Annexure A FORM 1 [See Regulation 3] ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date:08/07/2023 To, The Shakti Lifespaces Pvt Ltd (Formally known as Credence Creators Pvt Ltd.). Office no 4, 5 th Floor, ABC East, Beside Prozone Mall, MIDC Chikalthana, Aurangabad. Subject: Certificate of Percentage of Completion of Construction Work of <> having MahaRERA Registration Number P51500033289 being Developed by Shakti Lifespaces Pvt Ltd (Formally known as Credence Creators Pvt Ltd.) Sir, I / We have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of <> having MahaRERA Registration Number P51500033289 being Developed by Shakti Lifespaces Pvt Ltd (Formally known as Credence Creators Pvt Ltd.) Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A Row house block A & B and Apartment Building wing A,B,C & D S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1. Excavation of Apartment Building 100% Up to 30th June 2023 2. Excavation of Row house block A & B 100% Up to 30th June 2023 3. Plinth Apartment Building 100% Up to 30th June 2023 4. Basement Slab Apartment Building 100% Up to 30th June 2023 5. Podium if Any 30% Up to 30th June 2023 6. Stilt Floor 100% Up to 30th June 2023 7. Slab of Super Structure 100% Up to 30th June 2023 8. Internal Walls, Internal Plaster, Floorings, Doors, windows 40% Up to 30th June 2023 within Flats / Premises 9. Sanitary Fittings within Flats / Premises ------ 10. Staircases, Lift Wells & Lobbies at each Floor Level Overhead ------ and Underground Water Tanks 11. External Plumbing & External Plaster, Elevation, Completion of ------ Terraces, with waterproofing of the Building / Wing 12. Installation of Lifts, Water Pumps, Fire Fighting Fittings and ------ Equipment’s as per CFO NOC, Electrical Fittings, Mechanical Equipment’s, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity Row Houses S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1. 2. Excavation of Row house block A & B 100% Up to 30th June 2023 3. Plinth Row house block A 100% Up to 30th June 2023 4. 1st Slab of Row house block A 100% Up to 30th June 2023 5. Plinth Row house block B 100% Up to 30th June 2023 6. 1st Slab of Row house block B 100% Up to 30th June 2023 7. Internal Walls, Internal Plaster, Floorings, Doors, windows 85% Up to 30th June 2023 within Flats / Premises 8. Sanitary Fittings within Flats / Premises ------ 9. Staircases, Lift Wells & Lobbies at each Floor Level Overhead ------ and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, Completion of 15% Up to 30th June 2023 Terraces, with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and ------ Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number S. No. Common Areas & Facilities Proposed Percentage of actual Work Done Details (Yes / NO) (As on date of Certificate) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths 55% Up to 30th June 2023 2. Water Supply (Water Tank) ------ 75% Up to 30th June 2023 ------