Amol Kshirsagar Arch itectural Planner, Consulting Engineer & Annexure A Valuer FORM 1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:1.0-07-2023 To, SARA LANDMARKS, 11, A-WING, NARAYAN PLAZA, CANNAUGHT PLACE, AURANGABAD Subject: Certificate of Percentage of Completion of Construction Work of sARA SAIIYADRI PARK having MahaRERA Registration Number P51500033910 being developed by SARA LANDMARKS Sir, I / WeER AMOL KSHIRSAGAR has undertaken assignment as Architect / Licensed Suiveyor of Certifying Percentage of Completion of Construction Work of SARA SAIIYADRI PARK having MahaRERA Registration Number P51500033910 being developed by SARA / on the Site Inspection, with respect to the Layout each Building/Wing of the aforesaid Estate Project I certify that as on date of this Certificate, the Percentage of Work Done for of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein . The percentage of work executed with respect to each of the activity of entire Phase is in Table-B. TABLE-A.1 Wi Number -SARA SAIIYADRI PARK RH No Lto 12 Percentage of Actual Work Done As on date of the X number' FIat No.4, Plot No. 102, Nath prangan, Garkheda, Chhatrapati Sambhajinagar Mob. :09960669921 I 4 Stilt Floor 0 5 X number of Slabs of Super Structure 0 6 Internal walls, Internal Plaster, Floorings wittdn 0 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 0 Fittings within the Flat/Prernises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0 connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0 completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings 0 and Equipment as per CFO NOC, Electrical fittings to Comrnon Areas, electro, mechanical equipmen! Compliance to conditions of environment /CRZ NOC, Finishing to enh.ance lobby/ s, plinth protectiory paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation / Completion Certificate TABLE-A.2 Number - SARA SAHYADRI PARK RH no.13 to 18 Tasks/Activity Percentage of Actrlal Work Done X number of Basement(s) and Plinth X number of Podiums X number of Slabs of Super Structure Internal walls, Internal Plaster, I;loorings within Flats/Prernises, Doors and Windows to each of the Sanitary Fittings within the Ftat/Premises, Electrical Fittings within the Staitcases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and The external plumbing and external plaster, elevatiorL completion of terraces with waterproofing of the Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electical fittines to Nv Common Areas, electro, mechanical equipmen! Compliance to conditions of environment /CRZ NOC, Finishing to ent'ance lobby/s, plinth protection, paving of areas appurtenant to Building/Wrng, Compound Wall and all other requirements as may be required to Obtain Occu ion Certificate TABLE.A-3 Wi.g Number - SARA SAIfYADRI PARK RH No. t9 to 25 S. Tasks/Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) a) (3) 1 Excavation 0 2 X number of Basement(s) and Plinth 0 3 X number of Podiums 0 4 Stilt Floor 0 5 X number of Slabs of Super Structure 0 6 Internal walls, Internal Plaster, Floorings within 0 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 0 Fittings within the Flat/Irremises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0 connecting Staircases and Lifts, Overhead and ! Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0 completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Ilire Irighting Fittings 0 and Equipment as per CFO NOC, Electrical fiftings to Common Areas, electro, rnechanical equipment, Compliance to conc{itions of environment /CRZ, NOC, Finishing to enbrance lobby/ s, plinth protection, paving of areas appurtenant to Building/Wng, Compound Wall and all other requirements as may be requirecl to Obtain Occupation /Completion Certificate TABLE-A4 Wing Number - SARA SAIfYADRI PARK RH no. 26to 37 s. Tasks/Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 7 Excavation 0 2 X number of Basement(s) ancl Plinth \ \ /.4 *r r.l' , 8€ rH fra" Qtrlrer@ &; J X number of Podiums 0 4 Stilt Floor 0 5 X number of Slabs of Super Structure 0 6 Internal walls, Internal Plaster, Floorings within 0 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 0 Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0 connecting Staircases and Lifts, Overhead and Underground Water Tanks. I The external plumbing and external plaster, elevatiory 0 cornpletion of terraces wittr waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings 0 and Equipment as per CFO NOC, Electrical fittings to Cornmon Areas, electro, mechanical equipmen! Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/ s, plinth protectiory paving of areas appurtenant to tsuilding/Wrng, Compound Wall and all other requirernents as rnay be required to Obtain Occupation /Completion Certificate TABLE.A-5 Buildi wi Number - SARA SAHYADRI PARK RH no. 38 to lI9 Percentage of Actual Work Done As on date of the X number of Basernent(s) and P1inth X number of Slabs of Super Shucture Internal walls, Internal Plaster, Floorings within Flats/Prernises, Doors and Windows to each of the Sanitary Fittings within the F1at/Premises, Electrical Fittings within the FlatlPrernises Staircases, Lifts Wells and Lobbies at each Floor level cormecting Staircases and Lifts, Overhead and Underground Water Tanks. The external plumbing and external plaster, elevatiory completion of terraces with waterproofing of the Installation of lifts, water purnps, Fire Fiehtine Fi E @ and Equipment as per CFO NOC, Elecbical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to enh:ance lobby/ s, plinth protection, paving of areas appurtenant to Buildtng/Wng, Compouncl WaIl and all other requirements as may be required to Obtain Occupation / Completion Certificate TABLE.A-5 Wiog Number - SARA SAIIYADRI PARK RH No. S0 to 58 s. Tasks/Activity Percentage of Acfual Work No. Done (As on date of the Certificafel (1) (21 (3) 1 Excavation 0 2 X nurnber of Basement(s) and I{inth 0 3 X number of Podiums 0 4 Stilt Floor 0 5 X number of Slabs of Super Structure 0 6 Internal walls, Internal Plaster, Floorings within 0 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 0 Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and 0' Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0 completion of terraces with waterproofing of the Building/Wing 10 TABLE-A.7 / Buildi Number - SARA SAHYADRI PARK RH no.59 to Gg, Percentage of Acfual Work Done on date of the X number of Basement(s) and plinth J X number of Podiums 0 4 Stilt Floor 0 5 X number of Slabs of Super Structure 0 6 Internal walls, Internal Plaster, Floorings within 0 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 0 Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0 connecting Staircases and Lifts, Overhead and Underground Water Tanks 9 The external plumbing and external plaster, elevatiorl 0 completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water prunps, Fire Fighting Fittings and Equipment as per CIrO NOC, Electrical fittings to Common Areas, electro, mechanical equipmen! Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protectiory paving of areas appurtenant to Building/Wing, Compouncl Wall and all other requirements as may be requirecl to Obtain Occupation / Completion Certificate TABLE-A-8 t Wing Number - SARA SAIIYADRI PARK RH no.69 to 80 S. Tasks/Activity Percentage of ActuaI Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 100 2 X number of Basernent(s) and Plinth 100 J X number of Podiums 0 4 Stilt Floor 0 5 X number of S1abs of Super Structure 100 6 Internal walls, Internal Plaster, Floorings within 100 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 100 Fittings within the Flat/Prernises 8 Staircases, Lifts Wells and Lobbies at each Floor level 100 connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 100 completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittines / too /t+l and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, rnechanical equipmen! Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby / s, plinth protection, paving of areas appurtenant to Buildtng/Wng, Compound Wall and all other requirements as may be required to Obtain Occupation /C, Certificate TABLE.A-9 w Number - SARA SAIIYADRI PARK RH no.81to 90 s. Tasks/Activity Percentage of Acfual Work No. Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100 2 X number of Basement(s) ancl Plinth 100 3 X number of Podiums 0 4 Stilt Floor 0 5 X number of Slabs of Super Structure 100 6 lnternal walls, Internal Plaster, Floorings within 100 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical 80 Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 40' corurecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0 completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water purnps, Fire Fighting FittingJ 0 and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to enhance lobby/s, plinth protection, paving of areas appurtenant to Buildng/rNng, Compound Wall and all other requirements as may be required to Obtain Occupation / Cornpletion Cerfficate TABLE-A.l0 Number - SARA SAIIYADRI PARK RH no. 9tto97 s. Tasks/Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) 't (21 ,(3) 2 Excavation X number of Basement(s) and Ptinth ,// 0 0 NX Jt\ ;.i 1 ri: In,, {8dEl-,.