MANGGAL DESIGN ARCHITECTS & INTERIOR DESIGNER Annexure A FORM 1 (See Regulation 3] ARCHITECT'S CERTIFICATE Withdrawal of (To be submitted at the time of Registration of Ongoing Project &for Money from Designated Account) Date: 14-10-2023 To, NABHRAJ BUILDERS AND DEVELOPERS PVT LTD. 735, Nabhraj Nandanvan, Opposite Airport, Chikalthana, Chhatrapati Sambhaji Nagar (Aurangabad), Work of Subject: Certificate of Percentage of Completion of Construction Registration Number NABHRAJ TRILOK HEIGHTS having MahaRERA BUILDERS AND P51500032020 being developed by NABHRAJ DEVELOPERS PVT LTD Sir, as Architect / Licensed Surveyor of |/We Mangal Design have undertaken assignment Work of NABHRAJ TRILOK Certifying Percentage of Completion of Construction P51500032020 being developed by HEIGHTS having MahaRERA Registration NumberLTD NABHRAJBUILDERS AND DEVELOPERS PVT Layout / each Building/Wing of the Based on the Site Inspection, with respect to the on date of this Certificate, the Percentage aforesaid Real Estate Project, Icertify that as Wing of the Real Estate Project under of Work Done for each of the Building / percentage of work executed with MahaRERA is as per Table-A1-A5 herein below. The in Table-B. respect to each of the activity of entire Phase is detailed TABLE-A-1 WING -A Percentage of Actual Work S. Tasks /Activity Done No. (As on date of the Certificate) 1 (1) (2) (3) 1 Excavation 100% NA Basements (if any) NA 3 Podiums (if any) 100% Plinth 5 Stilt Floor 100% 100% 6 Slab of Super Structure 7 Internal Walls, Internal Plaster, Floorings, Doors, 80% windows within Flats / Premises Sanitary Fittings within Flats /Premises 50% 50% Staircases, Lift Wells & Lobbies at each Floor Level Overhead and Underground Water Tanks 50% 10 External Plumbing & External Plaster, Elevation, Completion of Terraces, with waterproofing of the Building / Wing 50% 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipments as per GFO-NOC, Electrical Fitings, Mechanical Equipments, Cemplianee to coditiens-ef Environment GRZ NOG: Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to complete Project Any other as per specifications to Agreement of Sale, Activity TABLE-A-2 WING -B Percentage of Actual Work S. Tasks I Activity Done No. (As ondate of the Certificate) (2 (3) (1) 100% 1 Excavation N.A. 2. Basements (if any) N.A. 3. Podiums (if any) 100% 4 Plinth 100% 5. Stit Fioor 100% 6 Slab of Super Structure 80% 7. internal Walls, Internal Plaster, Floorings, Doors, windows within Flats / Premises 30% 8. Sanitary Fittings within Flats /Premises Floor Level 50% 9. Staircases, Lift Wells & Lobbies at each Overhead and Underground Water Tanks 50% Plaster, Elevation, External Plumbing & Externalwaterproofing 10. of the Completion of Terraces, with Buiding / Wing 2 50% 11 Installation of Lifts, Water Pumps, Fire Fighting Fitings and Equipments as per CFO NOG, Electrical Fittings, Mechanical Equipments, Cempliance to conditiens of Eevirenment CR2 NOG, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-A-3 WING-C Percentage of Actual Work S. Tasks / Activity Done No. (As on date of the Certificate) (2) (3) (1) 100% 1. Excavation NA. 2. Basements (if any) N.A. 3 Podiums (if any) 00% 4. Plinth 00% 5. Stilt Floor 00% 6 Slab of Super Structure 00% Doors, 7. Internal Walls, Internal Plaster, Floorings, windows within Flats / Premises 00% 8 Sanitary Fittings within Flats / Premises 00% Level 9. Staircases, Lift Wells & Lobbies at each Floor Overhead and Underground Water Tanks 00% 10. External Plumbing & External Plaster, Elevation, Completion of Terraces, with waterproofing of the Building / Wing 00% 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings