FORM-2 [See Regulation 3] ENGINEER’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account- Project wise) Date : 25/10/2022 To, M/s PM Infraventures Shricon House, 25, Pragati Layout Rajeev Nagar, Wardha Road Nagpur – 440025 Subject: Certificate of Cost incurred for Development of Project of 906 EWS Houses for Construction of 51 building(s) /Wing(s) situated on the Plot bearing No. 35/1, 35/3, 55/3, 56(P) and 57(P) Survey no./Kh. No. 35/1, 35/3, 55/3, 56(P) and 57(P) of Mouza –Nanda, Tah.-Korpana, Dist.- Chandrapur (MS). having Maha RERA Registration Number P50900045831 being developed by PM Infraventures. Sir, 1. I/ We DHIRAJ JAGYASI have undertaken assignment of certifying Estimated Cost for the PROJECT of 906 EWS Houses for Construction of 51 building(s) /Wing(s) situated on the Plot bearing No. 35/1, 35/3, 55/3, 56(P) and 57(P) Survey no./Kh. No. 35/1, 35/3, 55/3, 56(P) and 57(P) of Mouza –Nanda, Tah.-Korpana, Dist.- Chandrapur (MS). having MAHA RERA Registration no P50900045831, being developed by PM Infraventures. 2. We have estimated the cost of Civil, MEP and Allied works, required for completion of Apartments and proportionate completion of internal and external works of the project as per specifications mentioned in agreement to sale. Our estimated cost of calculations are based on the Drawings/plans made available to us for the project under reference by the Developer / Consultants. The Schedule of items and quantity for the entire work as calculated by Mr. Jayant Mridha Quantity Surveyor* appointed by Developer/Engineer, and the assumption of the cost of material, labour and other inputs made by developer, and the site inspection carried out by us. 3. We estimate Total Estimated Cost of completion of the aforesaid project under reference as Rs. 5280.62 /-Lakhs (Total of Table A and B) at the time of Registration. The estimated Total Cost of project is with reference to the Civil, MEP and allied works required for completion of the apartments and proportionate completion of internal and external work as per specifications mentioned in agreement of sale and for the purpose of obtaining occupation certificate / completion certificate of buildings / Wings / Layout / Plotted development from the being planning authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost Incurred till date is calculated at Rs 856.80 Lacs (Total of Table A and B). The amount of Estimated Cost Incurred is calculated on the basis of input materials / services used and unit cost of these items. 5. The Balance cost of Completion of the Civil, MEP and Allied works of the completion of the apartments and proportionate completion of internal and external works, as per specification mentioned in agreement of sale, of the project is estimated at Rs. 4423.82 Lacs (Total of Table A and B). TABLE A 39 & 46 to 57 or called Building /Wing / Layout / Plotted development bearing Number Ito development of the Real (to be prepared separately for each Building /Wing / Layout / Plotted Estate Project) Amount in Rs Lacs SNo Perticulars 3 (1 (2) Rs. 4645.99/. 1 Total Estimated cost of the building/wing as on date of Registration is Rs, 667 95 /. 2 Cost incurred as on date of certificate 14.38 % Work done in Percentage (as Percentage of the estimated cost) Rs. 3978.04/ Balance Cost to be Incurred * (Based on Estimated Cost) Rs. 0 /-. Cost Incurred on Additional /Extra Items TABLE B registered phase) (Internal and External development works in respect of the Amount in Rs Lacs Perticulars SNo 3) (2) Rs. 634.63/ (1) Development Works 1 Total Estimated cost of the Internal and External on date of including amenities and Facilities in the layout as Registration is Rs. 188.85 / Cost incurred as on date of certificate 29.76 % the estimated cost) Work done in Percentage (as Percentage of Estimated Cost) Rs. 445.78 / Balance Cost to be Incurred * (Based on Rs. 0 - Items not included in the 5 Cost Incurred on Additional /Extra Estimated Cost (Table C) ERED ENGINEEER Yours Faithfully, M-167181-7 stamphgineer. Signature and Name in BLOCK LeMer with Dhiraj Jagyasi (License No M-1671817.) mnONO Agreed and AcceptedAVE Signatute of Proinp Name :- Purnima SHP Date : 25/10/2022 * Note: 1. The scope of work is to complete registered Real Estate Project as per drawings approved from time to time and as per specification mentioned in agreement of sale. 2. (*) Quantity survey can be done by office of Engineer or can be done by an independent Quantity Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) and in case quantity are being calculated by office of Engineer, the name of the person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). 3. (**) Balance cost to be incurred (4) may vary from difference between total estimated cost (1) and actual cost incurred (2) due to deviation in quantity required / escalation of cost etc., as this is an estimated cost, any deviation in quantity required for development of the Real Estate Project will result in amendment of the cost incurred / to be incurred. 4. All components of work with specifications are indicative and not exhaustive. 5. Please specify if there are any deviation / qualifications. Example: Any deviation in input material used from specification in agreement of sale. TABLE C List of Extra/Additional/Deleted Items considered in Cost (which were not part of the original Estimate of Total Cost) S.No. List of Extra / Additional / Amount in Rs Lacs Deleted items Nil Nil