FORM 1 ARCHITECT'S CERTIEICATE (To be submitted at the time of Quarterly Update Registered Project and for withdrawal of Money from Designated Account) Dec 2022 Date: 15.02.2023 To, The Dhariwal andChhoriya Developers LLP, Chhoriya Realty, Office No 401,4th Floor Adinath Shopping Center, Adinath Society, Pune Satara Road, Opp Hotel Panchami, Pune 411037. Subject: Certificate of Percentage of Completion of Infrastructural Development Work of R.M. Dhariwal Greens Phase 3 having MahaRERA Registration Number: P51000015553 being developed by Dhariwal and Chhoriya Developers LLP. Sir, IKunal Patil have undertaken assignment as Architect / Licensed Suveyor of certify in Percentage of Completion of Construction Work of R.M. Dhariwal Greens Phase 3 having MahaRERA Registration Number: P51000015553 being developed by Chhoriya Properties and Development Company. Based on Site Inspection, with respect to Layout / each of the Building / Wing of the aforesaid Real Estate Project, Icertify that as on the date of this certificate, the Percentage of Work done for each of the building / Wing of the Real Estate Project as registered Under MahaRERA is as per Table A herein below, The Percentage of the work executed with respect to each of the activity of the entire phase is detailed Table B. ONAL P NG A R C H From 1 Table - B Internal External & Development Works in Respect of the entire Registered Phase -3 Project:-R.M.Dhariwal Greens Phase 3 S. No Common areas and Facilities, ProposedPercentage of Amenities (Yes/No) Work done Details 1 Internal Roads &Foot paths Concrete Road- In Phase Yes 100 |Water Supply Yes 100 3 Sewerage (chamber, lines, Septic Tank, STP) Yes 100 STP. In Phase 1 4 Storm Water Drains Yes 100 Pit- In Phase 1 5 Land scaping &Tree Planting Yes 100 OS Garden- In Phase 1 6 Street Lighting Yes 100 Street light- In Phase 1 7 Community Buildings Yes 100 Yoga Hal- In Phase 1 8 Treatment and disposal of sewage and sullage Treatment and disposal |water Yes 100 In Phase 1 9 Solid Waste Vermiculture pit- In Phase management &Disposal Yes 100 1 10 Water conservation ,Rain water harvesting Yes 100 Pit- In Phase 1 11 Energy management Yes 100 Solar Light- In Phase 1 12 Fire protection and fire safety requirements No NA 13 Electrical meter room, sub- station, receiving Yes 100 Electrification- In Phase 1 station Cricket and Basket ball- In 14 Aggregate area of recreational open space Yes 100 Phase 1 15 Open Parking NA 16 Entrance Gate and Compound Wall Yes 100 Layout Ent- In Phase 1 CCTV Camera- In Phase 17 CCTV Camera for layout security Yes 100 1 Yours FaithruLP.P. PA ING ARCH KBanal Patil Consulting Architec Agreed and Accepted by, Signature of Promoter Name:Anmol K. Chhoriya