N.A. 11. Installation of Lifts, Water Pumps, Electrical Fittings, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (Internal &External Development Works) in respect of the Registered Phase / Project Number S. No. Common Areas & Facilities Proposed Percentage of actual Work Details (Yes / NO) Done (As on date of Certificate) (1) (2) (3) (4) (5) 1 Internal Roads & Footpaths YES 100% 2 Water Supply YES 100% 3. Sewerage (Chamber, Lines, Septic|YES 100% Tank, STP) 4 Strom VWater Drains NA 5 Landscaping &Tree Planting YES 100% NA 100% 6 Street Lighting NA 7. Community Buildings 8. Treatment & Disposal of Sewage NA and Sullage Water 9. Solid Waste Management & NA Disposal 10. Water Conservation / Rain Water YES Harvesting 11. Energy Management NA 12. Fire Protection & Fire Safety NA requirements 13. Electrical Meter Room, Sub- YES Station, Receiving Station 14. Others (Option to Add more) 60% of the construction Hence, as an architect of the scheme we hereby certify that work of the project namely ANANDAM RESIDENCY, is Over. Yours faithfully MANGGAL Ar.Pramod Vithoba Naroale N a r a l e . p r a m o d 2 8 G g m a i l . c o m (B.ARCH) CA/2011/53824 Signature & Name of Land Surveyor / Architect License Number Agreed &Accepted by: /S AB DEVELOPERSA PARTNER Signature of Promoter Name: AB Developers, Rameshwar K. Bharuka & Kaushal S. Ajmera Date:09/07/2025