FORM-2A [See MahaRERA order no. of 2018] ENGINEER'S CERTIFICATE FOR QUALITY ASSURANCE To, Deepak Jhunjhunwala Raghuvir Realities, Harikunj housing project, Pharola, Paithan road, Aurangabad. Quality Assurance Certificate (Certificate no CRT/QUA/RR/HK-14 for the quarter ending 30.06.2019) Subject: Certificate for quality of materials used and quality of Constructicon and workmanship for the Work of 2 No. of Building(s) D and G and A and B Wings(s) of the Phase of the project situated on the plot bearing C. s. No./C.T.s. No./ Survey No./Final plot no. 1 demarcated by its boundaries (latitude and longitude ofthe end points) 194346, 751746 to the North 194342, 751747 to the South 194344, 751747 to the East 194344, 751745 to the West of Division Farola village Paithan taluka Aurangabad District 431105 PIN admeasuring 7119.69 sq.mtrs. area being developed by Raghuvir Realities, Deepak Jhunjhunwala. Reference: MahaRERA Registration Number- P51500000992. Sir, wWe Kishore Ashok Mareadiya have undertaken an assignment of supervision of this real estate project. 1. Our Responsibility: - To carry out the work in accordance with the development permission and as per the approved plan and submit certificate of supervision of work and to carry out material testing in-situ or in the authorized laboratory and to ensure quality of work and 1. Material Testing: we, have applied following mandatory checks on the basic materials, used in the construction. i. Cement It has been tested for its fineness, soundness, setting time, compressive strengthetc as per IS code 3535:1986 or as per other relevant I5/85/NBC code, or as per industry standards and its results are within the permissible limits. ii. Coarse aggregate It has been tested, for deleterious materials, clay lumps, crushing value, impact value as standards per IS 243011986 or as per other relevant IS/BS/NBC code or as per industry and its results are within the permissible limits. ii. Bricks/ blocks etc. as IS 5454:1978 They have been tested for water absorption, crushing strength per or as per other relevant IS/85/NBC code or as per industry standards and its results are within permissible limits. iv. Concrete/Ready-mix Concrete- as per 15 456:2000 and It has been tested for compressive strength for various periods standards and its IS 1199 or as per other relevant IS/BS/NBC codes, as per industry results are within permissible limits. v. Steel for concrete- other relevant IS/BS/NBC code or as It has been tested as per IS 2062:2011 or as per tensile strength, elongation and gauge length etc. and its per industry standards for results are within permissible limits. vi. Testing of Other materials floor tiles, fixtures and {ittings, pipes and Other materials like sand, crushed sand, used in this project conform to relevant sanitary fittings etc. (List out all items) the Industry for a particular material. IS/BS/NBC code or as per standards laid down by 2. Workmanship: been carried out under our supervision. We further /we hereby certify that work has is satisfactory and up to the mark and the work has certify that workmanship and quality limits of deviations as per relevant code of been acceptable within the permissible practice. 3. Electrical Materials and workmanship: - Works of all the electrical wiring/connections/lift installation/other electrical installations ave been carried out under authorized/registered electrical has been maintained. engineer and its records ne materials used industry standards. conform to the relevant I.S/ B.S/ National Building codes or as per 4. Structural engineer: -Promoters has engaged structural having Licenses engineer Mr. Pradeep Mote no.DDMCB/R/2021/APL/01141 having office no cell no. 8855844438. The structural design of He has checked the soil buildings in this project has been done under his supervision. report before laying PCC for foundation in consultation with soil consultant. The formwork and concrete mix or as per other relevant design has been done as Is 10262:2009 per codes as applicable. His periodic checks and certificates for STABILITY and SAFETY have been kept on record. 5. Preservation of records: - Record of all test results of this project have been properly kept in the formats and will be preserved at least up to the defect liability period orprescribed for the period as required by any other provision of law. 6. Please specify materials or any other item of work which were not conforming to the standard specifications and which were not rejeded. Nil. Yours Faithfully, Signature of Engineer(SiteSupervisor) Name Kishore Ashok Mareadiya Phone no.7385353888 Place: Aurangabad.