FORM-2A (See MahaRERA order No. Of 2018) ENGINEER'S CERTIFICATE FOR QUALITY ASSURANCE To The SARA BUILDERS AND DEVELOPERS, SARA GOKULDHAM-A, BUILDING, GUT NO. 701 at Aurangabad (M Corp.), Aurangabad, Aurangabad, 431007. Quality Assurance Certificate (Certificate No. FORM -2A for the quarter MARCH-2019) Subject: - Certificate for quality of materials used and quality of Construction and workmanship for the Work of 3 No. off buildings(s)/ 3 Wings(s) of the SARA BUILDERS AND DEVELOPERS of the project situated GUT NO. 701 at Aurangabad (M Corp.), Aurangabad, Aurangabad, 431007, demarcated by its boundaries (latitude and longitude of the end points) OPEN SPACE OF LAYOUT to the North, c TYPE BUILDING OF SAME HOUSING SCHEME to the South, INTERNAL ROAD to the East, LAND OF AIRPORT AUTHORITIES to the West, of Division Aurangabad, village Aurangabad, taluka Aurangabad, District Aurangabad, Pin-431007, admeasuring 1823 Sq. Mtrs. area being developed by SARA BUILDERS AND DEVELOPERS. Reference: - MahaRERA Registration Number - PS1500003721. Sir, of this assignment of supervision IHARISH BHARUKA have undertaken an real estate projec 1. Our Responsibility: development permission in accordance with the the work To Carry out of work and submit certificate of supervision plan and and to n d as per the approved authorized laboratory in-situ o r in the material testing and to c a r r y out specification, a s per prescribed and workrmanship Cnsure qluality of work relevant code of practice. and o r other s per NBC 1. Material Testing: materials, mandatory checks on the basic 1/We have applicd following constructions. used in the i. Cement:- soundness, setting time, compressive tested for its lineness, lt has been other relevant IS/BS/NBC code 3535:1986 o r a s per 1S the permissible strength ete. a s per and its results a r e within standards code o r a s per industry limits. ii. Coarse aggregate:- value, deleterious materials, clay lumps, crushing tested, for relevant IS/BSNBC code or It has been other 2430:1986 or a s per a s per 1S impact value results a r e within the permissible limits. standards and its a s per industry iii. Bricks/blocks: strengths etc. a s lor water absorption, crushing They have been tested code or a s pr industry other relevant 1S/BS/NBC 5454:1978 or a s per per 1S within permissible limits. s t a n d a r d s and its results a r e iv. Concrete/Ready-mix Concrete for v a r i o u s periods as per IS strength testcd for compressiVe It has been per as other relevant IS/BS/NBC codes, and 1S 1199 or as pcr 50:2000 permissible limits. results are within s t a n d a r d s and its industry v. Steel for concrete: It has been tested as per IS 2062:2011 or as per other relevant IS/BS/NBC code or a s per industry standards for tensile strength, elongation and gauge length etc. and its results are within permissible limits. vi. Testing of Other materials: Other materials like sand, crushed sand, floor tiles, fixtures, and fittings, conform out all items) used in this project pipes and sanitary fittings etc. (List for to relevant IS/BS/ NBC code or a s per standards laid down by the industry a particular material. 2. Workmanship: carried out under our 1/we hereby certify that work has been and quality is satisfactory supervision. We further certify that workmanship and up to the mark and the work has been acceptable within the permissible limits off deviations as per relevant code of practice. 3. Electrical Materials and workmanship: works of all the clectrical wiring / connections /lit installation/ other electrical installations have been carried out under authorized /registered electrical engineer and its records has been maintained. The materials used conform to the relevant I.S/B.S/ National Building codes or as per industry standards. 4. Structural engineer: Promoters has cngaged structural engineer Mr. N G KARKHANE having Licenses No.-AMC-59/89 having office No.-0240-2452305 cell No. 9823028081 The structural design of buildings in this project has been done under his supervision. He has checked the soil report before laying PCC for foundation in consolation with soil consultant. The formwork and concrete mix other relevant codes a s design has been done a s per IS 10262:2009 or per as STABILITY and SAFETY applicable. His periodic checks and certificates for have been kept orn record. 5. Preservation of records: Record of all test results of this project have been properly kept in the prescribed formats and will be preserved at least up to the defect liability period or for the period as required by any other provision off law. 6. Please specily materials or any other item off work which were not conforming to the standard specifications and which were not rejected. 1:- Coloring, 2:- Aluminum, 3:-Doors & It's Fitting, 4:Tiles, 5:- CP &% sanitary. Yours Faithfully, Signature of Engineer Name: Harish Bharuka Phone No: 9960669925 Place: Aurangabad,