PRADEEP V. MOTE * OFFICE B.E. (Cit,il) SHANKARA RESIDENCY Reg. No. E- 615 12016 PLOT NO. 2151216, SHOP NO. 05, * R.C.C. CONSULTANT ULKANAGARI, GARKHEDA, + STRUCTUR.AL ENGINEER AURANGABAD. * CONSULTINGENGINEER Mo. No. 9422213027, 8855844438. FORM.2 ENGINEER'S CERTIFICATE (To be submitted at the lime of Registration of ongoing Proiecl and for vrithdrawal of Money from Designated Account Prgect wise) . Date:2010112022 To SAI SAMRUDDHI PARK Subject Certificate of Cost lncuned for Developmenl of SAI SAMRUDDHI PARK, for Construction of 02 nos 2BHK Row House, 08 nos 2BHK flat, situated on the bearing Gut No. 137, Plot No. 47 to 48, At. Satara,Aurangabad 43t001. demarcated by its boundaries GutNO. 137 North - 0.00 M, WIDE ROAD South- PLOT NO.rt6 East - 6.00 M. WIDE ROAD West - PLOT NO.49 & 50 VILLAGE SATARA, Taluka & District Aurangabad PIN 43100{ admeasuring Total Land Area as Per Possession = 432.00 Sq.mt. & Propooed Built-up area = 760.32 Sq.mt. area being developed by J PROP.VITTHALRAO RAJARAM KALE. Ref: RERA Registration Number: To be register in RERA Sir U We/ PMDEEP V, MOTE have undertaken assignment of certifying Estimated Cosl Ior the Subject Real Estate Project proposed to be registered under RERA being Of'SAl SAMRUDDHI PARK' of the 02 nos 2BHK Row House, 08 nos 2BHK flat situated on lhe bearing Gut No.137 of village SATARA taluka & Dislrict Aurangabad PIN 431001 admeasuring Total Land Area as Per Possession = 432.00 Sq,mt. & Proposed Built-up area = 760.32 Sq.mt. area being developed by SAI SAMRUDDHI PARK. ;'"1\'o^r /N{JY' PT"ADEEP V. IWOTE R.egd. No. DDMCB/R/20211APU01141 Consulting Civil Engineer Plot N0.212 & 2,l6, Shankara Residency, Ulkanagari, Garkhede, Aurangabad. Mob. 94:r.2130?? 1. Following technical professionals are appointed by Owner / Promoter: - i. tt'l/s, DHANANJAY B. DOIFODE (Reg. No CA/2013160839.), Aurangabad as L.S. / Architect; ii. M/s PRADEEP V. MOTE (Er.), Aurangabad as Structurall Consultant. iii. M/s PMDEEP V. MOTE as MEP Consultant. iv. M/s/ PMDEEP V. ilIOTE (Reg. No E-615/2016), Aurangabad as Quantlty Surveyor 2. We have estimated the cost of the completion to obtain Occupation Certifrcate/ Completion Certificate, of the Civil, MEP and Allied works, of the Building(s) of the project. Our estimated cost calculalions are based on the Drawings/plans made available to us for the project under reference by the Developer and Consultants and the Schedule of items and quantity for the entire work ,as calculated by - PRADEEP V. MOTE quantity Surveyof appointed by Developer/Engineer, and the assumption of the cost of malerial, labu and other inputs made by developer, and the sitdinspection canied out by us. 3. We estimate Total Estimated Cost of completion of the building(s) of the afore$aid project under reference as Rs. 1,53,93,000.00 (One Crore Fifty Three Lacks Ninte Three Thoueand Only) The estimated Total Cost of proiect is with reference to the Civil, MEP and allied worts required to be completed for the purpose of obtaining occupation certificate / completion certificate for the building(s) from the Corporation, Aurangabad (planning Authority), being the Planning Aulhority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost lncurred till daie is calculated at fu. 0,fi1 The amount of Estimated Cost lncurred is calculated on the base of amounl of Total Estimated Cost. 5. The Balance cost of Completion of the Civil, MEP and Allied works of the Building(s) of the subiect proiect to obtain Occupation Certificate / Completion Cerliftcate from Corporatiorr, Aurangabad (planning Authority) is estimated at Rs, 0.00 6. I certiff that the Cost of the Civil, MEP and allied work for the aforesaid Project as completed on the date of this certificate is as given in Table A and B below PRAD Regd. No. 0DMCBIR/2021,APU0it4t Consulting Civil Engineer Plot No.212 & 2,l6, Shankara Residency, Ulkanagari, Garkheda, Aurangabad. Mob.9422213027 TABLE A Building / Wing bearing Number Row Houses (to be prepared separately for each Building lVVing of the Real Estate Project) Sr. no, Particulars Amountr in Lakhs Total Estimated cost of the building / wing as on 1. 1,53,93,000.00 N10112022 date ot Registration is Cost lncurred as on 20/0112022. (based on the 2. 30;78,000/- Estimated cost) 3. Work done in Percentage (as Percentage of the 20% estimated cost) 4. Balance Cost to be lncurred(Based on Eslimated Cost) 1,23,15,000t- / Cost lncurred on Additional Extra ltems as on 5. Nrc1n022 not included in the Estimaled Cost Rs. Nil (Annexur+A) TABLE B (b be plEp.nd for the entir€ mgbbred phe3€ ot the r€al o3bto proiect) Sr. no. Particulars Amounts Total Estimated cost of tlire lniernal and External 1. Developmenl Works including amenities and Facilities 14,00,000.00 in the layout as on 20n1n022. Date of Regiskation is Cost lncurred as on 20/0112022 based on lhe 2. 0.00 Estimated cost) ..l Work done in Percentage 3.. lYo (as Percentage of lhe estimated cost) 4. Balanoe Cost to be lncurred(Based on Estimated Cost) 00.00 / Cost lncuned on Additional Extra ltems as on 5. mn1lil21 not included in the Estimated Cost Rs, Nil (Ann€xureA) Yours Faithfully PRADEEP V. MoTE (R PRADEEPV. MOTE . Regd. No. DDMCB/R/2021/APU01l4t Consulting Civil Engineer Ploi No.212 & 216, Shankara Residency, Ulkanagari, Garkheda, Aurangabad. Mob.9422213027