SANJAY SITARAM NIMBALKAR N-S E-04-02 GULMOHAR COLONY,CIDCO 10 ,AURANGABAD PAN- AKOPN2284M ,Mobile NO -9372233690 ---------------------------------------------------------------------------------- FORM-2 [see Regulation 3] ENGINEER'S CERTIFICATE (to be submittedat the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account- Project wise) Date: 29.1.2018 To The Directors Pride Ventures (I) Pvt Ltd Office No. 101 to 104 Sai Trade Centre Station Road Aurangabad 431001 Subject: Certificate of Cost Incurred for Development of (Pride Phoneix] for Construction of 1No. r:t)Rf\h " of Building "C-1 C-2" of the Project PRIDE PHOENIX BUILDING - "C-1 C-2" REGISTER No- [P51500000337] situated on Gut No. 736, behind Civil Hospital Jalna Road, Chikalthana, A':Irangabad demarcated by its boundaries ( latitude and longitude of the end points) side margin and gut no 732 to the North Internal Road, Open Space And Club House to the South Internal Road and Building Type B to the West Building Type D to the East of Division Aurangabad village Chikalthana taluka Aurangabad District Aurangabad PIN 431001 admeasuring 2618.56 sq.mts. for Building "C-l - C-2" and Open Space for "C-l -C-2" Building is 230.00 sq. mtrs Area being developed by Mis Pride Ventures (I) Pvt Ltd Sir, I Sanjay Sitaram Nimbalkar have undertaken assignment of certifying Estimated Cost for the Subject Real Estate Project proposed to be registered under Maha RERA, being BUILDING PRIDE PHOENIX BUILDING - "C-1 C-2" situated on the plot bearing Gut No. 736 of Division Aurangabad village Chikalthana taluka Aurangabad District Aurangabad PIN 431001 admeasuring 2618.56 sq.mts. for Building "C-I C-2" and Open Space for "C-l -C-2" Building is 230.00 sq. mtrs Area being developed by Mis Pride Ventures (1) Pvt Ltd 1. Following technical professionals are appointed by Owner I Promoter:- i) Mis Nitin Bagdiya & Associates as Architect ii) Mis Core Consultant (Prop. Rajesh Wargantwar) as Structural Consultant iii) Shri Santosh Uttamrao Throat as Site Supervisor 2. We have estimated the cost of the completion to obtain Occupation Certificate/ Completion Certificate, of the Civil, MEP and Allied works, of the Building(s) of the project. Our estimated cost calculations are. based on the Drawings/plans made available to us for the project under reference by the Developer and Consultants and the Schedule of items and quantity for the entire work as calculated by Shri Santosh Uttamrao Throat Site Supervisor appointed by Developer/Engineer, and the assumption of the cost of material, labor and other inputs made by developer, and the site inspection carried out by us. 3. We estimate Total Estimated Cost of completion of the building(s) of the aforesaid project under reference as Rs. 6,35,SO,000.00 (Total of Table A and B). The estimated Total Cost of project is with reference to the Civil, MEP and allied works required to be completed for the purpose of obtaining occupation certificate / completion certificate for the building(s) from the Aurangabad Municipal Corporation being the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost Incurred till date is calculated at Rs.68,41,070.00 (Total of Table A and B). The amount of Estimated Cost Incurred is calculated on the base of amount of Total Estimated Cost. S. The Balance cost of Completion-of-the Civil, MEP and Allied works of the Building(s) of the subject project to obtain Occupation Certificate / Completion Certificate from Aurangabad Municipal Corporation (planning Authority) is estimated at Rs.5,67,08,930.00 (Total of Table A and B). 6. I certify that the Cost of the Civil, MEP and allied work for the aforesaid Project as completed on the date of this certificate is as given in Table A and B below: SANJAV SITARAM NIMBALKAR N-5 E-04-02 GULMOHAR COLONY,CIDCO 10 ,AURANGABAD PAN- AKOPN2284M ,Mobile NO -9372233690 ---------------------------------------------------------------------------------- TABLE A Pride Phoenix Building "C-1 C-2" Sr. No Particulars Amounts 1 Total Estimated cost of the building PRIDE PHOENIX - C-1 C-2 as on Rs.. 6,35,50,000.00 30.06.2017 is 2 Cost incurred as on 30.06.2017 (based on the Estimated cost) Rs. 68,41,070.00 3 Work done in Percentage (as Percentage of the estimated cost) 10.76% ·..JLtVtli.ii,\ a', ..I; , 4 Balance Cost to be Incurred (Based on Estimated Cost) Rs.5,67,08,930.00 5 Cost Incurred on Additional/Extra Items not included in the NIL Estimated Cost (Annexure A) TABLE B (to be prepared for the entire registered phase of the Real Estate Project) Sr. Particulars Amounts No 1 Total Estimated cost of the Internal and External Nil Development Works including amenities and Facilities in the layout as on 30.06.2017 is 2 Cost incurred as on 30.06.2017(based on the Estimated cost) Nil 3 Work done in Percentage (as Percentage of the estimated cost) Nil 4 Balance Cost to be Incurred (Based on Estimated Cost) Nil 5 Cost Incurred on Additional/Extra Items not included in the Estimated Cost Nil (Annexure A) Yours Faithfully Signature of Engineer Annexure A SaAjay S. """Hlkar elY" EnCin~ List of Extra / Additional Items executed with Cost '" ~ (Which were not parts of the original Estimate of Total Cost) A-'" I ;.",~ NOT APPLICABL£BEINGCERTIFICATE'IS FOR ESTIMATED COST t/ ~~ ,