gipt graffic infrastructure put. ttd Annexure - B FORM - 2 [See Regulation 3] ENG IN EER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for Withdrawal of Money from Designated Bank Account) Date: 16-10-2023 To, Marathwada Constructions Pvt Ltd, 60, Hari Prasad Complex, Dashmeshnatar, Osmanpura Aurangabad Subject: Certificate of Cost lncurred for Development of GREEN SPACE RES|DENCY PROJECT 1 B BLOCK having MahaRERA Registration Number P51500045761 being Developed by Marathwada Constructions Pvt Ltd. Sir, I / We Er.Sunil Raka have undertaken assignment of Certifying Estimated Cost for GREEN SPACE RESIDENCY PROJECT 1 B BLOCK having MahaRERA Registration Number P51500045751 being Developed by Marathwada Constructions Pvt Ltd. We have estimated the cost of Civil, MEP and Allied Works required for completion of the apartments & proportionate completion of internal & external works of the Project as per the specifications mentioned in the Agreement of Sale. Our estimated cost calculations are based on the Drawings/Plans made available to us for the Project under Reference by the Developers / Consultants. The Schedule of ltems & Quantity required for the entire work as calculated by ER. Amol Patil Quantity Surveyor* appointed by the Developer/Engineer, the assumption of the cost of material, labour & other inputs made by the Developer, and the Site lnspection carried out by us to ascertain / confirm the above analysis given to us. 3. We estimate Total Estimated Cost of completion of the aforesaid Project mentioned under reference al Rs.24236879/- (Total of Table A & B) at the time of Registration. The estimated Total Cost of Project is with reference to the Civil, IMEP & Allied Works completion of the apartments & proportionate completion of internal & external works, as per the specifications mentioned in the Agreement of Sale & for the purpose of obtaining Occupation Certificate / Completion Certificate for the Building(s) / Wing(s) / Layout / Plotted Development from the Head office : 70 Suvarnaneel House, Dashmesh Nagar, Aurangabad-431 005 Tel.: (0240) 2355387 Mob.: 9423189136 Email: contact@graflicinfra,com, Branch Office : Kamla Niwas, Plot No. 32, Lane - D, Sector - 8, Vashi, Navi Mumbai - 400703. Web: www.grafficinfra.com FIRE FIGHTI}IG CO}ISULTANTS FIRE FlGHTll{G PL,AI{i{ll'G & DESlOtall{C FIRE FIGHTIIG EsTll.{ATloll & TENoER gipt graffic infrastructure put. ttd. 4. AURANGABD MUNICIPAt CORPORATION being the Planning Authority under whose jurisdiction the aforesaid Project ls being implemented. 5. The Estimated Cost incurred till date is calculates to Rs. 1,00,58,279/-(Total of Table A & B). The Amount of .Estims!.ed.eg.sl.Ln-c.u.[red.t9.c.d.Cu!a.ted.9.n.the.b.?.qi9.p_f- jnpy!..rr'.?!.e.ri9.!.s/_-s.c.ryj-qss..ug-e.d.& !t n!!. ga$.t .aI.th-e.es. i!e mr. 6. The Balance Cost of completion of the Civil, MEP & Allied Works for completion of Apartments & proportionate completion of internal & external works, as per specifications mentioned in Agreement of Sale, of the aforesaid Project is estimated at Rs. 1,41,78,540/- (Total of Table A & B). 