qa Amol Kshirsagrar Architectural Planne r, Annexure A Consulting Engineer & FORMl Valuer [Sea Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:12-11-2024 To, SARA LANDMARKS, 11, A-WING, NARAYAN PLAZA, CANNAUGHT PLACE, AURANGABAD Certificate of Percentage of Completion of Construction Work of SARA SAHYADRI PARK having MahaRERA Registration Number P515000339,t0 being developed by SARA LANDMARKS. (For Jul to Sep 2024 QTR) Sir, I / We ER AMOL KSHIRSAGAR has undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of SARA SAHYADRI PARK having MahaRERA Registration Number P51500033910 being developed by SARA LANDMARKS. Based on the Site lnspection, with respect to the Layout / each BuildingMing of the aforesaid Real Estate Project, I certify that as on datb of this Certificate, the Percentage of Work Done for each of the BuildingMing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Tabl+8. TABLE-A-1 / Buildins / Wins Number -SAM SAHYADRI PARK RH No I to 12 S\ Tasks / Activity Percentage of Actual Work tta\ Done (As on date of the Certificate) (1) (2) (3) 1 *cavation o% 2 X AUmber of Basement(s) and Plinth 0% 3 X nu\ber of Podiums 00k 4 Stilt F\or 0o/o ( X numbk of Slabs of Super Structure lYo b lnternal \alls. lnternal Plaster, Floorings within 0% Flats/Premi\s. Doors and Windows to each of the FlaUPremise\ I Plot No. 102, lat No.4, Plol Flat Nathprangan,Garkheda, athp Chhatrapati Sambhajinagar hhat H Mob. : 099606 09960669921 7 Sanitary Fittings within the FlaUPremises, Electrical 0% Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor levei 0% connecting Staircases and Lifts, Overhead and Underground Water Tanks. I The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the BuildingA/Ving 10 lnstallation of lifts, water pumps, Fire Fighting Fittings 0o/o and Equrpment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completlon Certificate TABLE-A-2 / Building /Wing Number- SARA SAHYADRI PARK RH no. 13 to,l8 S Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 0% 2 X number of Basement(s) and Plinth 0o/o 3 X number of Podiums 0o/o 4 Stilt Floor 0o/o X number of Slabs of Super Structure 0% b lnternal walls, lnternal Plaster, Floorings within 0Yo FlatsiPremises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical Oo/o Fittings within the FlaUPremrses 8 Staircases, Lifts Wells and Lobbies at each Floor level 0o/o connectrng Staircases and Lifts, Overhead and Underground Water Tanks. o The external plumbing and erilernal plaster, elevation, Oo/o completion of terraces with waterproofing of the BuildingA/Ving 10 lnstallation of lifts, water pumps, Fire Fighting Fittings 0% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Buildingl/Ving, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A.3 Building /Wing Number- SARA SAHYADRT PARK RH No. 19 to 25 s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2t (3) 1 Excavation Oo/o 2 X number of Basement(s) and Plinth 0% X number of Podiums 0% 4 Stilt Floor 0o/o X number of Slabs of Super Structure 0% b lnternal walls, lnternal Plaster, Floorings within 0o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FIaUPremises, Electrical Fittings within the FlaUPremises I Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and lJnderground Water Tanks. o The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the BuildingA/Ving 10 lnstallation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC. Electricat fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment iCRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A4 Number - SARA SAHYADRI PARK RH no. 26 to 37 s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation Oo/o 2 X number of Basement(s) and Plinth Oo/o 3 X number of Podiums lYo 4 Stilt Floor 0o/o 5 X number of Slabs of Super Structure b lnternal walls, lnternal Plaster, Floorinqs within 0o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, gtectrlcal 0o/o Fittings within the FlaUPremises I Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and Underground Water Tanks. o The external plumbing and e)dernal plaster, elevation, 0% completion of terraces with waterproofing of the BuildingAtVing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings Oo/o and Equipment as per CFO NOC, Electricat fittings io Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A-5 Number - SARA SAHYADRI PARK RH no. 38 to 49 S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100% 