P IYUSH BHAVSAR & ASSOCIATES ARCHITECTS INTERIORDESIGNERS LANDSCAPEDESIGNERS B-No-T8, Dashmesh vihar Co-op Hosing society, Devanagr, Shanoorwadi, Arangabad MOB:-+919766455187E-MAILscalearchitectslabgmail.com FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: ________ To, VANSH INFRASTRUCTURE Sheetal Niwas, Plot No.1-21-138, Naya Bazar, Jalna. Subject: Certificate of Percentage of Completion of Construction Work of Akshad Super City Phase- 2 having Maha RERA Registration Number P51500027259 being developed by VANSH INFRASTRUCTURE Sir, I Piyush Sunil Bhavsar have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction Work Akshad Super City Phase-2 having MahaRERA Registration Number P51500027259 being developed by VANSH INFRASTRUCTURE For the Period of 31.03.23 Based on SiteInspection. with respect to Layout/each of the Building/Wing of the aforesaid Real Estate Project. I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Lavout/Building/Wing Number/Block - F 1 to 10 (to be prepared separately for each Layout /Building /Wing of the Project) Percentage Sr. of Actual work Tasks /Activity No done(as on the date (2) (1) of certificate) (3) 1 Excavation 100.00 2 Basements (if any) 100.00 3 Podiums (if any) NA 4 Plinth 100.00 5 Stilt Floor NA 6 Slabs of Super Structure 100.00 7 Internal walls, Internal Plaster, Floorings, Doors and Windows within 100.00 Flats/Premises 8 Sanitary Fittings within the Flat/Premises 100.00 9 Staircases, Lifts Wells and Lobbies at each Floor level Overhead and 100.00 Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion 100.00 of terraces with waterproofing of the Building/Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities Table A Lavout/Building/Wing Number/Block - G 1 to 10 (to be prepared separately for each Layout /Building /Wing of the Project) Percentage Sr. of Actual work Tasks /Activity No done(as on the date (2) (1) of certificate) (3) 1 Excavation 100.00 2 Basements (if any) 100.00 3 Podiums (if any) NA 4 Plinth 100.00 5 Stilt Floor NA 6 Slabs of Super Structure 100.00 7 Internal walls, Internal Plaster, Floorings, Doors and Windows within 100.00 Flats/Premises 8 Sanitary Fittings within the Flat/Premises 100.00 9 Staircases, Lifts Wells and Lobbies at each Floor level Overhead and 100.00 Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion 100.00 of terraces with waterproofing of the Building/Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities TABLE-B Common Areas (Internal & External Development Works) in Respect of the Registered Phase/project number Percentage ofActual Sr. Proposed Work done(as on the Details No. Common areas and Facilities (2) (Yes/No) date of certificate) (5) (1) (3) (4) 1. Internal Roads & Footpaths YES 0.00 AS PER PLAN 2. Water Supply YES 0.00 AS PER PLAN 3. Sewerage (chamber, lines, Septic YES 0.00 AS PER PLAN Tank, STP) 4. Storm Water Drains YES 0.00 AS PER PLAN 5. Landscaping & Tree Planting YES 0.00 AS PER PLAN 6. Street Lighting YES 0.00 AS PER PLAN 7. Community Buildings NA - - 8. Treatment and disposal of sewage NA - - and sullage water 9. Solid Waste management & NA - - Disposal 10. Water conservation/ Rain water NA - - harvesting 11. Energy management NA - -- 12. Fire protection and fire safety NA - - requirements 13. Electrical meter room, sub- NA - - stationreceiving station 14. Others (option to add more) NA - - Signature & Name (IN BLOCK LETTERS)of L.S./Architect Yours faithfully, Agreed & Accepted by: VINOD Digitally signed by VINOD MURARILAL MURARILAL AGRAWAL Date: 2025.09.16 