B.R.PIPARHETE Consulting Architect & Civil Engineer. A WING 202, RAJAT SANKUL NEAR GANESHPETH BUS STOP NAGPUR- 440012. E-mail:-bhushanpip2023@gmail.com ref. Date :30/09/2025 Annexure A FORM 1 [See Regulation 3] ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) To, WAINGANGA LIFECITY MR. SHRIHARI JIYALAL CHAUDHARI. Tah.- Nagpur (Urban),Dist. Nagpur. Pin: 440025. Subject: Certificate of Percentage of Completion of Construction Work of WAINGANGA LIFECITY having MahaRERA Registration Number P50500079312 being Developed by Mr. Shrihari Jiyalal Chaudhari. Sir, I / We B.R.PIPARHETE have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of WAINGANGA LIFECITY having MahaRERA Registration Number P50500079312 being Developed by Mr. Shrihari Jiyalal Chaudhari. Based on the Site Inspection, with respect to the Layout / each Building/Wing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the Building/Wing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE-A Layout / Building / Wing Number __ (to be prepared separately for each Layout/Building/Wing of Project) S. Tasks / Activity Percentage of Actual Work No. Done (As on) (1) (2) (3) 1. Excavation NA 2. Basements (if any) NA 3. Podiums (if any) NA 4. Plinth NA 5. Stilt Floor NA 6. Slab of Super Structure NA 7. Internal Walls, Internal Plaster, Floorings, Doors, NA windows within Flats / Premises 8. Sanitary Fittings within Flats / Premises NA 9. Staircases, Lift Wells & Lobbies at each Floor Level NA Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, NA Completion of Terraces, with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings NA and Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number S. Common Areas & Facilities Proposed Percentage of actual Details No. (Yes / Work Done NO) (As on 30-09-2025) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths Yes 50% 2. Water Supply Yes 70% 3. Sewerage (Chamber, Lines, Septic Yes 70% Tank, STP) 4. Strom Water Drains Yes 70% 5. Landscaping & Tree Planting Yes NIL 6. Street Lighting Yes NIL 7. Community Buildings No 8. Treatment & Disposal of Sewage Yes NIL and Sullage Water 9. Solid Waste Management & Yes NIL Disposal 10. Water Conservation / Rain Water Yes 60% Harvesting 11. Energy Management No 12. Fire Protection & Fire Safety No requirements 13. Electrical Meter Room, Sub- Yes NIL Station, Receiving Station 14. Aggregate area of Recreational Yes 60% open Space Yours faithfully, Signature & Name (IN BLOCK LETTERS) of Land Surveyor / Architect License Number (____________________) Bhushan Digitally signed by Bhushan Agreed & Accepted by: Rajesh Rajesh Piparhete Date: 2026.01.17 WAINGANGA LIFECITY Signature of Promoter Piparhete 16:46:27 +05'30' Name: Mr. Shrihari Jiyalal Chaudhari. Date: