FORM 1 ARCHITECT'S CERTIFICATE (To be submitted at the time of Quarterly Update Registered Project and for withdrawal of Money from Designated Account) June 2023 Date: 15.07.2023 To, The Dhariwal and Chhoriya Developers LLP, Pune Satara Chhoriya Realty, Ofice No 401,4th Floor Adinath Shopping Center, Adinath Society, Road, Opp Hotel Panchami, Pune 411037. Development Work Subject: Certificate of Percentage of Completion of Infrastructural Registration Number: of R.M. Dhariwal Greens Phase 2 having MahaRERA P51000012173 being developed by Dhariwal and Chhoriya Developers LLP. Sir., certify in IKunal Patil have undetaken assignment as Architect / Licensed Surveyor of having Percentage of Completion of Construction Work of R.M. Dhariwal Greens Phase 2 MahaRERA Registration Number: P51000012173 being developed by Chhoriya Properties and Development Company. Based on Site Inspection, with respect to Layout / each of the Building / Wing of the aforesaid Real Estate Project, Icertify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered Under MahaRERA is as per Table A herein below, The Percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table A and Table B. FORM-1 (Table A) Building/ / RH 54 -59 PHASE 2 (to be prepared separately for each Building/ Wing of the Project) Sr. Percentage of work No Task /Activity done Excavation 100% 2 1 number of Basement(s) and Plinth 100% 3 0number of Podiums 0% 4 Stilt Floor 0% 5 2 number of Slabs of Super Structure 100% 6 Internal walls, Internal Plaster ,Floorings with in 100% Flats/Premises, Doors and Windows to each of the Flat/Premises |Sanitary Fittings within the Flat / Premises, Electrical Fittings within 100% 7 the Flat /Premises 8 Staircases, Lifts Wells and Lobbies at each Floor levelconnecting 100% Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, 9 elevation, completion of terraces with waterproofing of the 100% Building/Wing |Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of 10 environment/ CRZNOC, Finishing to entrance lobby/s ,plinth 70% protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to |Obtain Occupation/ Completion Certificate 11 Cumulative Total % work done of building 98% FORM-1 (Table A) Building RH 83-86 PHASE 2 (to be prepared separately for each Building/ Wing of the Project) Sr. Task /Activity Percentage of work No done 1 Excavation 0% 2 1number of Basement(s) and Plinth 0% 3 0 number of Podiums 0% 4 StiltFloor 0% 5 2 number of Slabs of Super Structure 0% 6 Internal walls, Internal Plaster ,Floorings with in 0% Flats/Premises, Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat /Premises, Electrical Fittings within 0% the Flat/Premises Staircases, Lifts Wells and Lobbies at each Floor level connecting 0% |Staircases and Lifts, Overhead and Underground Water Tanks The external plumbingand external plaster, 9 elevation, completion of terraces with waterproofing of the 0% Building/Wing Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of 10 environment/ CRZNOC, Finishing to entrance lobby/s ,plinth 0% protection, paving of areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to |Obtain Occupation / Completion Certificate 11 Cumulative Total %work done of building 0% FORM-1 (Table A) Building No 99-100 PHASE of the Project) (to be prepared separately for each Building/ Wing Percentage of work Sr. done Task lActivity No 0% 1Excavation 0% 2 1number of Basement(s) and Plinth 0% 3 0number of Podiums 0% 4 Stilt Floor 0% 52 number of Slabs of Super Structure Internal walls, Internal Plaster,Floorings with in 0% 6 Flat/Premises Flats/Premises, Doors and Windows to each of the Fittings within |Sanitary Fittings within the Flat / Premises, Electrical 0% 7 the Flat / Premises connecting Staircases, Lifts Wells and Lobbies at each Floor level 0% Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the 0% Building/MWing |Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of 0% 10 environment/ CRZNOC, Finishing to entrance lobby/s ,plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 11 Cumulative Total % work done of building FORM-1 (Table A) Building PB 101 PHASE 2 (to be prepared separately for each Building/ VWing of the Project) Percentage of work Sr. Task /Activity done No 100% 1 Excavation 100% 2 1 number of Basement(s) and Plinth 0% 3 0 number of Podiums 0% 4 Stilt Floor 0% 5 2 number of Slabs of Super Structure Internal walls, Internal Plaster,Floorings with in 0% 6 Flats/Premises,Doors and Windows to each of the Flat/Premises Fittings within 7 Sanitary Fittings within the Flat /Premises, Electrical 0% the Flat/Premises connecting Staircases, Lifts Wells and Lobbies at each Floor level 0% Tanks 8 Staircases and Lifts, Overhead and Underground Water The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the 0% Building/Wing |Installation of lifts, water pumps, Fire Fighting Fittings and Areas, Equipment as per CFONOC, Electrical fittings to Common of electro, mechanical equipment, Compliance to conditions 0% Finishing to entrance lobby/s ,plinth 10 environment/ CRZNOC, protection, paving of areas appurtenant to Building/Wing. required to Compound Wall and all other requirements as may be Obtain Occupation /Completion Certificate 16% 11 Cumulative Total % work done of building