ff r -4.- Jfi- .Abil (D.c.B.) CIVI L ENGIN EERING GONSU LTANT + Planning 1 Estimates * Supervision & Turn Key Works Ref.No. Date : Form - 2 [See Regulation 3] Engi neer's Certificate (To be submitted at the time of Registration of Ongoing Project and for Withdrawal of Money from Designated Account - Project Wise) Date" 20/04/2025 To, M/s. Shikhar lnfra Sanman Prestige Station Road, Nanded. PAN:AFAFS8070F Subject: Certificate of Cost incurred for Development of " Kala Mandir Trust Auditorium, Cultura! Halls and Commercial Complex " having MahaRERA Registration Number P511OOO797L7 being developed by M/s. Shikhar lnfra' Sir, 1. lA&e Er A. M. Adil have undertaken the assignment of certifying Estimated cost for Kala Mandir Trust Auditorium, Cultural Halls and Commercial Complex " having MahaRERA Registration Number P511OOO797t7 being developed by M/s. shikhar lnfra. 2.We have estimated the cost of Clvil, MEP and Allied works required for completion of the as per apartments and proportionate completion of internal & external works of the project on specifications mentioned in agreement of sale. Our estimated cost calculations are based the drawings/plans made available to us for the project under reference by the Developer/Consultants. The schedule of items and quantity required for the entire work as calculated by euantity Surveyor* appointed by Developer/Engineer, the assumption of - the cost of material, labour and other inputs made by the developer, and the site i carried out by us to ascertain/confirm the above analysis given to us' H,No.1 -23-56,Rauf Colony,Near Royal Rose,Chaitanya Nagar,NAN Cell :9766 412844 Emai I :musayyabadi l@gmait.com BTE Certificate No, 3.We estimate Total Estimated Cost of completion of the aforesaid project under reference at Rs.2.3.15,.00.009/- (Total of Table A and B) at the time of registration. The estimated Total cost of project is with reference to the Civil, MEP and allied works required for completion of the apartments and proportionate completion of internal & external works of the project as per specifications mentioned in agreement of sale and for the purpose of obtaining occupation certificate/completion certificate for the Buildings/ Wings/Layout/Plotted Development from the NWCMC being the planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The estimated cost incurred till date is calculated at Rs. 6.10.78.33Q/- ffotal of Table A and B). The amount of estimated cost incurred is calculated on the basis of input materials/services used and unit cost of these items. 5.The balance cost of completion of the Civil, MEP and allied works required for completion of the apartments and proportionate completion of internal & external works of the project as per specifications mentioned in agreement of sale, of the Project is estimated at Rs.17.04.21.6701- (Total of Table A and B) 6. I certify that the cost of the Civil, MEP and allied works for the apartments and proportionate internal & external works, as per specifications mentioned in agreement of sale, of the aforesaid Project as completed on the date of this certificate i given in Table A and B below: TABLE A Building/Wing/Layout/Plotted Development bearing Number "Kala Mandir Trust Auditorium, Cultural Halls and Commercial Complex " or called (to be prepared separately for each Building /Y{ing/Layout/Plotted Development of the Real Estate Project) Sr. Particulars Amounts No. Total Estimated cost of the buildings/wings as on 1 23,15,00,000/- date of Registration is 2 Cost incurred as on date of certificate 6,10,78,330/- Work done in Percentage /(as Percentage of the 3 25.350/o estimated cost) 4. Balance Cost to be lncurred** 17,04,21,670/- Cost lncurred on Additional /Extra ltems /not 5 NIL lncluded in the Estimated Cost (Table - C) TABLE B lnternal & External Development works in respect of the Registered Phase Total Estimated cost of the internal and external Development Works including amenities and facilities in the layout as on date of Registration is a"rt'r.r""d*ffi W"if. a"* l. P"r*.t.g. (rr P.r*.t.g" .f fi. estimated cost) M (Based on Estimated Cost) Cost lncurred on Additional /Extra ltems not lncluded in the Estimated Cost (Table - C) 'N.w.c.u'G' \zl lrn Llcr*:e- l(o' lrn sl/ 43 ,,i) *>-- \&a.m. Yours faitf,fully, ( Er. A. M. (Proprietor) I Local Authority License :- 066/CN297040 Agreed and Accepted by: For: M/s$hikhar lnfra w s idd hu n*]fi , h", lr,r. ri Partner Date:20/04/2025 Note: 1. The scope of work is to complete Registered Real Estate Project as per drawings approved from time to time and as per specifications mentioned in agreement of sale. 2. (*) Quantity survey can be done by office of Engineer or can be done by an independent Quantity Surveyol whose certificate of quantity calculated can be relied upon by the engineer. ln case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked(*) and in case quantity are being calculated by office of Engineer, the name of the person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked(*). 3. (**) Balance cost to be incurred (4) may vary from Difference between Total estimated cost (1) and Actual Cost incurred (2) due to deviation in quantity required/ escalation of cost etc. As this is an estimated cost, any deviation in quantity required for development of the Real Estate Project will result in amendment of the cost incurred/ to be incurred. 4. All components of work with specifications are indicative and not exhaustive. 5. Please specify if there are any deviations/qualifications. Example: Any deviations in input material used from specifications in agreement of sale.