2 X number of Basement(s) and Plinth 100o/o X number of Podiums 4 Stilt Floor X number of Slabs of Super Structure 100o/o o lnternal walls, lnternal Plaster, Floorings wrthin 100Yo Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 100o/o Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 100o/o connecting Staircases and Lifts, Overhead and Underground Water Tanks. o The external plumbing and external plaster, elevatiorl 100o/o completion of terraces with waterproofing of the Building/Wing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings 1000 and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingAruing, Compound Wail and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A-6 Number- SARA SAHYADRI P qRK RH No. 50 to 58 s. Tasks / Activity Percentage of Actual Woik No. Done (As on date of the Certificate) fl) (2t (3) 1 Excavation lYo 2 X number of Basement(s) and plinth 1Yo X number of Podiums 0o/o 4 Stilt Floor 0% 5 X number of Slabs of Super Structure 6 lnternal walls, lnternal Plaster, floorrngE within 00k Flats/Premises, Doors and Windows to eath of the FlaUPremises 7 Sanitary Fittings wit@ 0o/o Fittings within the FlaUPremises I Staircases, LiftsWeffi Oo/o connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, etevation, 0% completion of terraces with waterproofing of the BuildingAlVing 10 lnstallation of lifts, water pumps, Fire Figntlngf rttings 00k and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to condittons of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building^/Ving, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A.7 / Buildinq / Number - SARA SAHYADRI P qRK RH no. 59 to 68 S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (r ) (2t (3) 1 Excavation 0o/o 2 X number of Basement(s) and Plinth 0o/o 3 X number of Podiums 0o/o 4 Stilt Floor Oo/o 5 X number of Slabs of Super Structure 0% o lnternal walls, lnternal Plaster. Floffis within 0o/o FlatsiPremises, Doors and Windows to eaih of the FlaUPremises 7 Sanitary Fittings within the Flaupremisesjlectrical 0o/o Fittings within the FlaUPremises ffi 8 Staircases, Lifts Wells and Lobbies at each Floor level 00k connecting Staircases and Lifts, Overhead and Underground Water Tanks. o The external plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the BuildingANing 10 lnstallation of lifts, water pumps, Fire Fighting Fittings 0% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A.8 Number - SARA SAHYADRI PARK RH no. 69 to 80 s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2t (3) 1 Excavation 100Yo 2 X number of Basement(s) and Plinth 100% X number of Podiums 4 Stilt Floor X number of Slabs of Super Structure 100% o lnternal walls, lnternal Plaster, Floorings within 1000k Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Electrical 100% Fittings within the FlaUPremises I Staircases, Lifts Wells and Lobbies at each Floor level 100o/o connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 100o/o completion of terraces with waterproofing of the BuildingM/ing 10 lnstallation of lifts, water pumps, Frre Fighting Fittings 100% and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wail and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A-9 / Building /Wing Number- SARA SAHYADRT PARK RH no. Bl to g0 S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100o/o 2 X number of Basement(s) and Plinth 100yo 3 X number of Podiums 4 Stilt Floor 5 X number of Slabs of Super Structure 100% 6 lnternal walls, lnternal Plaster, Floorings wrthh 100o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaVPremises. Electrical 10Oo/o Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 1000/0 connecting Staircases and Lifts, Overhead and Underground Water Tanks. I The e)dernal plumbing and external plaster, elevatiorl 100o/o completion of terraces with waterproofing of the BuildingANing 10 lnstallation of lifts, water pumps, Fire Fighting Fitthgs 100o/o and Equipment as per CFO NOC, Electricat fittings to Common Areas, electro, mechanical equipment, Comp ance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingAr'Ving, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A.lO Building /Wing Number- SARA SAHYADRT PARK RH no. 91 to 97 S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 45% 2 X number of Basemelt(s) and Plinth 0o/o 3 X number of Podiums 0o/o 4 Stilt Floor 0o/o X number of Slabs of Super Structure 00h 6 lnternal walls, lnternal Plaster, Floorings withh 0% Flats/Premises, Doors and Windows to each of the FlaVPremises 7 Sanitary Fittings within tha Flat/premrsesjlectflcal 0% Fittings within the FlaUPremises I Staircases, Lifts Wells and Lobbies at each Floor level ook connecting Staircases and Lifts, Overhead and Underground Water Tanks. I The external plumbing and external plaster, elevaffi 0% completion of terraces with waterproofing of the BuildingMing 10 lnstallation of lifts, water pumps, Fire Fighting Fitting- 0o/o and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.A-11 Building / Wing Number - SARA SAHYADRI PARK RH no. 98 to 103 S. