FORM 1 ARCHITECT'S CERTIFICATE (To be submitted at the time of Quarterly Update Registered Project and for withdrawal of Money from Designated Account) Dec 2022 Date: 18.02.2023 To, The Dhariwaland Chhoriya Developers LLP Chhoriya Realty, Office No 401,4th Floor Adinath Shopping Center, Adinath Society, Pune Satara Road, Opp Hotel Panchami, Pune 411037. Subject: Certificate of Percentage of Completion of Infrastructural Development Work of R.M. Dhariwal Greens Phase 2 having MahaRERA Registration Number: P51000012173being developed by Dhariwal and Chhoriya Developers LLP. Sir, IKunal Patil have undertaken assignment as Architect / Licensed Surveyor of certify in Percentage of Completion of Construction Work of R.M. Dhariwal Greens Phase 2 having MahaRERA Registration Number: P51000012173 being developed by Chhoriya Properties and Development Company. Based on Site Inspection, with respect to Layout / each of the Building / Wing of the aforesaid Real Estate Project, Icertify that as on the date of this certificate, the Percentage of Work done for each of the building /Wing of the Real Estate Project as registered Under MahaRERA is as per Table A herein below, The Percentage of the work executed wth respect to each of the activity of the entire phase is detailed in Table A and Table B. .PA ARCY ING FORM-1 (Table A) Buildingl | RH 54 -59 PHASE2 (to be prepared separately for each Building/ Wing of the Project) Sr. No Task /Activity Percentage of work done 1 Excavation 100% 2 1number of Basement(s) and Plinth 100% 3 0 number of Podiums 0% 4 Stilt Floor 0% 5 2 number of Slabs of Super Structure 100% 6 |Internal walls, Internal Plaster ,Floorings with in Flats/Premises, Doors and Windows to each of the Flat/Premises 100% 7 Sanitary Fittings within the Flat / Premises, Electrical Fittings within |the Flat/Premises 100% 8 |Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks 100% The external plumbing and external plaster, 9 elevation, completion of terraces with waterproofing of the 100% Building/MWing |Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of 10 environment/ CRZNOC, Finishing to entrance lobby/s ,plinth 70% protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation / Completion Certificate 11 Cumulative Total % work done of building 98% FORM-1 (Table A) Building RH 83-86 PHASE2 (to be prepared separately for each Building/ Wing of the Project) Sr. No Task IActivity Percentage of work done 1 Excavation 0% 2 1number of Basement(s) and Plinth 0% 0 number of Podiums 0% 4 Stilt Floor 0% 5 2 number of Slabs of Super Structure 0% 6 |Internal walls, Internal Plaster,Floorings with in Flats/Premises, Doors and Windows to each of the Flat/Premises 0% 7 Sanitary Fittings within the Flat / Premises, Electrical Fittings within |the Flat /Premises 0% 8 |Staircases, Lifts Wells and Lobbies at each Floor level connecting |Staircases and Lifts, Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/MWing 0% |Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas, |electro, mechanical equipment, Compliance to conditions of 10 environment/ CRZNOC, Finishing to entrance lobby/s ,plinth 0% protection, paving of areas appurtenant to Building/Wing, Compound Walland all other requirements as may be required to Obtain Occupation /Completion Certificate 11 Cumulative Total % work done of building 0% FORM-1 (Table A) Building No 99-100 PHASE 2 (to be prepared separately for each Building Wing of the Project) Sr. Percentage of work No Task /Activity done 1 Excavation 0% 2 0% 1number of Basement(s) and Plinth 3 0number of Podiums 0% 4 Stilt Floor 0% 0% 52 number of Slabs of Super Structure 6 |Internal walls, Internal Plaster ,Floorings with in 0% Flats/Premises,Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat /Premises, Electrical Fittings within 0% the Flat/ Premises Staircases, Lifts Wells and Lobbies at each Floor level connecting 0% Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion of terraces with waterproofingof the 0% Building/Wing Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas. electro, mechanical equipment, Compliance to conditions of 10 environment/ CRZNOC, Finishing to entrance lobby/s ,plinth 0% protection, paving of areas appurtenant to Building/Wing, Compound Wall and allother requirements as may be required to Obtain Occupation / Completion Certificate 11 Cumulative Total %work done of building 0% FORM-1 (Table A) Building PB 101 PHASE 2 (to be prepared separately for each Building/ Wing of the Project) Sr. Percentage of work No Task /Activity done 1 100% |Excavation 1number of Basement(s) and Plinth 100% |0number of Podiums 0% Stilt Floor 0% 0% 52 number of Slabs of Super Structure 6 |Internal walls, Internal Plaster ,Floorings with in 0% |Flats/Premises,Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat / Premises, Electrical Fittings within 0% the Flat / Premises Staircases, Lifts Wells and Lobbies at each Floor level connecting 0% Staircases and Lifts, Overhead and Underground Water Tanks |The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the 0% Building/VWing Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFONOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of 0% 10 environment/ CRZNOC, Finishing to entrance lobby/s ,plinth protection, paving of areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 11 Cumulative Total % work done of building 16% From 1 Table - B Internal &External Development WNorks in Respect of the entire Project:- R.M.Dhariwal Greens Registered Phase -2 Phase 2 S. No Common areas and Facilities, Amenities Proposed Percentage of (Yes/No) Work done Details 1 |Internal Roads &Foot paths Yes 100 2 Water Supply Concrete Road Yes 100 3 Sewerage (chamber, lines, Septic Tank, STP) Yes 100 STP 4 Storm Water Drains 5 Land Yes 100 Pit scaping &Tree Planting Yes 100 OS Garden 6 Street Lighting Yes 100 Street light 7 Community Buildings Yes 100 Yoga Hall 8 |Treatment and disposal of sewage and sullage water Yes 100 Treatment and disposal 9 Solid Waste management &Disposal Yes 100 Vermicuture pit 10 Water conservation ,Rain water harvesting Yes 100 Pit 11 Energy management Yes 100 Solar Light 12 Fire protection and fire safety requirements No NA 13 Electrical meter room, sub- station, receiving |station Yes 100 Electrification 14 Aggregate area of recreational open space Yes 100 Cricket and Basket bal 15 Open Parking Yes 100 Open 16 Entrance Gate and Compound Wall Yes 100 Layout Ent 17 CCTVCamera for layout security Yes 100 CCTV Camera Yours Faithfully, RAL PP Kunal Patil Consulting Architect ING ARO Agreed and Accepted by, Signature of Promoter Name:Anmol K. Chhoriya