FORM-1 (Table A) Building// SRH 32 to 38-Plots PHASE 3 (tobe prepared separately for each Building/ Wing of the Project) Sr. Percentage of work Task /Activity done No 1 Excavation 0% 2 1number of Basement(s) and Plinth 0% 3 0 number of Podiums 0% 4 Stilt Floor 0% 0% 52 number of Slabs of Super Structure |Internal walls, Internal Plaster,Floorings with in 0% Flats/Premises,Doors and Windows to each of the Flat/Premises |Sanitary Fittings within the Flat / Premises, Electrical Fittings within 0% 7 the Flat /Premises Staircases. Lifts Wells and Lobbies at each Floor level connecting 0% 8 Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the 0% |Building/WNing Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of 0% 10 environment/ CRZNOC, Finishing to entrance lobby/s ,plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to |Obtain Occupation /Completion Certificate 0% 11 Cumulative Total % work done of building FORM-1 (Table A) Building No SRH 60 to 64 & 90 to 91-Plots PHASE 3 the Project) (tobe prepared separately for each Building/ Wing of Percentage of work Sr. Task /Activity done No 0% 1 Excavation 0% 2 1number of Basement(s) and Plinth 0% 3 0number of Podiums 0% 4 Stilt Floor 0% 5 2number of Slabs of Super Structure |Internal walls, Internal Plaster,Floorings with in Flat/Premises 0% |Flats/Premises, Doors and Windows to each of the Electrical Fittings within Sanitary Fittings within the Flat / Premises, 0% 7 the Flat/ Premises Staircases. Lifts Wells and Lobbies at each Floor levelconnecting 0% 8 Staircases and Lifts, Overhead and Underground Water Tanks The external plumbingand externalplaster, elevation, completion of terraces with waterproofing of the 0% BuildingWing |Installation of lifts, water pumps, Fire Fighting Fittings and Areas, Equipment as per CFONOC, Electrical fittings to Common of electro, mechanical equipment, Compliance to conditions 0% entrance lobby/s ,plinth 10 environment/ CRZNOC, Finishing to protection, paving of areas appurtenant to Building/Wing, Compound Walland allother requirements as may be required to Obtain Occupation /Completion Certificate 0% 11 Cumulative Total % work done of building From 1 Table - B Phase-3 Development Works in Respect ofthe entire Registered Internal &External -Phase 3 Nandurbar-Chhoriya Residency Project:- Proposed Percentage of Details Work done Facilities, Amenities (Yes/No) Common areas and No No Footpath 100 Yes &Foot paths Water pipe line 1 |Internal Roads Yes 100 2 Water Supply NOSTP Yes 100 (chamber, lines, Septic Tank, STP) 3 Sewerage NA No Drains 4 Storm Water In phase1 Yes 100 Planting 5 Land scaping &Tree 100 Street light Yes 6 Street Lighting In Phase 2 Yes 100 7 Community Buildings NA and sullage Treatment and disposal of sewage NG water NA No 9 Solid Waste management & Disposal NA No water harvesting 10 Water conservation ,Rain NA No 11 Energy management NA No safety requirements 12 Fire protection and fire Layout Electrification receiving 100 Electrical meter room, sub- station, Yes 13 station In Phase 1 Yes 100 recreational open space 14 |Aggregate area of 0 NA No 15 Open Parking In Phase 1 Yes 100 Compound Wall 16 Entrance Gate and Yours Faiti Kunal Patil Consulting Architect Agreed and Acceptsoy e Pune Signature of Promaet Name:Anmol K. ChhoRa k