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 450k 2 X number of Basement(s) and Plinth 0o/o 3 X number of Podiums 0o/o 4 Stilt Floor 0% 5 X number of Slabs of Super Structure 0o/o b lnternal walls, lnternal Phstea-Floorrngs wrthin 0% Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaUPremises, Eiectrical 00k Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0% connecting Staircases and Lifts, Overhead and Underground Water Tanks. o The external plumbing ana Gxtemat ptaster, elevafion, 0o/o completion of terraces with waterproofing of the BuildingA/Ving 10 lnstallation of lifts, water pumps, Fire Fighting fittings 0o/o and Equipment as per CFO NOC, Electricat fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wail and all other requirements as may be required to Obtain Occupation /Completion Certificate ,fu ffi TABLE.A.12 Number - SARA SAHYADRI PARK RH no. 104 to 1 '10 s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 65% 2 X number of Basement(s) and Plinth 0 3 X number of Podiums 0 4 Stilt Floor 0o/o X number of Slabs of Super Structure 0o/o b lnternal walls, lnternal Plaster, Floorings within 0a Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlauPremises, Electrical 0% Fittings within the FlaUPremises 8 Staircases, Lifts Wells and Lobbies at each Floor level lYo connecting Staircases and Lifts, Overhead and Underground Water Tanks. o The external plumbing and external plaster, elevation, lYo completion of terraces with waterproofing of the BuildingA/Ving 10 lnstallation of lifts, water pumps, Fire Fighting Fittings 0o/o and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Buildingl/Ving, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE-A.13 Number - SARA SAHYADRI PARK RH No. 'l l l to 120 s. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (2t (3) 1 Excavatron 100o/o 2 X number of Basement(s) and Plinth 100% 3 X number of Podiums 4 Stilt Floor ( X number of Slabs of Super Structure 100% 6 lnternal walls, lnternal Plaster, Floorings within 100o/o Flats/Premises, Doors and Windows to each of the FlaUPremises Sanitary Fittings within the FlaUPremises, Electrical 1O0o/o Fittings within the FlaUPremises I Staircases, Lifts Wells and Lobbies at each Floor level 1O0o/o 4,9 connecting Staircases and Lifts, Overhead and Underground Water Tanks. I The external plumbing and external plaster, elevation, 100o/o completion of terraces with waterproofing of the BuildingA/Ving 10 lnstallation of Iifts, water pumps, Fire Fighting Fittings 100o/o and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate TABLE.B Common Areas (lnternal & External Development Works) in of the Number - SARA SAHYADRI PARK S. Common Areas & Facilities Proposed Percentage of Details No. (Yes / NO) actual Work Done (As on date of Certificate) (1) (2) (3) (4) (s) 1 lnternal Roads & Footpaths : YES lYo TRIMIX ROAD 2. Water Conservation, Rain water YES 0o/o AS PER Harvesting: CONSULTANT J, Energy management : YES Oo/o LED LIGHTS FOR STREET LIGHTS 4. Fire Protection And Fire Safety NO NA Requirements: 5. Electrical Meter Room, Sub- NO NA Station, Receivinq Station : b. Aggregate area of recreational NO NA Open Space : 7. Open Parkino : NO NA 8 Water Supply : YES 25o/o OPEN WELL AND BOREWELL 9. Sewerage (Chamber, Lines, YES 0% COMMON SEPTIC Septic Tank , STP) : TANK '10 Storm Water Drains : YES lYo AS PER CONSULTANT 11 Landscaping & Tree Plantinq : NO NA 12. Street Lighting . YES Oo/o LED LIGHTS 13 Community Buildinqs : NO NA 14. Treatment And Disposal Of NO NA Sewage And Sullage Water . w\ \ Yours faithfully, B ER. AMOL KSHIRSAGAR Signature & Name (lN BLOCK LETTERS) of Land Surveyor / Architect License Number E I 174 193 Agreed & Accepted by: \ .\tuq' Signature of Pd{nbter Name: SAFiA LANDMARKS Oale:12-11-2024