Opp. HotelAtithi, Jalna Road, Aurangabad. j,.W-ffi-ffi; Telefax: 0240 - 2451616 5-6-37,Anand Building, Opp. Sant Rang Mandir, New Usmanpura, Aurangabad, Telefax: 0240 - 2325367,2348634 FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 03/02 /2018 To M/s Devanand Narayanrao Kotgire (HUF) Disha Square Sutgirni Chowk, Garkheda Aurangabad 43 1 000 1 Subject: Certificate of Percentage of Completion of Construction Work of 3 No. of Building A1' 42, A3o 81 B2 of the Project DISHA KUNJABAN PHASE - I [Registration No. - P515000011081 situated on Gut No. 52i2 part, Waluj Mahanagar - I, Wadgaon Kolhati' Aurangabad demarcated by its boundaries ( latitude and longitude of the end points) To the North - 15 Mtr Wide DP Road To the South - Approach, Open Space & Building Cl To the East - 6 Mtr Approach & Part of Gut No. 52 To the West - Approach & Building Cl,C2 Of Division Aurangabad village Wadgaon Kolhati Waluj taluka Aurangabad District Aurangabad admeasuring 4885.22 sq.mts for Phase - I comprising Building A1 A2, A3,Bl B2 and Open Space for Approach & Building Cl, C2 is 493.37 sq. mtrs area being developed by Promoter M/s Devanand Narayanrao Kotgire (HUF) Opp. HotelAtithi, Jalna Road, Aurangabad. &K ssCIflATE$_ ,$r-J Telefax: 0240 - 2451616 5-6-37,Anand Building, Opp. Sant Rang Mandir, New Usmanpura, Aurangabad, Telefax: 0240 - 2325367 ,2348634 Sir, I Manish Kale Partner of AKW ASSOCIATE,S have undefiaken assignment as Architect /Licensed Surveyor of certiffing Percentage of Completion of Construction Work of the Phase - I of the Project comprising Al A2, .A3, Bl 82 of the Project Disha Kunjaban, situated on the plot bearing Gut no Gut No. 52l2 part, Waluj Mahanagar - I, Wadgaon Kolhati, Aurangabad admeasuring 4885.22 sq.mts. for Phase - 1 comprising Building A1 A2, .A3, B1 B2 and Open Space for Approach & BuildingCl, C2 is 493.37 sq. mtrs area being developed by Promoter M/s Devanand Narayanrao Kotgire (HUF) 1. Following technical professionals are appointed by Owner / Promoter:- (i) AKW Associates as Architect; (ii) Core Consultants as Structural Consultant (iii) Shri Sachin Baburao Bagade as Site Supervisor Based on Site Inspection, with respect to each of Wing of the aforesaid Real Estate Project, I certiff that as on the date of this cerlificate, the Percentage of Work done for Phase - 1 comprising Building Al A2, ,A3, Bl 82 of the Real Estate Project - Disha Kunjaban as registered vide number P51500001108 under Maha RERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the cntire phase is detailed in Table B. Opp. HotelAtithi, Jalna Road, Aurangabad Telefax: 0240 - 2451616 5-6-37,Anand Building, Opp. Sant Rang Mandir, New Usmanpura, Aurangabad, Telefax: 0240 - 2325367,2348634 Table A DISHA KUNJABAN - PHASE l(Comprising Building Al L2, A3, Bl B2) S. No. Tasks / Activity Percentage of Work L Excavation 1,OO% 2 X Number of Basement(s) and Plinth LOO% 3 X Number of Podiums NA 4 Stilt Floor 1.00% 5 X number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats / 6 Premises, Doors and Windows to each of the Flat / Premise rcj% Sanitary Fittings within the Flat / Premises, Electrical Fittings with the Flat / Premises o% Staircases, Lift Wells and Lobbies at each Floor Level R connecting Staircases and Lifts, Overhead and Under- too% ground Water Tanks The external plumbing and external plaster, elevation 9 completion of terraces with water-proofing of the Building rcj% / Wing Installation of lifts, water pumps, Fire Fighting Fittings and Equipments as per CFO NOC, Electrical fittings to Common Areas, electro mechanical equipment, Compliance to conditions of environment / CRZ NOC, Finishing to 10 98% entrance lobby/s, plinth protection, paving of area appurtenant to Building / Wing, Compound Wall and all other requirements as may be required to Obtain Occupation / Completion Certificate Overall Percentage of Completion of the work done for the IT entire Building / Wing 98% Opp. HotelAtithi, Jalna Road, Aurangabad. Telefax: 0240 - 2451616 5-6-37,Anand Building, Opp. Sant Rang Mandir, New Usmanpura, Aurangabad, Telefax: 0240 - 2325367,2348634 TABLE-B Internal & External Development Works in Respect of the entire Registered Phase DISHA KUNJABAN - PHASE 1 (Comprising Building A-l A2, A3, Bl 82) Common Areas and Facilities, Amenities Proposed Percentage of Details Completion Internal Roads and Footpath Yes too% RCC & Paver Blocks Water Supply Yes too% Cidco Water Connection Sewerage (Chamber, Line, Septic, Tank, STP) Yes IOO% Chamber Line & Drainage Line Only Storm Water Drains NA Landscaping & Tree Planting Yes too% Regular Tree Plantation in Open Space Street Lighting Yes 1.OO% Generai Tube Lights Community Buildings NA Treatment and Disposal of Sewage and Sullage NA Water Solid Waste Management and Disposal NA Water Conversation, Rain Water Harvesting Yes LO0% Ground water recharge ofTerrace Water through Bore well Energy Management NA Fire Protection and Fire Safety Requirements NA Electrical Meter Room, Sub-station, Receiving Yes 1,00% Completed Station Aggregate Area of Recreational Open Space Yes 98% Open Space Development is almost completed for the resistered Open Parking Yes 100% Completed Yours Faithfully <\ <-I I \ / ,r.rru -*t c*'{?5- Ar. MANISH V. KALE Reg.No.CA -93/15610 For AKW Associates