#P" J X number of Podiums 0 4 Stilt Floor 0 5 X number of Slabs of Super Structure 0 6 Internal walls, Internal Plaster, Floorings within 0 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Ftat/Premises, Electrical 0 Fittings within the Flat/Premises 8 Staircases, Lifts Wells ancl Lobbies at each Floor level 0 connecting Staircases anc{ Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevatior; 0 completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings 0 and Equipment as per CI]O NOC, Electrical fittings to Cornmon Areas, electro, mechanical equipmenf Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protectiory paving of areas appurtenant to Buildtag/Wng, Compound Wall and all other requirernents as may be requirecl to Obtain Occupation / Completion Certificate TABLE-A-11 Number - SARA SAHYADRI PARK RH no. 9g to 103 Percentage of Actual Work Done As on date of the X number of Basernent(s) and Plinth X number of Podiums X number of Slabs of Super Structure Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Sanitary Fittings witlin the Flat/Premises, Electrical within the Flat/ Prernises Staircases, L,ifts Wells and L,obbies at each Floor level connecting Staircases and Lifts, Overhead ancl Underground Water Tanks. The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Installation of lifts, water purnps, Fire Fiehtine Fi h ei l? i,:/.i G# and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanicarl equipmen! Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby / s, plinth protection, paving of areas appurtenant to Building/Wtng, Compound Wall and all other requirements as may be required to Obtain Occu /Completion Cerfficate TABLE-A.12 W Number - SARA SAIfYADRI PARK RH no.104 to 110 s. Tasks/Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (21 (3) 1 Excavation 0 2 X number of Basement(s) and Irlinth 0 3 X number of Podiums 0 4 Stilt Floor 0 5 X number of Slabs of Super Structure 0 6 Internal walls, lnternal Plaster, Floorings within 0 Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary F-ittings within the F'1at/Premises, Electrical 0 Fittings within the Flat/Premises 8 Staircases, Lifts Wells and Lobbies at each Floor level 0t connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevatiorL 0 completion of terraces with' waterproofing of the Bu4ding/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings 0 and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipmen! Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby / s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall ancl all other requirements as may be required to Obtain Occupation / Completion Certificate TABLE.A.l3 Number - SARA SAHYADRI PARK RH No. 111 to 120 s. Tasks/ Activity Percentage of Actual Work No. Done (As on date of the Certificate) (1) (3) \2) 1 Excavation 100 2 X number of Basement(s) and Plinth // 100 H X number of Pocliums Stilt Floor X number of Slabs ofE"pe, St rr" Internal *atr, ".t Flats/Premises, Doors and Winclows to each of the llnitary rt* Fittings within the I;lat/Irremises Staircases, t 99ryecting Staircases and Lifts, Overheacl and Underground Water Tanks. The extern, completion of terraces with waterproofing of the Installa and Eq l-^* a Common Areas, -^ -,- - electro, mechanical equipmen! Compliance to conditions rf environment /CRiNOC; Finishing to entrance lobbyls, plinth protectioru paving o.f areas appurtenant to'tsuilcling/Wing, Compouni Wall and all other requirernents as rnay be requiecl to Obtain Occupation / Completion Certificate TABLE-B Areas (Internal & External Development .Common Works) in respect of the wirg Number - SARA pARi( 'AIT'ADRI s. Common Areal & facilities Proposed Percentage of actual Details No. (Yes/No) Work Done (As on date of (1) Certificate) (3) (4) 1. fnlamal El^^A- 9- 'uurPafns: (s) YES 0 TRIMIX ROAD 2. vYaLer Lonservauorg Kain water YES 0 Harvesting: ASPER 3. E-^-- .rrEry ut.l.rtaBelnent CONSULTANT : YES 0 LED LIGHTS FOR 4. Fire ProtecUor. a"dlE" Safety STREET LIGHTS I\U 0 NA Requirements: 5. Electrical tvleter noom, SuU- NO ,NA 0 StatiorU Receivins Station : 6. rrtgregare area ot recreational NO 0 NA 9p"., Space : 7. NO 0 / NA 8. yYafer Jupplv l < YES 20 7 OPEN UTELL AND a) BOREI,TELL 9. Sewerage (Chamber, Lines, Septic YES 0 COMMON SEPTIC Tank, STP): TANK 10. Storm Water Drains: YES 0 ASPER CONSULTANT 71.. Landscaping & Tree plantine r NO 0 NA 1,2. Street Lighting : YES 0 LED LIGHTS 13. Community Buildings: NO 0 74. NA Treatunent And Disposal Of Sewage And Sullage Water: NO /o NA Yours faithfully, ER. AMOL KSHIRSAGAR lienature t Name (IN BLocK LETTERS) of Land surveyor / Architect License Number E/ t74/ gg Agreed & Accepted by: Name: SARA LANDMARKS Date:7047-2023