Fittings, and Equipments as per CFO NOG, Electrical conditions of Mechanical Equipments, COmplianee t0 EnvironmenttGRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant all other to Building/Wing, Compound Wall and requirenents as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-A-4 WING D Percentage of Actual Work S. Tasks I Activity Done No. (As on date of the Certificate) (2) (3) (1) 3 00% Excavation NA. 2 Basements (if any) NA 3 Podiums (if any) 00% Plinth 00% 5 Stilt Floor 00% 6 Slab of Super Structure 00% 7 Internal Walls, Internal Plaster, Floorings, Doors, windows within Flats / Premises 00% 8 Sanitary Fittings within Flats / Premises Floor Level 00% Staircases, Lift Wells & Lobbies at each Overhead and Underground Water Tanks Plaster, Elevation, 00% 10 External Plumbing & Externalwaterproofing of the Completion of Terraces, with Building /Wing 00% Installation of Lifts, Water Pumps, Fire Fighting Fittings 11. NOG, Electrical Fittings, and Equipment's as per CFO to-eenditions of Mechanical Equipment's, Cempliance Entrance SRvirenment CRZ NOC. Finishing toappurtenant of Areas Lobby/s, Plinth Protection, Paving Wall Compound and all other to Building Wing, complete Project requirements as may be required toof Sale, Any other Agreement as per specifications to Activity TABLE-A-5 WING E Percentage of Actual Work Tasks / Activity Done No. (As on date of the Certificate) (3) (2) 00% (1) Excavation N.A. 1 Basements (if any) N.A. 2 Podiums (if any) 00% 3 Plinth 00% 4. 5. Stilt Floor 00% Slab of Super Structure Floorings, Doors, 00% 7 Internal Wals, Internal Plaster, windows within Flats / Premises 00% Sanitary Fittings within Flats / Premises 00% 8 Staircases, Lift Wells & Lobbies at each Floor Level 9. Tanks Overhead and Underground Water Plaster, Elevation, 00% 10. External Plumbing & Externalwaterproofing of the Completion of Terraces, with Building / Wing 4 00% Installation of Lifts, Water Pumps, Fire Fighting Fittings and Equipment's as per-Gf0 NOe, Electrical Fittings, Mechanical Equipment's, Cemplieee to conditions of Envionment t CRZ NOG- Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building Wing. Compound Wall complete and all other required to Project requirements as may be Sale, Any other as per specifications to Agreement of Activity TABLE-B Works) in respect of the Registered Common Areas (Internal & External Development Phase / Project Number Details Percentage of Common Areas & Facilities Proposed actual Work Done S. (Yes / NO) No. (As on date of Certificate) (4) (5) (3) Internal Project (1) (2) YES 30% Cement Roads 1. Internal Roads & Footpaths From Borewel YES 30% Drainage Line with 2. Water Supply YES 0% Chambers STP or (Chamber, Lines, 3 Sewerage Biodigeter Septic Tank, STP) N.A. Strom Water Drains NO Tree Plantation YES 00% Internal Project 5 Landscaping & Tree Planting YES 00% Street Lights 6 Street Lighting N.A NO STP or Biodigester 7 Community Buildings 00% YES 8. Treatment & Disposal of Sewage and Sullage Water NA. Solid Waste Management & NO 9 Rain Water Disposal YES 00% Water Conservation / Rain Water Harvesting As per 10. Harvesting Norms Common Solar Net YES Metering System 11. Energy Management 00% As per Norms & Fire Safety YES 12. Fire Protection requirements As per MSEB YES 00% Electrical Meter Room, Sub Requirements 13. Station, Receiving Station 14. Others (Option to Add more) Yours faithfully. 5 Signature &Name (IN BLOCK LETRERS)of LandSurveyor lArchitect GGAL License Number ( Agreed & Accepted by: a /ithoba Narale nod28tgrnal.com nCA2011/53e24 Signature of Promoter Name: NABHRAJBUILDERS AND DEVELOPERS PVT LTD Date:14-10-2023 6