7. I Certify that the cost of Civil, MEP & Allied Work for apartments & proportionate internal & external works, as per the specifications mentioned in Agreement of Sale, of the aforesaid Project as completed on the date of this certificate is as given in Table A & B below: TABTE - A For Row House 1 to 9 S. No, Particulars Amount (in Rs.) 1. Total Estimated Cost of Building / Wing / Layout / Rs.2,L8,L3,L37 /- Plotted Development as on date of Registration is 2. Cost incurred as on date of Certificate Rs.9815911/- 3. Work Done in Percentage (as Percentage of Estimated 450/o cost) 4. Balance Cost to be incurred ** ((based on Estimated 7,t9,97,226/- cost) 5. Cost incurred on Additional / Extra ltems not included in NIL the Estimated Cost (Table-C) TABLE - B lnternal & External Development Works the current Phase of Prorect S. No. Particulars Amount (in Rs.) 1. Total Estimated Cost of lnternal & External 2423682/- Development Works including amenities & facilities in the Layout as on date of Registration is 2. Cost incurred as on date of Certificate 242368/- 3. Work Done in Percentage (as Percentage of Estimated lOo/o Cost) Head Offlce : 70 Suvarnaneel House, Dashmesh Nagar, Aurangabad-431 005 Tel.: (0240) 2355387 Mob.: 94231891 36 Email: contact@grafficinfra.com, - Branch Office : Kamla Niwas, Plot N0.32, Lane - D, Sector - 8, Vashi, Navi Mumbai - 400703. web: www.grafficinfra.com FIRE FIGHTITG COiISULTANTS FIRE FIOHTII{O FI6HTII{G PLAI{IIIT{O & DESIOI'IT'G FIRE FI6HTIt{G ESTII,IATIOT & TE DER graffic infrastructure put. Ltd. 4. Balance Cost to be incurred ** ((based on Estimated 2787374/- cost) 5. Cost incurred on Additional / Extra ltems not included in NIL the Estimated Cost (Table-C) Yours faithfully, kl 6 rsrus,a.'. Signaturd with Stanpgfhineer Er. Sunil Raka Local Authority License Number (if applicable) Agreed & Accepted by: 6) r:/ E-r, \,\ Signature of Promoter Name:M/s.Marathwada Constructlons hd Ltd Date:15-07-2023 Note: The scope of work is to complete Registered Real Estate Project as per drawings approved from time to time as per specifications mentioned in the Agreement to Sale. 2. (*) Quantity Survey can be done by the office of Engineer or can be done by an independent Quantity Surveyor, who's Certificate of Quantity Calculated, can be relied up on by Engineer. ln case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) & in case quantity are being calculated by office of Engineer, the name of person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). Head office : 70 Suvarnaneel House, Dashmesh Nagar, Aurangabad-431 005 Tel.: (0240) 2355387 Mob.: 94231891 36 Email: contact@grafficinfra.com, Branch office : Kamla Niwas, Plot No. 32, Lane - D, Sector - 8, Vashi, Navi Mumbai - 400703. Web: www.grafficinfra.com FIRE FIGHTII{G CONSULTA}ITS FItE FIOHTIl{O FIoHTII|G PLAX IIG & DESIO]'IT6 FINE FIGHTING ESTIXATIO]{ & TE DER l*,,, graffic infrastructure put Ltd 3. (*l) Balance Cost to be incurred (4) may vary from difference between Total Estimated Cost (1) & actual Cost incurred (2) due to deviation in quantity required / escalation of cost etc. As this is an Estimated Cost any deviation quantity required for the Development of Real Estate Project will result in an amendment of the cost incurred / to be incurred. 4. All components of work with specifications are indicative & not exhaustive 5. Please specify if there are any deviations / qualifications. Example: Any deviation in input material used from specifications in Agreement of Sale. TABIE - C List of Extra / Additional / Deleted ltems considered in the Cost (Which were not parts of the original Estimate of Total Cost) S. No. list of Extra / Additional / Deleted ltems Amount (in Rs.) 1. 2. Head ffice : 70 Suvarnaneel House, Dashmesh Nagar, Aurangabad-431 005 Tel.: (0240) 2355387 Mob.: 9423189136 Email: contact@grafficinfra.com, Branch office : Kamla Niwas, Plot N0.32, Lane - D, Sector - 8, Vashi, Navi lvlumbai - 400703. Web: www.graflicinfra.com FIRE FI6HTIIIG COXSULTAiITS FIRE FIGI{TI1{O FIOHIIiIC PLAI{I{II'O & DEgIO}'II'G FIRE FIGHTIIG ESTIl,lATION & TEI{OER