r..,EEEffiMffi Amol Kshirsagar Architectural Planner, Consulting Engineer & Annexure - B Valuer FORM - 2 [See Regulation 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of ongoing project and for withdrawa.l of Money from Designated Bank Account) Date: 10-07-2023 To, SAKAMBARI BUILDCON, 11, A-wtNG, 1"t FLooR, NARAYAN pLAzA, CANNAUGHT PLACE, CIDCO, AURANGABAD Subject: Certificate of Cost lncurred for Development of SARA VATIKA having MahaRERA Registration Number p5l5OOO25439 being developed by SAKAMBART BU|LDCON. (For Apr to Jun 2023 eTR) 1 I i we Er. AMOL KSHTRSAGAR have undertaken assignment of certifying Estimated cost for SARA VATIKA having MahaREM Registration Number ps1500025439 being developed by SAKAMBARI BUtLDCON. 2. we have estimated the cost of civil, MEp and Allied works required for completion of the apartments & proportionate completion of internal & external works of the project as per the specifications mentioned in the Agreement of Sale. our estimated cost calculations are based on the Drawings/plans made available to us for the project under Reference by the Developers / consultants. The schedule of ltems & euantity required for the entire work as calculated by euantity Surveyor* appointed by the Developer/Engineer, the assumption of the cost of material,.labour & other inputs made the Developer, and the site lnspection carried out by us to ascertain / confirm the analysis given to us. 3. We mate Total Estimated Cost of completion of the aforesaid prolect mentioned erence at Rs. 6,27,91,8811 (Total of Table A & B) at the time of Registration. The Total Cost of Project is with reference to the Civil, MEp & Allied Works ofthe apartments & proportionate completion of Internal & external works, as per the mentioned in the Agreement of Sale & for the purpose of obtaining Occupation cate / Completion Certificate for the Buitding(s) / Wing(s) / Layout / Plotted fTom the ASST. DIRECTOR TOWN PLANNING - AUMNGABAD Flat No.4, Plot No. 102, Nathprangan,Garkheda, Chhatrapati Sambhajinagar Mob. : 09960669921 being the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated cost incurred ti date is carcurates to Rs. 6,27,91,gg1/- (Totar of rabre & B). The Amount of Es.fimg.t_e.d..q9-sl..lneuned..is..ce!culal9.d..-o.n..!he...b.esis...-oj..inputA m.a.ter! els./.seryrses. u.cp..d..&. un!!..sp..cL.aI.the9e. items. 5. The Balance cost of compretion of the civir, MEp & Aflied works for compretion of Apartments & proportionate completion of internal & external works, as per specifications mentioned in Agreement of sare, of the aforesaid project is estimated at Rs. NIU- (Total ofTabteA&B). I certify that the cost of civil, MEp & Allied work for apartments & proportionate internal & external works, as per the specifications mentioned in Agreement of sare, of the aforesaid Project as compreted on the date of this certificate is as given in Tabre A & B below: TABLE - A Building / Wing / Layout / plotted Development For Building 81 & 82 S. Particulars Amount (in Rs.) No. 1. Total Estimated Cosl-t Suitarny Wing, Layout / Rs. 4,93,83,675t Plotted Development as on date of Reqistraiion is 2. Cost incurred as on dEte of C-ertificat,e Rs. 4,93,83,675^ 30 June 2023 J. Work Done in PercentagElEGFErcentage of Estimated Cost) Tod%- 4. Balance Cost to Oe iniurred r. ((baied on Rs. NIL/- Estimated Cost) ( Cost incurred on Additional / Extra ttems not included in the Estimated Cost (Table-C) TABLE - B Internal & External Development Works For Building BL &, 82 S. Particulars Amount (in Rs.) No. 1. Total Estimated cosffi Rs. '1,34,08,206t Development Works including amenities & facilities in the Layout as on date of Registration is 2. Cost incurred as on date of Certificate Rs. '1,34,08,206^ 30 June 2023 ? Work Done in PercenEge (as percentage of 100o/o Estimated Cost) 4. Balance Cost to Ue incurreo ;(faleo on Rs. NIL^ Estimated Cost) 5. Cost incurred on RaOitionat lE{ra ltenrs not included in the Estimated Cost (Table-C) -.7.l.-\ krw) ffiK\ tlrrrlc: \7' I a.e. tcr"rr I W9 Yours Er. AMOL KS ffi Signature & Name (tN BLOCK LETTERS) with Stamp of Engineer Local Authority License Number Reg No _ E I 1i4 t 93 Agreed & Accepted by: Signature oi fudmoter Name; SAKAMBART BUTLDCON Date: 10-Ol -2023 fl* 9116) Note: 1. The scope of work is to complete Registered Real Estate project as per drawings approved from time to time as per specifications mentioned in tn" Agr""."ni io Sale. (*) Quantity survey can be done. by lhe office of Engineer or can be done by an independent Quantity surveyor, who's certificate -Quantity . of carcurated, can be relied up on by Engineer. ln case. of independent quantity surveyor being appointed by Developer, the name has to be mentioned at'tne quantity are being carcurated by office of fiace marked (*) & in case Engineer, the name of person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked ("). J- (..) Barance cost to be incurred (4) may vary from difference between Totar Estimated cost (1) & actuar cost incurred oue 1i1 to deviation in quantity required / escaration of cost etc' As this_is an Estimated cost any deviation quantity required for the Deveropment of Rear Estate project wirr resurt in an amenoment of the cost incurred / to be incurred. 4. All components of work with specifications are indicative & not exhaustive U tfr" are any- deviations / quatifications. Exampte: Any deviation in l^,:X^f:ly 'l from input material used specifications in Agreement of Sale. TABLE - C List of Extra / Additional / Deleted Items considered in the Cost (Which were not parts of the origina-l Estimate of Total Cost) S. No. List of Extra / Additional / Deleted ltenrs Amount (in Rs.) 1. ,.'1- 2. (, f,ffi; #!