AGRAWAL 13:30:23 +05'30' Signature of Promoter Ar. Piyush Bhavsar (B. Arch, MCA) Name: Vinod Agrawal Lic No:-CA/2017/86837 Vansh Infrastructure Date :- 16.09.25 Place :- Jalna P IYUSH BHAVSAR & ASSOCIATES ARCHITECTS INTERIORDESIGNERS LANDSCAPEDESIGNERS B-No-T8, Dashmesh vihar Co-op Hosing society, Devanagr, Shanoorwadi, Arangabad MOB:-+919766455187E-MAILscalearchitectslabgmail.com FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: ________ To, VANSH INFRASTRUCTURE Sheetal Niwas, Plot No.1-21-138, Naya Bazar, Jalna. Subject: Certificate of Percentage of Completion of Construction Work of Akshad Super City Phase- 2 having Maha RERA Registration Number P51500027259 being developed by VANSH INFRASTRUCTURE Sir, I Piyush Sunil Bhavsar have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction Work Akshad Super City Phase-2 having MahaRERA Registration Number P51500027259 being developed by VANSH INFRASTRUCTURE For the Period of 31.03.23 Based on SiteInspection. with respect to Layout/each of the Building/Wing of the aforesaid Real Estate Project. I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Lavout/Building/Wing Number/Block - H - 1 to 16 (to be prepared separately for each Layout /Building /Wing of the Project) Percentage Sr. of Actual work Tasks /Activity No done(as on the date (2) (1) of certificate) (3) 1 Excavation 100.00 2 Basements (if any) 100.00 3 Podiums (if any) NA 4 Plinth 100.00 5 Stilt Floor NA 6 Slabs of Super Structure 100.00 7 Internal walls, Internal Plaster, Floorings, Doors and Windows within 100.00 Flats/Premises 8 Sanitary Fittings within the Flat/Premises 100.00 9 Staircases, Lifts Wells and Lobbies at each Floor level Overhead and 100.00 Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion 50.00 of terraces with waterproofing of the Building/Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities Table A Lavout/Building/Wing Number/Block - I 1 to 16 (to be prepared separately for each Layout /Building /Wing of the Project) Percentage Sr. of Actual work Tasks /Activity No done(as on the date (2) (1) of certificate) (3) 1 Excavation 100.00 2 Basements (if any) 100.00 3 Podiums (if any) NA 4 Plinth 100.00 5 Stilt Floor NA 6 Slabs of Super Structure 100.00 7 Internal walls, Internal Plaster, Floorings, Doors and Windows within 100.00 Flats/Premises 8 Sanitary Fittings within the Flat/Premises 100.00 9 Staircases, Lifts Wells and Lobbies at each Floor level Overhead and 100.00 Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion 50.00 of terraces with waterproofing of the Building/Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities TABLE-B Common Areas (Internal & External Development Works) in Respect of the Registered Phase/project number Percentage ofActual Sr. Proposed Work done(as on the Details No. Common areas and Facilities (2) (Yes/No) date of certificate) (5) (1) (3) (4) 1. Internal Roads & Footpaths YES 0.00 AS PER PLAN 2. Water Supply YES 0.00 AS PER PLAN 3. Sewerage (chamber, lines, Septic YES 0.00 AS PER PLAN Tank, STP) 4. Storm Water Drains YES 0.00 AS PER PLAN 5. Landscaping & Tree Planting YES 0.00 AS PER PLAN 6. Street Lighting YES 0.00 AS PER PLAN 7. Community Buildings NA - - 8. Treatment and disposal of sewage NA - - and sullage water 9. Solid Waste management & NA - - Disposal 10. Water conservation/ Rain water NA - - harvesting 11. Energy management NA - -- 12. Fire protection and fire safety NA - - requirements 13. Electrical meter room, sub- NA - - stationreceiving station 14. Others (option to add more) NA - - Signature & Name (IN BLOCK LETTERS)of L.S./Architect Yours faithfully, Agreed & Accepted by: VINOD Digitally signed by VINOD MURARILAL MURARILAL AGRAWAL Date: 2025.09.16 AGRAWAL 15:35:01 +05'30' Signature of Promoter Ar. Piyush Bhavsar (B. Arch, MCA) Name: Vinod Agrawal Lic No:-CA/2017/86837 Vansh Infrastructure Date : 16.09.25 Place : Jalna P IYUSH BHAVSAR & ASSOCIATES ARCHITECTS INTERIORDESIGNERS LANDSCAPEDESIGNERS B-No-T8, Dashmesh vihar Co-op Hosing society, Devanagr, Shanoorwadi, Arangabad MOB:-+919766455187E-MAILscalearchitectslabgmail.com FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: ________ To, VANSH INFRASTRUCTURE Sheetal Niwas, Plot No.1-21-138, Naya Bazar, Jalna. Subject: Certificate of Percentage of Completion of Construction Work of Akshad Super City Phase- 2 having Maha RERA Registration Number P51500027259 being developed by VANSH INFRASTRUCTURE Sir, I Piyush Sunil Bhavsar have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction Work Akshad Super City Phase-2 having MahaRERA Registration Number P51500027259 being developed by VANSH INFRASTRUCTURE For the Period of 31.03.23 Based on SiteInspection. with respect to Layout/each of the Building/Wing of the aforesaid Real Estate Project. I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Lavout/Building/Wing Number/Block - J - 1 to 8 (to be prepared separately for each Layout /Building /Wing of the Project) Percentage Sr. of Actual work Tasks /Activity No done(as on the date (2) (1) of certificate) (3) 1 Excavation 100.00 2 Basements (if any) 100.00 3 Podiums (if any) NA 4 Plinth 100.00 5 Stilt Floor NA 6 Slabs of Super Structure 100.00 7 Internal walls, Internal Plaster, Floorings, Doors and Windows within 100.00 Flats/Premises 8 Sanitary Fittings within the Flat/Premises 100.00 9 Staircases, Lifts Wells and Lobbies at each Floor level Overhead and 0.00 Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion 0.00 of terraces with waterproofing of the Building/Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities Table A Lavout/Building/Wing Number/Block - K 1 to 8 (to be prepared separately for each Layout /Building /Wing of the Project) Percentage Sr. of Actual work Tasks /Activity No done(as on the date (2) (1) of certificate) (3) 1 Excavation 100.00 2 Basements (if any) 100.00 3 Podiums (if any) NA 4 Plinth 100.00 5 Stilt Floor NA 6 Slabs of Super Structure 100.00 7 Internal walls, Internal Plaster, Floorings, Doors and Windows within 100.00 Flats/Premises 8 Sanitary Fittings within the Flat/Premises 100.00 9 Staircases, Lifts Wells and Lobbies at each Floor level Overhead and 0.00 Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion 0.00 of terraces with waterproofing of the Building/Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities TABLE-B Common Areas (Internal & External Development Works) in Respect of the Registered Phase/project number Percentage ofActual Sr. Proposed Work done(as on the Details No. Common areas and Facilities (2) (Yes/No) date of certificate) (5) (1) (3) (4) 1. Internal Roads & Footpaths YES 0.00 AS PER PLAN 2. Water Supply YES 0.00 AS PER PLAN 3. Sewerage (chamber, lines, Septic YES 0.00 AS PER PLAN Tank, STP) 4. Storm Water Drains YES 0.00 AS PER PLAN 5. Landscaping & Tree Planting YES 0.00 AS PER PLAN 6. Street Lighting YES 0.00 AS PER PLAN 7. Community Buildings NA - - 8. Treatment and disposal of sewage NA - - and sullage water 9. Solid Waste management & NA - - Disposal 10. Water conservation/ Rain water NA - - harvesting 11. Energy management NA - -- 