Annexure A FORM 1 [See Regulation 3] ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date: 16/12/2023 To, M/S G S FORT REALTORS, PATEL NAGAR, CHANDRAPUR CHANDRAPUR. Subject: Certificate of Percentage of Completion of Construction Work of “G S HEIGHTS” having MahaRERA Registration Number P50900035159 being Developed by M/S G S FORT REALTORS upto 30/09/2023. Sir, I have undertaken assignment as Architect Certifying 6 % Percentage of Completion of Construction Work of “G S HEIGHTS” having MahaRERA Registration Number P50900035159 being Developed by M/S G S FORT REALTORS. Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A Building G S HEIGHTS (to be prepared separately for each Layout/Building/Wing of Project) S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1. Excavation 100 2. Basements (if any) 25 3. Podiums (if any) NA 4. Plinth 100 5. Stilt Floor NA 6. Slab of Super Structure 0 7. Internal Walls, Internal Plaster, Floorings, Doors, windows 0 within Flats / Premises 8. Sanitary Fittings within Flats / Premises 0 9. Staircases, Lift Wells & Lobbies at each Floor Level Overhead 0 and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, Completion 0 of Terraces, with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and 0 Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number S. No. Common Areas & Facilities Proposed Percentage of actual Work Details (Yes / NO) Done (As on date of Certificate) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths NO 2. Water Supply YES 100% BORING 3. Sewerage (Chamber, Lines, Septic YES 0% No STP Tank, STP) 4. Strom Water Drains NA 5. Landscaping & Tree Planting NA 6. Street Lighting NA 7. Community Buildings 8. Treatment & Disposal of Sewage and NA Sullage Water 9. Solid Waste Management & Disposal NA 10. Water Conservation / Rain Water YES 0% Harvesting 11. Energy Management NA 12. Fire Protection & Fire Safety YES 0% requirements 13. Electrical Meter Room, Sub-Station, YES 0% Receiving Station 14. Others (Option to Add more) Yours faithfully, Arc Vikrant Bhute License Number (CA/2005/35533) Agreed & Accepted by: Signature of Promoter ( Partner- Gajanan Nilawar) M/S G S FORT REALTORS Date: 16/12/2023