R.B & ASSOCIATES D.A.DESHPANDE DISGINER ENGINEERS consulting engineer OFFICE: Plot No-12/B ,Gut No- 64 New ST Colony Near N-2 Cidco Auangabad FROM -2 ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account- Project wise) Date: 05/08/2022 To , “RUSHIKESH VILLA” M/S Malode Builders & Developers Thro,Its Proprietor Shri.Kiran Baburao Malode . On Plot No-288 ,Gut No-1/1 & 51(P)At. Sunderwadi Tq & Dist.Aurangabad. Subject: Certificate of Percentage of Completion of Construction Work of “RUSHIKESH VILLA” Residential Building of the Project M/S Malode Builders & Developers Thro,Its Proprietor Shri.Kiran Baburao Malode . On Plot No-288 ,Gut No-1/1 & 51(P)At. Sunderwadi Tq & Dist.Aurangabad. [NOT YET REGISTERED], AURANGABAD Demarcated by its boundaries (latitude and longitude of the end points) To the North – Plot No-287 To the South – 18.00 m w road To the East – 9.00 m w road To the West – Gut No-19(p) Of Division Cidco Ltd. Fringe Area ,Aurangabad Situated at. Plot No-288 ,Gut No-1/1 & 51 (p) At.Sunderwadi. Tq & Dist.Aurangabad admeasuring 767.66 Sq.m for comprising 12 Nos- 2BHk Row House of the project Name “RUSHIKESH VILLA” the project M/S Malode Builders & Developers Thro,Its Proprietor Shri.Kiran Baburao Malode R.B & ASSOCIATES D.A.DESHPANDE DISGINER ENGINEERS consulting engineer OFFICE: Plot No-12/B ,Gut No- 64 New ST Colony Near N-2 Cidco Auangabad Sir, I _D.A.Deshpande have undertaken assignment of certifying Estimated Cost for the Subject Real Estate Project proposed to be registered under Maha RERA, being “RUSHIKESH VILLA ” On Plot No- 288,Gut No-1/1 & 51(P) At.Sunderwadi ,Tq & Dist.Aurangabad admeasuring 767.66 Sq.mts for 12 Nos-2BHk Row House ,of the project Name “RUSHIKESH VILLA ” the project By M/S Malode Builders & Developers Thro,Its Proprietor Shri.Kiran Baburao Malode . following technical professionals are appointed by Owner / Promoter:- i) Shri _B.V.Raut of as L.S. / Architect ii) Shri _D.A.Deshpande as Structural Consultant iii) Shri _ B.V.Raut as Quantity Surveyor 2. We have estimated the cost of the completion to obtain Occupation Certificate/ Completion Certificate, of the Civil, MEP and Allied works, of the Building(s) of the project. Our estimated cost calculations are based on the Drawings/plans made available to us for the project under reference by the Developer and Consultants and the Schedule of items and quantity for the entire work as calculated by Site Supervisor appointed by Developer/Engineer, and the assumption of the cost of material, labour and other inputs made by developer, and the site inspection carried out by us. 3. We estimate Total Estimated Cost of completion of the building(s) of the aforesaid project under reference as Rs. 2,17,33,646=00 (Total of Table A and B). The estimated Total Cost of project is with reference to the Civil, MEP and allied works required to be completed for the purpose of obtaining occupation certificate / completion certificate for the building(s) from the Cidco Ltd Waluj. being the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost Incurred till date is calculated at Rs. 0,00,00,000=00 (Total of Table A and B) the amount of Estimated Cost Incurred is calculated on the base of amount of Total Estimated Cost. 5. The Balance cost of Completion of the Civil, MEP and Allied works of the Building(s) of the subject project to obtain Occupation Certificate / Completion Certificate from Cidco Ltd fringe (planning Authority) is estimated at Rs. Rs. 2,17,33,646=00 (Total of Table A and B). 6. I certify that the Cost of the Civil, MEP and allied work for the aforesaid Project as completed on the date of this certificate is as given in Table A and B below : R.B & ASSOCIATES D.A.DESHPANDE DISGINER ENGINEERS consulting engineer OFFICE: Plot No-12/B ,Gut No- 64 New ST Colony Near N-2 Cidco Auangabad TABLE A Sr. No Particulars Amounts 1 Total Estimated cost of the building as on 22.06.2022 is Rs. 2,17,33,646=00 2 Cost incurred as on 05.08.2022 (based on the Estimated cost ) Rs. 0,00,000=00 3 Work done in Percentage (as Percentage of the estimated cost ) 0% 4 Balance Cost to be Incurred (Based on Estimated Cost) Rs. 2,17,33,646=00 5 Cost Incurred on Additional /Extra Items not included in the NIL Estimated Cost (Annexure A) TABLE B (To be prepared for the entire registered phase of the Real Estate Project) Sr. Particulars Amounts No 1 Total Estimated cost of the Internal and External Development Works NIL including amenities and Facilities in the layout as on 22.06.2022 is 2 Cost incurred as on 05.08.2022 ( based on the Estimated cost ) NIL 3 Work done in Percentage (as Percentage of the estimated cost ) 0% 4 Balance Cost to be Incurred (Based on Estimated Cost) NIL 5 Cost Incurred on Additional /Extra Items not included in the Estimated Cost NIL (Annexure A) Yours Faithfully Signature of Engineer