12. Fire protection and fire safety NA - - requirements 13. Electrical meter room, sub- NA - - stationreceiving station 14. Others (option to add more) NA - - Signature & Name (IN BLOCK LETTERS)of L.S./Architect Yours faithfully, Agreed & Accepted by: VINOD Digitally signed by VINOD MURARILAL MURARILAL AGRAWAL Date: 2025.09.16 AGRAWAL 17:38:03 +05'30' Signature of Promoter Ar. Piyush Bhavsar (B. Arch, MCA) Name: Vinod Agrawal Lic No:-CA/2017/86837 Vansh Infrastructure Date : 16.09.25 Place : Jalna P IYUSH BHAVSAR & ASSOCIATES ARCHITECTS INTERIORDESIGNERS LANDSCAPEDESIGNERS B-No-T8, Dashmesh vihar Co-op Hosing society, Devanagr, Shanoorwadi, Arangabad MOB:-+919766455187E-MAILscalearchitectslabgmail.com FORM 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: ________ To, VANSH INFRASTRUCTURE Sheetal Niwas, Plot No.1-21-138, Naya Bazar, Jalna. Subject: Certificate of Percentage of Completion of Construction Work of Akshad Super City Phase- 2 having Maha RERA Registration Number P51500027259 being developed by VANSH INFRASTRUCTURE Sir, I Piyush Sunil Bhavsar have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of Completion of Construction Work Akshad Super City Phase-2 having MahaRERA Registration Number P51500027259 being developed by VANSH INFRASTRUCTURE For the Period of 31.03.23 Based on SiteInspection. with respect to Layout/each of the Building/Wing of the aforesaid Real Estate Project. I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Lavout/Building/Wing Number/Block - N - 1 to 16 (to be prepared separately for each Layout /Building /Wing of the Project) Percentage Sr. of Actual work Tasks /Activity No done(as on the date (2) (1) of certificate) (3) 1 Excavation 100.00 2 Basements (if any) 100.00 3 Podiums (if any) NA 4 Plinth 100.00 5 Stilt Floor NA 6 Slabs of Super Structure 100.00 7 Internal walls, Internal Plaster, Floorings, Doors and Windows within 50.00 Flats/Premises 8 Sanitary Fittings within the Flat/Premises 0.00 9 Staircases, Lifts Wells and Lobbies at each Floor level Overhead and 0.00 Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion 0.00 of terraces with waterproofing of the Building/Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and NA Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities TABLE-B Common Areas (Internal & External Development Works) in Respect of the Registered Phase/project number Percentage ofActual Sr. Proposed Work done(as on the Details No. Common areas and Facilities (2) (Yes/No) date of certificate) (5) (1) (3) (4) 1. Internal Roads & Footpaths YES 0.00 AS PER PLAN 2. Water Supply YES 0.00 AS PER PLAN 3. Sewerage (chamber, lines, Septic YES 0.00 AS PER PLAN Tank, STP) 4. Storm Water Drains YES 0.00 AS PER PLAN 5. Landscaping & Tree Planting YES 0.00 AS PER PLAN 6. Street Lighting YES 0.00 AS PER PLAN 7. Community Buildings NA - - 8. Treatment and disposal of sewage NA - - and sullage water 9. Solid Waste management & NA - - Disposal 10. Water conservation/ Rain water NA - - harvesting 11. Energy management NA - -- 12. Fire protection and fire safety NA - - requirements 13. Electrical meter room, sub- NA - - stationreceiving station 14. Others (option to add more) NA - - Signature & Name (IN BLOCK LETTERS)of L.S./Architect Yours faithfully, Agreed & Accepted by: VINOD Digitally signed by VINOD MURARILAL MURARILAL AGRAWAL Date: 2025.09.17 AGRAWAL 11:38:11 +05'30' Signature of Promoter Ar. Piyush Bhavsar (B. Arch, MCA) Name: Vinod Agrawal Lic No:-CA/2017/86837 Vansh Infrastructure Date:-16.09.25 Place : - Jalna