PAWAN RAVIPRASAD GUPTA CONSULTING CIVIL ENGINEER PIANNERS, EUILDERS AND DEVELOPERS LICENCE. NO NIT 1964. N MO-330, NM RDA-34. (OFF SHOP N0 115 SECOND ELOOR SHRI SHYAM TOWER SADAR NAGPUR. 440001 M 9923432949 DATE: - 31-03-2026 ARCHITECT'S CERTIFICATE To MIS ARA BUILDCON Partnership firm through Authorized partner SHRI. ATUL PREMCHAND TAJPURIYA N-103, 104, Laxmivihar Apartment, Wardha Road, Somalwada, Nagpur-440025. Subject: Certificate of Percentage of Completion of Development Work of the M/s. ARA BUILDCON [Mahalaxmi Nagar- 42] Ph. No. 42, KH. NO.- 238/2, Mouza - Jamtha, Tahsil-Nagpur (Rural) and District-Nagpur having [Maha RERA Registration Number P50500079059] being developed by [M/s. ARA BUILDCONJ (For Quarter January - March 2026) Sir, / We Pawan R. Gupta have undertaken assignment as Architect ILicensed Surveyor of certifying Percentage of Completion of Development Work of M/s. ARA BUILDCON having Maha RERA Registration Number P50500079059 being developed by [M/s ARA BUILDCONI Based on Site Inspection, with respect to the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for the entire Real Estate Project as each as registered vide number P50500079059 under Maha RERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. PawanRaviprasad Gupta B.E.(CIVIL) PLANNERSs, BUILDEAS AND DEVELOPERS Iic. No.:T.1989, N. M.R.D.A. 39, N.MC. 380 Uh.: Shop No. 115 Second Floor, Shriram Shyam Towor, Sadar, Nagpur440001. E-mail lD: pawan r_gupta @yahc0.co. in MOB. No. 9923432949 Table A Building NWing Number (to be prepared separately for each Building Wing of the Project) Sr. Tasks IActivity Percentage of No work done 1 Excavation Not Applicable 2 number of Basement(s) and Plinth Not Applicable 3 number of Podiums Not Applicable 4 Stilt Floor Not Applicable 5 Plinth Not Applicable 6 number of Slabs of Super Structure Not Applicable 7 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors Not Applicable and Windows to each of the Flat/Premises 8 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Not Applicable Flat/Premises 9 Staircases, Lifts Wells and Lobbies at each Floor level connecting Not Applicable Staircases and Lifts, Overhead and Underground Water Tanks 10 The external plumbing and external plaster, elevation, completion of Not Applicable terraces with waterproofing of the Building/Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as Not Applicable per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate NOTE. Table -A is not applicable to this project as it is a project of plotted development (layout of plots) and not construction of building. Parwan Ra viprasad Gupia BE(CIVIL) PLANNERS, BUILDERS AND DEVELOPERS lic. No..T.1C39, NMR.DA. 39, N.M.C. 330 U.: Shop No. 115 Second Floor, Shiram Shyam Tower, Sadar, Nagpur-440001. E-mail lD: pawan gupta O yaho0.co. in MOB No. 9923432949 TABLE-B Internal & External Development Works in Respect of the entire Registered Phase Sr Common areas and Facilities. Proposed Percentage Details No. Amenities (Yes/No) of Work done 1 Internal Roads & Footpaths YES 90% Ongoing 2 Water Pipeline YES 100% Completed 3 Sewerage (chamber, lines, Septic YES 100% Completed Tank, STP) 4 Storm Water Drains YES 100% 5. Completed Landscaping & Tree Planting YES 90% 6 Street Lighting Ongoing YES 95% Ongoing 7 Community Buildings 8 Treatment and disposal of sewage NO and sullage water 9. Solid Waste management & Disposal NO 10. Water conservation, Rain water YES 100% Completed harvesting 11. Energy management NO 12. Fire protection and fire safety NO requirements 13. Electrical meter room, sub-station, NO receiving station 14. Others (Open space) YES 95% Ongoing NOTE- Entire development work in the project is ongoing as per specifications given by NMRDA (Nagpur Metropolitan Regional Development Authority) Yours Faithfully Agreed and accepted by: Powan B.E(CIVIL) Raviprasad Grpia PLANNERS, BUILDERS AND DEVELOPERS 'ir. No.JT.1039, M.IA.R.D.A. 39, N.M.C. 300 Un: Shop No. 115 Second Floor, Shriram Shyam Tower, Sadar, Nagpur-440001. E-mail ID:pawan_r gupta@yaho0.co.in MOB. No. 9923432949 Signature of Rromoter